Thompson-Arthur Paving Co. v. Lincoln Battleground Associates, Ltd.

382 S.E.2d 817, 95 N.C. App. 270, 1989 N.C. App. LEXIS 771
CourtCourt of Appeals of North Carolina
DecidedSeptember 5, 1989
Docket8818SC1019
StatusPublished
Cited by16 cases

This text of 382 S.E.2d 817 (Thompson-Arthur Paving Co. v. Lincoln Battleground Associates, Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thompson-Arthur Paving Co. v. Lincoln Battleground Associates, Ltd., 382 S.E.2d 817, 95 N.C. App. 270, 1989 N.C. App. LEXIS 771 (N.C. Ct. App. 1989).

Opinion

COZORT, Judge.

This appeal follows a jury verdict and entry of judgment in favor of plaintiff on plaintiff’s claim for breach of contract. The jury found that a settlement agreement entered into by the parties was subject to rescission because of mistake. The jury then rejected both parties’ express contract theories and awarded damages based on an implied in fact contract theory of recovery. We uphold judgment for plaintiff but remand for an additional award of interest.

The evidence at trial was as follows: On or about 5 November 1985, plaintiff submitted a Proposal and Contract Form to Lincoln Contractors, Inc. (“Lincoln”), agent for defendants, for curb, gutter, and paving work to be done by plaintiff for an apartment complex being constructed by defendants. The Proposal provided that the curb, gutter, and paving work needed for the job, in the quantities estimated in the Proposal, would cost $232,221.72. Below the typewrit *273 ten list of paving materials (including stone), curb, and gutter (and the cost for each per square yard or lineal foot), were the following clauses (also typewritten): “Extra Stone, if needed @ $9.00 per ton,” and “Job to be measured upon completion to determine final quantities and monies due.” At the bottom of the Proposal was the following pre-printed language:

Unless a lump sum price is to be paid for the foregoing work and is clearly so stated it is understood and agreed that the quantities referred to above are estimates only and that payment shall be made at the stated unit prices on the actual quantities of work performed by the Company. Billings to be in accordance with paragraph 2 on reverse side.

Paragraph 2 provided that “Invoices shall be rendered monthly for all work performed under this agreement during any month . . . .”

After receiving plaintiff’s Proposal, Lincoln prepared three Purchase Orders and Contracts for Construction Work, which divided the work to be done by plaintiff into three separate contracts: off-site curb, gutter, and paving; on-site curb and gutter; and on-site paving. Each of the Purchase Orders had the words “Lump Sum” typed in the “quantity” column, and “Total Contract Amount Not to Exceed” next to the dollar figure. Each Contract for Construction Work contained a provision that “deviations” from plans and specifications without written authority were at Thompson-Arthur’s risk. Each contract further provided that 10°/o of each interim billing for work performed by plaintiff would be retained and that the amount retained would be paid to plaintiff thirty days after completion of the job.

Lincoln sent plaintiff three packets. Each packet contained, stapled together, one of Lincoln’s Purchase Orders and Contracts and a copy of plaintiff’s Proposal.

In December 1985, plaintiff’s representatives met with Lincoln’s job superintendents to discuss scheduling. According to testimony, the work normally would be scheduled to allow the curb and gutter to be installed first to provide confinement for the stone, which was the base for the asphalt. Lincoln, however, did not want to delay its access to the project during the winter months. Therefore, Lincoln’s superintendent requested that the stone be put down immediately for use by construction traffic, despite *274 plaintiff’s warning that, if the stone was laid down first and pushed into or off the roadbed, plaintiff would have to replace it. Plaintiff requested that Lincoln’s instructions be put in writing, but Lincoln’s superintendent said a letter was unnecessary because of the “extra stone at $9.00 a ton” language in their contract. The superintendent also stated that he did not want copies of “stone tickets,” or receipts from the quarry, but that they would “settle it up” when the job was finished.

The stone was laid down, as requested by Lincoln, prior to the installation of curb and gutter. No written authorization for extra stone was issued. During the project, plaintiff sent Lincoln monthly invoices from March through September. The invoices showed paving and curb and gutter work, expressed in square yards or lineal feet, which was completed during the billing period. According to defendants, prior to the final invoicing in September, the invoices did not specify that there were charges for extra stone. Nor did plaintiff advise Lincoln of the quantities of extra stone used. In September of 1986, after making on-site measurements, plaintiff submitted to defendants a billing for 3,101.58 tons of extra stone, an amount confirmed by stone tickets also sent to defendants. The total charge for the extra work was $29,376.05.

Contending that they had a “lump sum” contract, Lincoln refused to pay for the extras. Plaintiff filed a Notice of Claim of Lien for $29,376.05. At the time, Lincoln also held approximately $22,000.00 in retained funds. The amount retained was not reflected in the Claim of Lien, and, during conversations about the amount in dispute for the extra work, neither party mentioned the re-tainage. In March of 1987 the parties met to discuss settling their dispute. At that meeting, counsel for defendants wrote “$29,000.00” on a piece of paper and asked if that was approximately the amount in dispute. Plaintiff’s lawyer, who was unaware of the retainage, said “yes.” Counsel for defendants then asked how much plaintiff wanted in settlement. Having been informed by plaintiff that no other amounts were due, plaintiff’s lawyer made an offer to settle for $20,000.00, which defendant accepted. The parties thereafter entered into a Settlement Agreement releasing each party “of any and all claims” under their contract in consideration of the $20,000.00. The following day, plaintiff discovered that the retainage had not been paid and informed Lincoln that it did not consider the $20,000.00 settlement to include the retainage. Lincoln expressed its contrary view, whereupon plaintiff returned the check for $20,000.00. Lincoln *275 refused to accept the check and returned it to plaintiff. The un-cashed check was placed in evidence at trial.

The following issues were submitted to the jury and were answered as indicated: (The court’s road map instructions are in capitals, as they were on the verdict sheet.)

Issue One (a)
1(a). At the meeting on March 6,1987, was Thompson-Arthur’s vice president, Steve Arthur, mistaken regarding the total amount Thompson-Arthur claimed due from Lincoln on the Lincoln Green II project?
Answer: Yes
If YOU ANSWER ISSUE NUMBER ONE(A) “YES,” CONSIDER ISSUE Number One(B).
If YOU ANSWER ISSUE NUMBER ONE(A) “NO,” RETURN TO THE COURTROOM.
Issue One (b)
1(b). If so, did Lincoln’s agents have reason to know of Thompson-Arthur’s mistake?
Answer: Yes
If you answer Issue Number One(B) “yes,” consider Issue Number One(C)
If you answer Issue Number One(B) “no,” return to the courtroom.
Issue One (c):
1(c).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lannan v. Bd. of Governors of the Univ. of N.C.
Court of Appeals of North Carolina, 2022
Teague & Glover, P.A. v. Kane & Silverman, P.C.
822 S.E.2d 788 (Court of Appeals of North Carolina, 2019)
Bowles Automotive, Inc. v. North Carolina Division of Motor Vehicles
690 S.E.2d 728 (Court of Appeals of North Carolina, 2010)
North Carolina Industrial Capital, LLC v. Clayton
649 S.E.2d 14 (Court of Appeals of North Carolina, 2007)
Sanders v. State Personnel Commission
644 S.E.2d 10 (Court of Appeals of North Carolina, 2007)
Roberts v. Century Contractors, Inc.
592 S.E.2d 215 (Court of Appeals of North Carolina, 2004)
Phillips v. Warren
568 S.E.2d 230 (Court of Appeals of North Carolina, 2002)
Furr v. Fonville Morisey Realty, Inc.
503 S.E.2d 401 (Court of Appeals of North Carolina, 1998)
Members Interior Construction, Inc. v. Leader Construction Co.
476 S.E.2d 399 (Court of Appeals of North Carolina, 1996)
State ex rel. Motorists Mutual Insurance v. Broadwater
453 S.E.2d 591 (West Virginia Supreme Court, 1994)
Smith v. Childs
437 S.E.2d 500 (Court of Appeals of North Carolina, 1993)
Routh v. Snap-On Tools Corp.
423 S.E.2d 791 (Court of Appeals of North Carolina, 1992)
Bushkin Associates, Inc. v. Raytheon Company
906 F.2d 11 (First Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
382 S.E.2d 817, 95 N.C. App. 270, 1989 N.C. App. LEXIS 771, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thompson-arthur-paving-co-v-lincoln-battleground-associates-ltd-ncctapp-1989.