Thomas W. Finucane Co. v. Board of Education

82 N.E. 737, 190 N.Y. 76, 28 Bedell 76, 1907 N.Y. LEXIS 1354
CourtNew York Court of Appeals
DecidedNovember 19, 1907
StatusPublished
Cited by15 cases

This text of 82 N.E. 737 (Thomas W. Finucane Co. v. Board of Education) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas W. Finucane Co. v. Board of Education, 82 N.E. 737, 190 N.Y. 76, 28 Bedell 76, 1907 N.Y. LEXIS 1354 (N.Y. 1907).

Opinion

Chase, J.

The plaintiff entered into a contract with the defendant to erect the “East High School” in the city of Rochester, not including excavations and foundations therefor. After (as claimed by the plaintiff) the contract had been performed and the building completed a controversy arose between the parties as to the amount to be paid to the plaintiff in settlement of its demands. The plaintiff brought this action alleging a balance due it of $18,500 on the stipulated contract price ; $3,072.74 for certain alterations in the work and $30,739 damages under paragraph 18 of the contract, which we will herein further mention.

The defendant, answering the plaintiff’s complaint, denied many of the material allegations thereof, and interposed various counterclaims. The issues were referred to a referee, and he made findings of fact and conclusions of law upon which he directed judgment in favor of the plaintiff for $25,099.38 and judgment was entered thereon accordingly. The plaintiff appealed therefrom to the Appellate Division of .the Supreme Court where the judgment was modified by adding a small amount in accordance with a stipulation of the respondent and as so modified the judgment was unanimously affirmed. An appeal is taken to this court, but only questions of law can be considered.

The tenth finding of fact is as follows:

“ That the specifications required that all finished floors should be thoroughly kiln dried and taken from the kiln directly to the machine and then direct to the building, and only as fast as wanted for laying; that at the request of the plaintiff this provision of the specifications was waived so as to allow the plaintiff to have the flooring kiln dried in the southern states where it was purchased and put through the planing and matching machine there before being shipped here for use, and that on account of such change the expense *80 to the plaintiff of such floors was reduced by $7.00 per thousand feet and 101,000 feet of flooring was used in said building and that the defendant is entitled to a counterclaim against the plaintiff or to a deduction from the contract price of $707.00 on this account with interest thereon from June 1st, 1903, to this date which amounts to $66.34.”

The facts stated in such finding are wholly insufficient to sustain the conclusion of law therein. The other findings negative any claim that the plaintiff failed to perform its contract so far as it relates to the- floors. The counterclaim is not based upon findings that the floors were not of the material required by the specifications or that they were not planed, matched, kiln dried, laid and finished as therein provided.

The fact that the specifications, so far as they relate to the place where the flooring should be' kiln dried, were waived by the defendant, and that the plaintiff was allowed to have the material kiln dried in the southern states where it was purchased, is not sufficient on which to charge the plaintiff with the amount saved by it through procuring a lower price for the kiln dried flooring in such southern states. The intention of the plaintiff in requesting the defendant to waive the provision of the specifications in regard to the place where the flooring should be kiln dried was doubtless for the express purpose of enabling it to make a better bargain for itself in purchasing such kiln dried flooring. The consent to have the flooring kiln dried in the southern states was unconditional. If, at the time the flooring was laid, it was kiln dried as contemplated by the specifications, and the completed floors are in all respects according to the specifications, there is not in the findings any basis for the counterclaim against the plaintiff.

If the defendant claimed that the flooring absorbed moisture in being transferred to the school building, or in any other way the flooring became or was injured, or that the completed floors were inferior to the floors required by the specifications, it should have shown such injuries or inferiority upon the trial and obtained a finding to that effect by the referee.

*81 The eighteenth paragraph of the complaint is as follows: “Whatever damage or expense the contractor may suffer or be put to by reason of the owners not delivering the building on August 1st, shall be considered and paid for by the owner as an extra, and the character, amount and valuation of such extra shall be audited by the architect- In case such character, amount or valuation is not agreed to, the same shall be referred to three arbitrators to be appointed as follows : one by each of the parties to this contract and the third by the two thus chosen, and the decision of any two of such arbitrators shall be final and conclusive, and each of the parties shall pay one-half of the expense of such arbitration * * * ” The purpose of that paragraph of the contract is apparent. The other parts of the contract assume that the foundations for the building will be completed by August 1st, 1901, and that the plaintiff will pn that day have complete possession thereof under its contract. It provides that the plaintiff shall advance its work to certain points of completion by specified days and that the building shall be wholly completed by August 1, 1902. The contract also contained a provision as follows: “Said contractor shall and will proceed with said work and every part and detail thereof in a prompt and diligent manner, and shall and will wholly finish said work according to said drawings and specifications, and in default thereof said contractor shall pay to the owner ten dollars for every day thereafter that said work shall remain unfinished as and for liquidated damages.”

The contract was not actually signed by the parties until August 2, 1901, and the foundations were not then completed and could not be completed for some period of time thereafter. They were not completed and ready for the plaintiff until October 10, 1901. Paragraph 18 of the contract was made necessary by reason of the delay in such foundation work.

When the plaintiff’s president was being examined his attention was called to paragraphs 6 and 18 of the contract and lie testified that at the time the contract was executed he *82 had some conversation with the president of the defendant. The record then shows the following tpiestion, objection, ruling and statements :

“ Q. Will yon state to us what that conversation was ?
[Objected to as incompetent, irrelevant and immaterial. The contract is the best evidence of its terms and any conversation would be incompetent and immaterial if he intended to controvert or change the terms of the written contract, and if it was not intended for some such effect it would be immaterial and irrelevant.]
“Mr. O’Grady : Clause 6 of the contract seems to be without any ambiguity, but nevertheless the learned counsel and myself differ very materially as to the interpretation of it apparently from my statement of what I think it means and from what he has already stated he thinks it means and, therefore, I offer this testimony for the purpose of simply clarifying that section showing the meaning of it.
“Mi.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seidman v. Ungar
246 A.D.2d 641 (Appellate Division of the Supreme Court of New York, 1998)
In re Bayer Cadillac, Inc.
164 B.R. 450 (E.D. New York, 1994)
Avon Products, Inc. v. Solow
79 A.D.2d 53 (Appellate Division of the Supreme Court of New York, 1981)
American Reserve Insurance v. China Insurance
79 N.E.2d 425 (New York Court of Appeals, 1948)
Clark v. American Morgan Co.
268 A.D. 209 (Appellate Division of the Supreme Court of New York, 1944)
Bulk Carriers Corp. v. Kasmu Laeva Omanikud
43 F. Supp. 761 (S.D. New York, 1942)
Park Construction Co. v. Independent School District No. 32
296 N.W. 475 (Supreme Court of Minnesota, 1941)
Hochstim v. Grossman
258 A.D. 445 (Appellate Division of the Supreme Court of New York, 1940)
Beatty v. Employers' Liability Assurance Corp.
168 A. 919 (Supreme Court of Vermont, 1933)
Red Cross Line v. Atlantic Fruit Co.
264 U.S. 109 (Supreme Court, 1924)
Ames Canning Co. v. Dexter Seed Co.
195 Iowa 1285 (Supreme Court of Iowa, 1922)
Matter of Berkovitz v. . Arbib Houlberg
130 N.E. 288 (New York Court of Appeals, 1921)
Matter of City of New York (Main St.)
110 N.E. 176 (New York Court of Appeals, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
82 N.E. 737, 190 N.Y. 76, 28 Bedell 76, 1907 N.Y. LEXIS 1354, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-w-finucane-co-v-board-of-education-ny-1907.