Thomas v. United States

53 Ct. Cl. 430, 1918 U.S. Ct. Cl. LEXIS 118, 1918 WL 1009
CourtUnited States Court of Claims
DecidedApril 29, 1918
DocketNo. 32548
StatusPublished

This text of 53 Ct. Cl. 430 (Thomas v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas v. United States, 53 Ct. Cl. 430, 1918 U.S. Ct. Cl. LEXIS 118, 1918 WL 1009 (cc 1918).

Opinion

DowNey, Judge,

delivered the opinion of the court:

After the cancellation of the contract and supplemental contracts which had been entered into between the United States and the Atlantic, Gulf and Pacific Company for the construction of a dry dock at the Philadelphia Navy Yard a contract was made with The G. M. Scofield Company for the completion of the dock in accordance with the contracts of the Atlantic, Gulf and Pacific Company, and certain supplemental contracts with said Scofield Company were also entered into.

The Scofield Company performed the major part of its contracts by the completion of the dock proper and the installation of most of the machinery, but before it had finally completed its work it became embarrassed financially, went into bankruptcy, and soon thereafter, when satisfactory progress was not being made in the completion of the dock and its appurtenances, its contract was canceled, and the dock, together with all the materials, supplies, and machinery on hand, was taken over by the United States, and through- the [439]*439Bureau of Yards and Docks they proceeded with the completion of the dock at the expense of the contractor.

There were retained percentages in a considerable amount due the contracting company, and when the work had been finally completed by the United States it rendered a statement in which it charged against the retained percentages quite a number of items of expense alleged to have been incurred in the completion of the work. With reference to many of these charges the plaintiff makes no question. As to seven items plaintiff contends that the charges were improperly made and seeks recovery. Those seven items are as follows:

2. Placing the filling required by contract_$1, 577. 58
U; Three main engines_ 58,775.42
13. Repairing stokers_ 215.28
14. Providing anchor bolts for foundation of engine_ 96.16
15. Providing and installing gauges, etc_ 162. 80
19. Substituting larger and approved engine in caisson_ 2,182. 50
27. Maintaining dry dock and appurtenances_ 4, 917. 95

In addition to these the plaintiff seeks recovery also for the charge made against it of $2,851.20 on account of gravel theretofore paid for, $2,628.31 on account of redredging not paid for, and the balance of $11,365.43 shown by the final accounting to be due and unpaid.

The findings as to some of these items so speak for themselves that but little, if any, discussion is necessary.

With reference to the deduction of $1,577.58 as to alleged cost of completing the fill which the contractors were obligated to make, it clearly appears that this fill was not made because of the failure of the United States through its separate contractor to complete the sea wall which was to retain a part of the fill and without which the fill could not be completed. The contractors, in order that they might perform their contract in this respect as fully as might be, constructed at an expense of $250 a temporary dike inside of the line of the proposed sea wall to hold the fill, and when they had filled to- the required height against that dike it is plainly apparent that they had done all which, under the circumstances, they could do. The contractor for the construction of the sea wall so delayed his work that it was not completed until approximately a year and a half after the ex[440]*440piration of the contract period, and not until after the Scofield Company had become involved financially, had gone into bankruptcy, and their contract had been canceled. It is found, by deduction, that it would have cost that company $740.38 to complete the fill had the sea wall been in place. A statement of the facts seems to be all that is necessary to justify the conclusion that there should be a recovery of the excess charge of $837.20 and also of the $250 expended in the construction of the dike erected to facilitate the progress of the work and made necessary by the absence of the sea wall.

The next item is much the largest of all the contested items and gives room for more of controversy. The record is replete with correspondence, expressions of opinion, reports of tests and various matters of that sort from which we have drawn conclusions, but which we have not found it necessary to incorporate in detail in the findings.

It appears to our entire satisfaction that when the contract was made for this dry dock, which carried with it detailed specifications and among them the'specifications for two engines by which the dock was to be operated, it was then intended that these engines should perform solely the work necessary in connection with the operation of the dock; that is, so far as they were concerned, its pumping. The record bears evidence of some uncertainty in the minds of those in authority as to exactly what was desired to be accomplished at the Philadelphia Navy Yard. When the contractor first informed the Chief of the Bureau of Yards and Docks of the awarding of the contract to the Great Lakes Engineering Works for the two engines required they were informed that changes in the power plant were under consideration. They were afterwards notified that it had been determined not to make changes but to abide by the provisions of the original contract. Again, later on, the matter of the changes presented itself. A board was appointed to investigate and recommend, and changes were determined, upon. The change, so far as engines are concerned, excepting some matters of minor detail, consisted in the addition to the power plant of one more engine, specifically of Great Lakes Engineering Works’ manufacture, and of the type [441]*441called for by the original contract, and already under contract as between the Scofield Company and the Great Lakes Engineering Works.

It is quite apparent that this change in power plant was for the purpose of accomplishing something more than that for which it had been originally designed and intended; that is, the installation of a centralized power plant which, in addition to the pumping of the dock, should perform the added functions of furnishing heat, light, and power for the whole yard; and, in this connection, we are also impressed with the idea that when these engines were being subjected to official tests there was always present in the minds of those making these tests the idea, not simply that they were engines to be used for the purpose for which originally intended, but that they were to constitute a power plant for other and different purposes. To the nonexpert it also appears entirely possible that an official test might demonstrate satisfactory efficiency in an engine designed to pump a dock and not demonstrate the same degree of satisfactory efficiency in three engines necessary to be used in parallel and for entirely different purposes. But if it be possible that any of the difficulties encountered in connection with the satisfactory operation of these engines was due to the fact that they were not of a suitable type for the performance of a service other than that for which they were originally intended, it would seem that, so far as the type of engine is concerned, the defendant had foreclosed itself when it specifically, by supplemental contract, provided for the addition of a Great Lakes engine of the same type as those already under contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
53 Ct. Cl. 430, 1918 U.S. Ct. Cl. LEXIS 118, 1918 WL 1009, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-v-united-states-cc-1918.