Thomas v. South Haven & Eastern Railroad

100 N.W. 1009, 138 Mich. 50, 1904 Mich. LEXIS 780
CourtMichigan Supreme Court
DecidedOctober 18, 1904
DocketDocket No. 2
StatusPublished
Cited by2 cases

This text of 100 N.W. 1009 (Thomas v. South Haven & Eastern Railroad) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas v. South Haven & Eastern Railroad, 100 N.W. 1009, 138 Mich. 50, 1904 Mich. LEXIS 780 (Mich. 1904).

Opinion

Carpenter, J.

Plaintiff recovered a verdict and judgment in the court below for the nonperformance by defendant of its alleged contract to construct a side track alongside of plaintiff’s warehouse. Plaintiff’s testimony tended to prove that defendant, acting through its general manager, verbally agreed to construct the side track in question if plaintiff would move to a piece of land near its track, owned by him, a large building situated remote therefrom, and repair and remodel the same so as to make it suitable for a warehouse; that he at once removed, repaired, and remodeled the building; and that defendant refused to construct the side track as agreed. Defendant denied the making of this agreement. The issue was submitted to a jury, who, as above stated, rendered a verdict in plaintiff’s favor.

We are asked to reverse this judgment on the ground that, according to plaintiff’s testimony, there was no consideration for the alleged contract. This point is not well taken. The expense incurred by the plaintiff in removing, repairing, and remodeling the building was the consideration, and it was a sufficient consideration. See Sanford v. Huxford, 32 Mich. 313; Stevens v. Corbitt, 33 Mich. 458; People v. Taylor, 2 Mich. 253.

In announcing this conclusion, we overrule defendant’s contention that this consideration was insufficient because plaintiff did not, at the time of defendant’s promise, agree to remove, repair, and remodel the building.

“It is not necessary that the consideration should exist at the time of making the promise, for, if the person to whom the promise is made should incur any loss, expense, or liability in consequence of the promise, and relying upon it, the promise thereupon becomes obligatory. Thus if A. promises B. to pay him a sum of money if he will do a particular act, and B. does the act, the promise thereupon becomes binding, although B. at the time of the promise does not engage to do the act.” People v. Taylor, supra.

See, also, Stevens v. Corbitt, supra.

The contract in suit might have been performed within one year after it was made, and therefore it is not, as de[52]*52fendant contends, within the terms of section 9515, subd. 1, 3 Comp. Laws, which makes void every verbal agreement “that by its terms is not to be performed in one year from the making thereof.” See Detroit, etc., R. Co. v. Forbes, 30 Mich. 165.

Nor was the verdict, in our judgment, contrary to the weight of evidence or excessive.

The judgment is affirmed, with costs.

The other Justices concurred.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Feiler v. Midway Sales, Inc.
108 N.W.2d 884 (Michigan Supreme Court, 1961)
Caplis v. Monroe
200 N.W. 123 (Michigan Supreme Court, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
100 N.W. 1009, 138 Mich. 50, 1904 Mich. LEXIS 780, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-v-south-haven-eastern-railroad-mich-1904.