Thomas Creek Lumber and Log Company v. Kempthorne

250 F. App'x 316
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 3, 2007
Docket2007-1054
StatusUnpublished
Cited by1 cases

This text of 250 F. App'x 316 (Thomas Creek Lumber and Log Company v. Kempthorne) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Thomas Creek Lumber and Log Company v. Kempthorne, 250 F. App'x 316 (Fed. Cir. 2007).

Opinion

RADER, Circuit Judge.

The Department of the Interior Board of Contract Appeals (IBCA) decided that Thomas Creek Lumber and Log Company (Thomas Creek) is not entitled to compensation for deterioration of timber between 1991 and 1995. Appeals of Thomas Creek Lumber and Log Company, IBCA No. 3917R-3921R-2005, 06-2 BCA ¶ 33,342 (July 20, 2006). Because no contract existed before October 26, 1995, this court affirms.

I

On September 11, 1991, the Board of Land Management (BLM), offered for sale timber within an area known as Rocky Road in the state of Oregon. Although it was the highest bidder, Thomas Creek was not immediately awarded the timber contract. Instead, the BLM delayed 4 years due to questions regarding Thomas Creek’s ability to pay as well as the requirement for consultation under the Endangered Species Act to protect spotted owl habitat. On Jan 30, 1992, the habitat requirement halted the sale. In 1994, BLM formally cancelled the sale.

The Rescissions Act, on July 27, 1994, intervened to require BLM to award certain timber sale contracts, such as the Rocky Road contract, to the previously designated highest bidders “with no changes in originally advertised terms, volumes and bid prices.” Pub.L. No. 140-19; 109 Stat., 1995. Accordingly, the BLM offered the contract to its highest bidder from 1991, Thomas Creek. The BLM clarified that Thomas Creek had no obligation to accept the award because over 90 days had elapsed since the bid.

In July of 1995, Thomas Creek conducted another inspection and found that additional damage had occurred to the site since 1991. Nonetheless, and knowing that it had no obligation to enter into the contract, on October 26, 2005, Thomas Creek accepted the contract in its original form.

Over the next three years (1995-1998), BLM modified the contract price several times to account for deterioration of the timber on the site. The final purchase price agreed to by BLM was $716,262, which was lower than the original contract price. Thomas Creek, still dissatisfied, sought from the Contracting Officer (CO) additional compensation for damage to the timber. The CO increased BLM’s liability by $55,973. Thomas Creek wanted more, $286,164, and therefore appealed to the IBCA.

On May 18, 2005, the IBCA determined that Thomas Creek was not entitled to any compensation for the deterioration of timber between 1991 and 1995. The IBCA determined sua sponte that no contract bound the parties until October 26, 1995. Therefore, the Board did not award Thomas Creek any compensation for damage to the timber prior to that time. After additional briefing on reconsideration, the Board sustained its holding. Thomas Creek now appeals.

*318 II

Section 6 of the contract specifies that Thomas Creek accepts the timber after its examination in “as is ” condition: Sec. 6. Inspection of Timber and Disclaimer of Warranty:

(a) Purchaser warrants that this contract is accepted and executed on the basis of its examination and inspection of the timber sold under this contract and its opinion of the value thereof.
(b) Government expressly disclaims any warranty of fitness of the timber for any purpose, all timber sold hereunder is accepted As Is without any warranty of merchantability by Government. Any warranty as to the quantity or quality of the timber sold hereunder is expressly disclaimed by Government .... (emphasis in original).

Section 6(a) of the contract shows that Thomas Creek accepted the contract based on its own examination of the site. Thomas Creek examined the site not only in 1991 before it submitted its bid, but also again in 1995 before signing the contract. Thomas Creek also knew that it had no obligation to accept the contract. Thus, knowing of the changed circumstances on the site, Thomas Creek chose to sign and accept the contract in its original form. Moreover section 6(b) of the contract expressly disclaims any warranty on the quantity or quality of the timber.

Thomas Creek argues that contract does not specify the point in time to which the “As Is ” condition refers. Because “as is,” by its terms, refers to the present tense, the Board reasoned properly that “As Is ” means “As Is ” at the time of contract entry. [RB 12], As the Court of Claims expressed in its analysis of an identical disclaimer, “[i]t is difficult to imagine how the disclaimer could have been any clearer.” Webco Lumber Inc. v. The United States, 230 Ct.Cl. 457, 677 F.2d 860, 863 (1982).

Thomas Creek refers to the behavior of the parties as evidence that the contract had a different meaning. Thomas Creek notes that the CO behaved as if the government was liable for some of the damage that occurred prior to the signing of the contract. Thomas Creek argues that the CO, apparently, believed that the contract allowed payment of lost quantity and quality value from date of its original bid. The conduct of the parties, however, is not necessary or, even relevant to interpret an unambiguous contract. As this court has stated, contract terms “phrased in clear and unambiguous language ... must be given their plain and ordinary meaning, and we may not resort to extrinsic evidence to interpret them.” Coast Federal Bank v. United States, 323 F.3d 1035, 1038 (Fed.Cir.2003) (quoting McAbee Constr. Inc. v. United States, 97 F.3d 1431, 1435 (Fed.Cir.1996)). This court has considered extrinsic evidence in order to discern the presence of an ambiguity in contract terms, but in this case, the evidence presented does not demonstrate that Thomas Creek reasonably relied on a competing interpretation of “As is ” when it entered into the contract. See Metric Constructors, Inc. v. Nat’l Aeronautics & Space Admin., 169 F.3d 747, 751-52 (Fed.Cir. 1999) (trade practice and custom examined when party relied upon competing interpretation at contract formation); Beta Sys. Inc. v. United States, 838 F.2d 1179, 1183 (Fed.Cir.1988). Because the disclaimer of warranty in section 6 of the contract as to the fitness, quality, and quantity of the timber was unambiguous, this court declines to examine the extrinsic evidence pointed to by the appellant. City of Tacoma v. United States, 31 F.3d 1130, 1134 (Fed.Cir.1994) (“[E]xtrinsic evidence ... may not be considered unless an ambiguity is identified in the contract language.”).

*319 Section 7 also does not place the risk of loss on the government for damage that occurred prior to the formation of the contract:

Sec. 7.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abraham v. United States
81 Fed. Cl. 178 (Federal Claims, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
250 F. App'x 316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/thomas-creek-lumber-and-log-company-v-kempthorne-cafc-2007.