Thermal Design v. Thorson

2022 MT 191
Montana Supreme Court·Decided October 4, 2022·No. DA 21-0516·Published

Opinion

10/04/2022

DA 21-0516 Case Number: DA 21-0516

IN THE SUPREME COURT OF THE STATE OF MONTANA

2022 MT 191

THERMAL DESIGN, INC., a Nebraska Corporation,

Plaintiff, Counterclaim Defendant, and Appellee,

STEVE THORSON, an individual, d/b/a TNT Building Systems, a general partnership; TRAVIS THORSON, an individual, d/b/a TNT Building Systems, a general partnership;

Defendants, Crossclaim Defendants, and Appellees,

STEEL CONCEPTS, LLC, an Idaho limited liability company; and STEVE LARSON, an individual,

Defendants and Appellees,

v.

MARK and PAM DUFFY, a married couple,

Counterclaim Plaintiffs, Crossclaim Plaintiffs, and Appellants,

MARK DUFFY, an individual; PAM DUFFY, an individual; and CENTRAL COPTERS, INC., a Montana corporation,

Defendants and Appellants.

APPEAL FROM: District Court of the Eighteenth Judicial District, In and For the County of Gallatin, Cause No. DV-15-403-A Honorable Peter B. Ohman, Presiding Judge COUNSEL OF RECORD:

For Appellants:

Kellie G. Sironi, Attorney at Law, Billings, Montana

For Appellee Thermal Design, Inc.:

Michael P. Manning, Ritchie Manning Kautz PLLP, Billings, Montana

For Appellees Steven Thorson and Travis Thorson:

Steve Thorson, Self-Represented, Manhattan, Montana

Travis Thorson, Self-Represented, Belgrade, Montana

Submitted on Briefs: July 13, 2022

Decided: October 4, 2022

Filed: r-6tA•-if __________________________________________ Clerk

2 Justice James Jeremiah Shea delivered the Opinion of the Court.

¶1 Defendants Mark and Pam Duffy and Central Copters, Inc. (Central Copters) appeal

the October 4, 2021 Judgment, Decree of Foreclosure, and Order of Sale by the Eighteenth

Judicial District Court, Gallatin County, as well as all orders and actions contained therein.

We restate and address the following issues:

1. Whether the District Court abused its discretion during voir dire.

2. Whether the District Court erred by ruling that Thermal Design’s construction lien was valid against Central Copters, as the contracting party to a real estate improvement contract with TNT, and the Duffys, as landowners.

3. Whether the District Court erred by allowing TNT to make a crossclaim against Central Copters that was not included in the pretrial order.

¶2 We affirm.

FACTUAL AND PROCEDURAL BACKGROUND

¶3 Mark and Pam Duffy own two parcels of real property near the Bozeman

Yellowstone International Airport in Belgrade that they lease to Central Copters, a charter

helicopter and precision lifting company owned and operated by the Duffys.

¶4 In the fall of 2013, Mark ordered a pre-engineered steel building from R & M Steel,

a company based in Idaho. The building was to serve as a hangar and repair facility for

Central Copters. In the spring of 2014, Central Copters hired Steve Thorson and his son,

Travis, d/b/a TNT Building Systems (TNT), to assemble the building. TNT met with Mark

at the Central Copters facility in Belgrade to discuss the details of the job. Because Mark

was concerned about the building’s insulation, the group visited three of TNT’s completed

projects nearby, each with a different type of insulation, including one called the “Simple

3 Saver System,” designed and supplied by Thermal Design, Inc. Steve testified at trial that,

to his recollection, Mark was “focused on the Simple Saver one because it’s the best

looking. It’s the most energy efficient. It’s the best of those three products.” Steve

testified:

When we left that meeting, he was definitely interested in it. The only other insulation that he ever mentioned to me -- I mean, he said he didn’t want what was in his current hanger [sic], which was clear, and then he said he looked into doing spray foam in the new building. However, he thought that was going to be too expensive, and so I told him about the Simple Saver System, which is a -- like I said -- very good looking, highly efficient system, and so I told him, at that point, that I would get him literature, and that he could look at it then, so that’s what we did.

¶5 On June 6, 2014, Steve sent an e-mail to Mark, bidding a flat fee of $70,000 to erect

the pre-engineered building kit, specifying that “[t]his quote includes installing the [sic] all

the doors.” The e-mail noted that Steve had been “talking to several subs to get the ball

rolling,” and explained that TNT would mark up any subcontractor invoices by ten percent

as a general contractor fee. While neither party signed the bid, Mark testified at trial that

the parties had an agreement encapsulated by the June 6 e-mail. The e-mail did not specify

a completion date or specifically reference any costs associated with TNT providing or

installing insulation for the building.

¶6 Over the summer, Mark and Central Copters prepared the job site. When Mark was

having trouble finding a contractor to pour the concrete foundation on schedule, he gave

TNT permission to engage C&H Engineering and Surveying, Inc. to re-engineer the slab

and hire Kruse Enterprises to pour the foundation. Central Copters paid TNT’s related

4 invoices within days, including a ten percent general contractor markup on both invoices,

without dispute.

¶7 On August 15, 2014, Mark sent Steve an e-mail updating him on the progress at the

job site and asking Steve to “please confirm that you have ordered the insulation for the

building from the source you have.” Steve testified that “because [the Simple Saver

System] was the only insulation that [TNT] offered,” he understood the e-mail to request

that he purchase the Simple Saver System from Thermal Design. However, Steve waited

until the building had progressed to a certain point in early October to provide Thermal

Design with the final building plans and actually place the order. Thermal Design’s

engineering department then used the building plans to design an insulation system specific

to the Central Copters hangar. Based on Thermal Design’s specifications, another

company, Johns Manville, manufactured and shipped the fiberglass insulation directly to

the job site from its plant. The Simple Saver System insulation kit shipped in three parts

in late October, arriving in Belgrade by early November 2014. Mark testified that when

the pallets arrived at the site he had “never heard of Thermal Design,” TNT had never

provided him a quote for the product, and he never authorized TNT to purchase the

insulation kit.

¶8 The pre-engineered building was shipped to the site in late August and TNT

unloaded eight flatbed trailer loads over two days. Kruse Enterprises completed the

concrete foundation in mid-September. By mid-October, Steve testified that the building

was about 40 percent complete, and TNT submitted an invoice to Central Copters for

$62,520. The invoice included a $25,000 charge labeled “1st labor deposit,” which was

5 about 35 percent of TNT’s $70,000 bid, and a $37,520 charge for “[i]nsulation materials[:]

Simple Saver System.”1 Mark testified that, with winter approaching, he was disappointed

with the progress on the building and “was not prepared to pay TNT for something he had

not done.” Mark and Steve met on November 13, 2014. The meeting deteriorated into a

shouting match. Mark wrote Steve an e-mail later that day, which stated, “I fully intend to

pay you in a timely manner, but I need you to ‘outline the scope of the project with dates

Free access — add to your briefcase to read the full text and ask questions with AI

Thermal Design v. Thorson, 2022 MT 191 (Mo. 2022).

2022 MT 191 (Thermal Design v. Thorson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

State v. Thomson
545 P.2d 1070 (Montana Supreme Court, 1976)
Keaster v. Bozik
623 P.2d 1376 (Montana Supreme Court, 1981)
Scofield v. Estate of Wood
683 P.2d 1300 (Montana Supreme Court, 1984)
Williams v. Rigler
761 P.2d 833 (Montana Supreme Court, 1988)
Searight v. Cimino
748 P.2d 948 (Montana Supreme Court, 1988)
Mahan v. Farmers Union Central Exchange, Inc.
768 P.2d 850 (Montana Supreme Court, 1989)
Wise v. Ford Motor Co.
943 P.2d 1310 (Montana Supreme Court, 1997)
Reff-Conlin's Inc. v. Fireman's Fund Insurance
2002 MT 60 (Montana Supreme Court, 2002)
PUBLIC LANDS ACCESS ASS'N, INC. v. Jones
2004 MT 394 (Montana Supreme Court, 2004)
State v. Heath
2004 MT 58 (Montana Supreme Court, 2004)
Weimar v. Lyons
2007 MT 182 (Montana Supreme Court, 2007)
Johnson v. Costco Wholesale
2007 MT 43 (Montana Supreme Court, 2007)
Turk v. Turk
2008 MT 45 (Montana Supreme Court, 2008)
Harris v. Hanson
2009 MT 13 (Montana Supreme Court, 2009)
State v. Gunderson
2010 MT 166 (Montana Supreme Court, 2010)
State v. Grant
2011 MT 81 (Montana Supreme Court, 2011)
Stubblefield v. Town of West Yellowstone
2013 MT 78 (Montana Supreme Court, 2013)
State v. LaMere
621 P.2d 462 (Montana Supreme Court, 1980)
Kuchan v. Harvey
585 P.2d 1298 (Montana Supreme Court, 1978)
Martin v. BNSF Railway Co.
2015 MT 167 (Montana Supreme Court, 2015)