the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do

CourtCourt of Appeals of Texas
DecidedMarch 5, 2013
Docket01-11-00966-CV
StatusPublished

This text of the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do (the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do, (Tex. Ct. App. 2013).

Opinion

Opinion issued March 5, 2013

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-11-00966-CV ——————————— THE WATERHILL COMPANY, LLC, JONATHAN WASSERBERG, AND JASON FELT, Appellants V. Y HOANG DO AND QUY LINH NGO DO Appellees

On Appeal from the 334th District Court Harris County, Texas Trial Court Case No. 2008-21558

MEMORANDUM OPINION

Appellants, The Waterhill Company, LLC (“Waterhill”), Jonathan

Wasserberg, and Jason Felt, challenge the trial court’s rendition of summary judgment in favor of appellees, Y Hoang Do and Quy Linh Ngo Do (the “Dos”), in

the Dos’ suit for violations of the Texas Trust Fund Act, 1 breach of contract, fraud,

fraudulent transfer, 2 and conversion. In seven issues, Waterhill, Wasserberg, and

Felt contend that the trial court erred in striking their amended pleadings and

granting the Dos’ summary-judgment motion.

We reverse and remand.

Background

In their sixth amended petition, the Dos alleged that on March 30, 2005,

they entered into a “Construction Agreement” with Waterhill to build the Dos a

residence at 12 Farnham Park Drive for $1.313 million. On October 9, 2007, the

Dos and Waterhill executed an “Addendum to the Waterhill Companies Limited

Construction Agreement,” which adjusted the total construction cost of the

residence to $1,819,320.00. The Addendum provided that “construction of the

residence should be completed at the end of a twelve month period from the time

the foundation is completed. Change orders may extend construction time.”

In 2007, Waterhill submitted to the Dos a draw request for $372,933.04, and

on January 4, 2008, it submitted to the Dos a draw request of $72,223.54, with

$57,543.00 of the request designated to be paid to Boswell Construction, L.P.

1 See TEX. PROP. CODE ANN. § 162.031 (Vernon Supp. 2012). 2 See TEX. BUS. & COM. CODE ANN. § 24.005(a) (Vernon 2009). 2 (“Boswell”). In its January 4, 2008 request, Waterhill certified that “all suppliers

and subcontractors had been paid for work and materials on previous draws.”

However, the Dos subsequently received a letter from Boswell, informing them

that Waterhill owed it $56,100 for work done on the Dos’ residence. The Dos

further alleged that Waterhill had failed to pay a steel contractor, KV Weld, Inc.

(“KV Weld”) $48,455.00 for work done on the residence. And Waterhill then

“abandoned all activities on the property without excuse and materially breached

the[ir] Agreement by the repeated and extensive construction delays.” Finally, the

Dos alleged that Waterhill breached their contract by failing to deliver “travertine

tiles” pursuant to another request and converting the tiles for Waterhill’s own use.

In their original answer to the Dos’ original petition, appellants generally

denied the Dos’ claims. After the Dos filed several amended petitions, appellants

filed an amended answer, raising various affirmative defenses and counterclaims.3

Appellants then filed a second amended answer, generally denying the Dos’

allegations and raising twenty-four affirmative defenses. The Dos filed a motion to

strike appellants’ amended answers, asserting that appellants had “stalled, delayed

and used the arbitration process to avoid discovery and trial.” The Dos asserted

that appellants had “avoided the first trial at the last minute by demanding

3 Waterhill’s first amended answer does not appear in the record. However, Waterhill’s brief and the Dos’ “Motion to Strike [Waterhill’s] Amended Answer and Original Counterclaim” indicate that the first amended answer was filed on August 20, 2010. 3 arbitration” and then “avoided the arbitration trial by refusing the pay the

arbitrator.” They also argued that appellants’ “late filed answer and counterclaim

should be stricken” because it was filed “after 28 months of litigation and only 23

days before trial” and Waterhill had not disclosed the affirmative defenses during

discovery. The trial court granted the Dos’ motion and struck Waterhill’s first and

second amended answers.

In their summary-judgment motion, the Dos asserted that it was

“undisputed” that appellants had breached their construction contract by failing to

“complete the construction of the home within the contract period,” “properly

construct the home,” and “pay subcontractor[s] as per the parties’ agreement.” The

Dos attached to their motion a copy of a contract that they entered with Mike Stahl

to complete their residence at a cost of $1,765,506.00. Asserting that they had paid

appellants $569,589.96, the Dos sought breach-of-contract damages of

$524,326.49.

The Dos further argued that Felt and Wasserberg were individually liable for

Waterhill’s debts and obligations because they “acted as general partners and held

themselves out as general partners,” “participated in the daily control of the

business,” and “admitted that they were in fact general partners of Waterhill.”

They argued that appellants violated the Texas Trust Fund Act, committed fraud,

and converted the Dos’ funds because appellants received draw request payments

4 from the Dos for construction of their residence, but “commingled those specific

trust funds . . . by depositing [them] into a general bank account.” The Dos

asserted that appellants “misappropriated, converted or misapplied over

$108,000.00 in trust funds,” “used the funds to pay their debts on other projects,”

and “converted [the Dos’] tiles . . .[,] causing damages in the amount of $10,665.45

to replace the converted tiles.” And the Dos sought attorney’s fees in the amount

of $43,575 and punitive damages in the amount of $200,000.00.

The Dos attached to their summary-judgment motion the affidavit of Y

Hoang, who testified that he and his wife, Ling Ngo, had met with Wasserberg and

Felt prior to their signing of the construction contract with Waterhill. At the

meeting, Wasserberg and Felt told Y Hoang and Ngo that they were Waterhill’s

general partners and “all funds deposited or transferred to them from [the Dos]

would be used only on” the construction of the Dos’ residence. Hoang further

testified that Waterhill “never completed the construction of [the] home within the

time period set forth in the contract,” “walked off the jobsite in February 2008

without cause,” and “refused to complete the work set forth in the contract and pay

the subcontractors.”

The Dos also attached to their motion the depositions of Wasserberg and

Felt. Wasserberg testified that he was “an owner of Waterhill Companies Limited

in a general partner capacity” and Felt was a “co-managing partner” who

5 “oversee[s] bank relationships.” Felt testified that he was a “managing partner” of

Canary Financial, LLC (“Canary Financial”), which was “one of the general

partners of Waterhill.” He explained that he was “in charge of securing financing

for [Waterhill] and “other various banking relations.”

Finally, the Dos attached to their motion the affidavit of Jack Arnold, the

president of KV Weld, who testified that his company was hired by Waterhill to

“provide the structural steel” for construction of the Dos’ residence. Wasserberg

told Arnold that “he was the person who controlled the day to [day] activities of

[Waterhill].” Arnold noted that “KV Weld submitted an invoice and received the

sum of $48,455.00 . . . to be used at the Dos’ residence,” but Wasserberg directed

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mladenka v. Mladenka
130 S.W.3d 397 (Court of Appeals of Texas, 2004)
Coleman Cattle Co., Inc. v. Carpentier
10 S.W.3d 430 (Court of Appeals of Texas, 2000)
Quinn v. Dupree
303 S.W.2d 769 (Texas Supreme Court, 1957)
Khorshid, Inc. v. Christian
257 S.W.3d 748 (Court of Appeals of Texas, 2008)
Grainger v. Western Casualty Life Insurance Co.
930 S.W.2d 609 (Court of Appeals of Texas, 1996)
Anglo-Dutch Petroleum International, Inc. v. Haskell
193 S.W.3d 87 (Court of Appeals of Texas, 2006)
Cathey v. Booth
900 S.W.2d 339 (Texas Supreme Court, 1995)
Telephone Equipment Network, Inc. v. Ta/Westchase Place, Ltd.
80 S.W.3d 601 (Court of Appeals of Texas, 2002)
Nixon v. Mr. Property Management Co.
690 S.W.2d 546 (Texas Supreme Court, 1985)
Sterquell v. Scott
140 S.W.3d 453 (Court of Appeals of Texas, 2004)
Rhone-Poulenc, Inc. v. Steel
997 S.W.2d 217 (Texas Supreme Court, 1999)
CDB Software, Inc. v. Kroll
992 S.W.2d 31 (Court of Appeals of Texas, 1998)
Jamie Murphey v. State
86 S.W.3d 283 (Court of Appeals of Texas, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
the Waterhill Company LLP, Jonathan Wasserberg and Jason Felt v. Y Hoang Do and Quy Linh Ngo Do, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-waterhill-company-llp-jonathan-wasserberg-and--texapp-2013.