The Town of Black Mountain v. Lexon Insurance Company

CourtCourt of Appeals of North Carolina
DecidedDecember 16, 2014
Docket14-740
StatusPublished

This text of The Town of Black Mountain v. Lexon Insurance Company (The Town of Black Mountain v. Lexon Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals of North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Town of Black Mountain v. Lexon Insurance Company, (N.C. Ct. App. 2014).

Opinion

NO. COA14-740

NORTH CAROLINA COURT OF APPEALS

Filed: 16 December 2014

THE TOWN OF BLACK MOUNTAIN, NORTH CAROLINA and THE COUNTY OF BUNCOMBE, NORTH CAROLINA,

Plaintiffs,

v. Buncombe County No. 12 CVS 05118 LEXON INSURANCE COMPANY and BOND SAFEGUARD INSURANCE COMPANY,

Defendants.

Appeal by defendants from order entered 4 March 2014 by

Judge Gary M. Gavenus in Buncombe County Superior Court. Heard

in the Court of Appeals 20 October 2014.

Cannon Law, P.C., by William E. Cannon, Jr. and Ronald E. Sneed, P.A., by Ronald E. Sneed, for plaintiffs-appellees.

Shumaker, Loop & Kendrick, LLP, by William H. Sturges and Daniel R. Hansen, for defendants-appellants.

HUNTER, Robert C., Judge.

The Town of Black Mountain, North Carolina (“the Town”) and

the County of Buncombe, North Carolina (“the County”)

(collectively “plaintiffs”) filed suit against Lexon Insurance

Company and Bond Safeguard Insurance Company (“defendants”)

seeking to enforce a series of subdivision performance bonds. -2- The trial court entered summary judgment in plaintiffs’ favor.

On appeal, defendants argue that summary judgment for plaintiffs

was improper because: (1) neither the Town nor the County has

standing to enforce the bonds; and (2) the statute of

limitations for plaintiffs’ claim has run.

After careful review, we affirm the trial court’s order.

Background

From March 2005 through February 2007, defendants entered

into four subdivision performance bonds (“the bonds”) as

sureties for The Settings of Black Mountain, LLC and Richmarc

Black Mountain, LLC (collectively “developers”).1 Approval from

the County for the developers to begin construction on a

residential subdivision was conditioned on obtaining the

performance bonds to secure completion of the project. Thus,

the obligee on each of the bonds in question was the County, not

the Town. Each of the bonds contained a clause indicating that

defendants, as sureties, would not be required to complete the

infrastructure or pay the principal amount of the bond until

they received a resolution from the obligee indicating that the

improvements had not been installed or completed by the

1 Although plaintiffs named all four bonds in their complaint, the construction secured by one of the bonds has since been completed; thus, only three remaining bonds are the subject of plaintiffs’ claim. -3- developers. The bonds also contained a provision holding

defendants and the developers jointly and severally liable for

any amounts due upon default.

The real property that was secured by the bonds was annexed

by the Town at varying times between May 2005 and February 2007.

Defendants assert that they lacked knowledge of the annexation

until 5 January 2012. In 2009, the Town sought confirmation

from the developers that they intended and had the means to

complete the infrastructure secured by the bonds. In a letter

dated 23 October 2009, attorneys for the developers indicated

that they were working toward closing a recapitalization loan.

On 18 December 2009, a principal in one of the development

companies stated via e-mail that “we still believe we have

viable entities, though obviously troubled. We are committed to

finishing our communities without need of the bonds[.]” Indeed,

construction activity by the developers continued into 2010.

Ultimately the companies failed. Richmarc Black Mountain, LLC

filed its final annual report on 7 June 2011, and The Settings

at Black Mountain, LLC was administratively dissolved on 21

August 2011.

On 5 January 2012, the County contacted defendants and

asked if they would consent to an assignment of the bonds to the -4- Town. In its inquiry, the County conceded that, due to the

annexation, “Buncombe County no long[er] has any jurisdiction

over the properties and cannot enforce any rights per its

ordinances.” Defendants did not consent to the assignment.

On 1 August 2011 and 20 December 2011, the Town sent

defendants notice that the developers had ceased all

construction activity. On 22 June 2012, the County assigned its

rights in the bonds to the Town, which accepted assignment on 9

July 2012. On that same day, the Town adopted a resolution

finding the infrastructure to be incomplete. The Town sent

defendants notice of their claims under the bonds on 24 July

2012. Following nonpayment by defendants, plaintiffs filed

their complaint for breach of contract on 25 October 2012. Both

the County and the Town brought suit because they anticipated

that defendants would challenge standing if either party sued

separately; thus, their claims are pled in the alternative

pursuant to Rule 8 of the North Carolina Rules of Civil

Procedure.

Plaintiffs and defendants each moved for summary judgment

and were heard on their respective motions 10 February 2014.

The trial court entered an order granting summary judgment for -5- plaintiffs on 4 March 2014. Defendants filed timely notice of

appeal.

Discussion

I. Standing

Defendants first argue that neither the Town nor the County

has standing to bring suit. Specifically, defendants contend

that once the Town annexed the property covered by the bonds,

the bonds were extinguished, leaving no rights for the County to

assign. We disagree.

“This Court reviews orders granting summary judgment de

novo.” Foster v. Crandell, 181 N.C. App. 152, 164, 638 S.E.2d

526, 535 (2007). Summary judgment is appropriate “only when the

record shows that there is no genuine issue as to any material

fact and that any party is entitled to a judgment as a matter of

law.” In re Will of Jones, 362 N.C. 569, 573, 669 S.E.2d 572,

576 (2008) (internal quotation marks omitted). The burden of

proof rests with the movant to show that summary judgment is

appropriate. Development Corp. v. James, 300 N.C. 631, 637, 268

S.E.2d 205, 209 (1980). We review the record in the light most

favorable to the non-moving party. Caldwell v. Deese, 288 N.C.

375, 378, 218 S.E.2d 379, 381 (1975). -6- Defendants rely on Stillings v. City of Winston-Salem, 311

N.C. 689, 319 S.E.2d 233 (1984), in support of their contention

that the bonds were extinguished when the subject properties

were annexed by the Town. In Stillings, the Court stated the

issue it considered as follows: “Does an exclusive solid waste

collection franchise granted by a county remain effective in

areas subsequently annexed by a city and thereby entitle the

franchisees to compensation for a taking when the city, pursuant

to statutory mandate, begins providing its own garbage

collection service?” Id. at 691, 319 S.E.2d at 235. The Court

answered this question in the negative. Id. In holding that

the exclusive waste collection franchise entered into by the

county and a private party terminated in the geographic areas

annexed by the city, the Court noted that the garbage collection

company, “had no rights which the [c]ity was bound to respect.”

Id. at 694-96, 319 S.E.2d at 237-38. According to the statutory

mandate in N.C. Gen. Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. State Art Museum Building Commission v. Travelers Indemnity Co.
432 S.E.2d 419 (Court of Appeals of North Carolina, 1993)
Rowan County Board of Education v. United States Gypsum Co.
359 S.E.2d 814 (Court of Appeals of North Carolina, 1987)
Steel Creek Development Corp. v. Smith
268 S.E.2d 205 (Supreme Court of North Carolina, 1980)
Foster v. Crandell
638 S.E.2d 526 (Court of Appeals of North Carolina, 2007)
City of Reidsville v. Burton
152 S.E.2d 147 (Supreme Court of North Carolina, 1967)
Lynn v. Overlook Development
389 S.E.2d 609 (Court of Appeals of North Carolina, 1990)
Rowan County Board of Education v. United States Gypsum Co.
418 S.E.2d 648 (Supreme Court of North Carolina, 1992)
Stillings v. City of Winston-Salem
319 S.E.2d 233 (Supreme Court of North Carolina, 1984)
Caldwell v. Deese
218 S.E.2d 379 (Supreme Court of North Carolina, 1975)
Sides v. Cabarrus Memorial Hospital, Inc.
213 S.E.2d 297 (Supreme Court of North Carolina, 1975)
In Re the Will of Jones
669 S.E.2d 572 (Supreme Court of North Carolina, 2008)
Derwort v. Polk County
501 S.E.2d 379 (Court of Appeals of North Carolina, 1998)
North Carolina Bank & Trust Co. v. Williams
160 S.E. 484 (Supreme Court of North Carolina, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
The Town of Black Mountain v. Lexon Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-town-of-black-mountain-v-lexon-insurance-compa-ncctapp-2014.