The Saxon Group Inc. v. South Mississippi Electric Power Association

CourtCourt of Appeals of Mississippi
DecidedSeptember 3, 2019
Docket2017-CA-01482-COA
StatusPublished

This text of The Saxon Group Inc. v. South Mississippi Electric Power Association (The Saxon Group Inc. v. South Mississippi Electric Power Association) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Saxon Group Inc. v. South Mississippi Electric Power Association, (Mich. Ct. App. 2019).

Opinion

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI

NO. 2017-CA-01482-COA

THE SAXON GROUP INC. APPELLANT

v.

SOUTH MISSISSIPPI ELECTRIC POWER APPELLEE ASSOCIATION

DATE OF JUDGMENT: 09/21/2017 TRIAL JUDGE: HON. ROBERT B. HELFRICH COURT FROM WHICH APPEALED: FORREST COUNTY CIRCUIT COURT ATTORNEYS FOR APPELLANT: CLYDE X. COPELAND JASON EDWIN WEEKS ATTORNEYS FOR APPELLEE: MARK EDWARD NORTON LAWRENCE CARY GUNN JR. NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED - 09/03/2019 MOTION FOR REHEARING FILED: MANDATE ISSUED:

BEFORE CARLTON, P.J., WESTBROOKS AND McCARTY, JJ.

WESTBROOKS, J., FOR THE COURT:

¶1. Southern Mississippi Electric Power Association (SMEPA) contracted with a Georgia

construction company named Saxon Group Inc. (Saxon), to provide mechanical and electrical

construction services. In violation of the construction contract, Saxon defaulted on payments

to its subcontractors and suppliers, forcing Hanover Insurance Company (Hanover), Saxon’s

surety, to assume Saxon’s posture as payor. Saxon sued SMEPA in Forrest County Circuit

Court, seeking contract reformation and alleging several claims for breach of contract.

¶2. On SMEPA’s motion, the circuit court granted partial summary judgment on Saxon’s claim for interest owed for monies remitted to Hanover. At the conclusion of Saxon’s case

in chief, SMEPA moved for a directed verdict on Saxon’s consequential damages claim. The

court denied the motion. The jury found Saxon was entitled to recovery on all of its

remaining claims. SMEPA then filed a motion for a judgment notwithstanding the verdict,

which the court granted. Saxon’s $1.2 million verdict and corresponding claim for

consequential damages were set aside. Aggrieved, Saxon now appeals. After reviewing the

record, we affirm the circuit court’s judgments.

FACTS & PROCEDURAL HISTORY

¶3. SMEPA, now known as Cooperative Energy, is a South Mississippi electric

cooperative headquartered in Hattiesburg, Mississippi.1 Saxon was a Georgia heavy-

industrial construction company owned by Jeni Bogdan. On or about August 9, 2010, Saxon

received a “Request for Quotation” from the engineering firm, Burns McDonnell; the request

solicited bids for the opportunity to act as general contractor over SMEPA’s Moselle

Repower Project (Project. No. 49302) (“Moselle Project”).2 The Moselle Project sought to

upgrade and modernize SMEPA’s Moselle, Mississippi Power Station. Saxon, one of five

invited contractors, submitted bids for the mechanical and electrical construction contracts

associated with the project. By submitting the lowest bid, two percent lower than Yates

1 After 75 years of doing business as “Southern Mississippi Electric Power Association,” the company changed its name to “Cooperative Energy” on November 9, 2016. 2 Burns McDonnell is a full-service engineering firm; they provided engineering and construction oversight for the Moselle project.

2 Construction, Saxon was awarded both contracts.

¶4. Consistent with industry custom, Saxon was compelled to obtain a surety bond as a

prerequisite to securing the construction contract. The bond, obtained from Hanover,

guaranteed indemnity for SMEPA in the event Saxon failed to meet its obligations under the

Moselle contract. To acquire Hanover as its surety, Saxon signed an unqualified indemnity

agreement, assigning all of its rights under the SMEPA contract to Hanover in the event of

a default. The agreement further provided that, if necessary, Hanover would be responsible

for fulfillment of Saxon’s unrealized contractual obligations.

¶5. As the project proceeded, Saxon indeed fell behind on payments to its subcontractors

and suppliers. On or about July 2012, SMEPA was contacted by several subcontractors and

made aware of the defaults. SMEPA ceased paying Saxon based on the terms of the

construction contract, which provided that Saxon “within five (5) days after receipt of any

payment from [SMEPA]” would pay all of its material suppliers and subcontractors. As a

penalty for violating the provision, the contract stated that “[n]o payment shall be due while

[Saxon] is in default” and allowed SMEPA to withhold payment based on Saxon’s “failure

to perform.” In August 2012, Saxon sent correspondence acknowledging the delinquent

accounts and assuring SMEPA that they were on track to bring them current pending the

resolution of some disputed invoice amounts the subcontractors and suppliers submitted.

Saxon demobilized from the work site in September 2012; the accounts were still past due.

A subsequent investigation into the defaulted payments revealed Saxon was, in fact, upside

3 down on the contractual obligations and ultimately prompted SMEPA to contact Saxon’s

surety, Hanover, in October 2012.3

¶6. In March 2013, Hanover issued a “freeze funds” letter, demanding that SMEPA

submit the final contract payments to Hanover instead of Saxon, citing their indemnity

agreement. The surety paid all of the aggrieved vendors, disbursing a total of $3,017,455.04;

the final payment Hanover received from SMEPA was only $2,690,721.79. SMEPA agreed

that a significant delay of about two years occurred before Hanover was paid the remainder

owed on the contract. No clear explanation was provided for the delay, but there were

several factors cited in the record, namely Saxon’s failure to submit the required forms and

the ongoing litigation of the current case. After receiving a valid Certificate of Completion

on April 8, 2015, SMEPA submitted the final payment amount to Hanover on May 26, 2015.4

Saxon maintains the money was improperly withheld and faults SMEPA’s delayed payment

for its downfall. Unable to maintain as an independent company, Saxon agreed to an

acquisition of its assets by Primoris Services Corporation in 2012.

¶7. Saxon filed a complaint on February 14, 2014, blaming SMEPA for the “ruination of

3 SMEPA contacted individual subcontractors and found that they were owed more than Saxon indicated. The delinquency totals were significantly more than the total contract with SMEPA was worth. Even if SMEPA paid out the entire amount due on the contract, Saxon would not have been able to cover the delinquencies. Hanover was contacted to pay the aggrieved suppliers and subcontractors. 4 The final payment submitted by SMEPA to Hanover was deficient by $326,733.25 compared to the settlement payments Hanover made to fulfill SMEPA’s outstanding debts to suppliers and subcontractors.

4 the company.” The complaint sought equitable reformation of the parties’ mechanical

construction contract, damages for bad faith breach of contract and wrongful withholding of

amounts due related to the mechanical contract and a separate electrical contract. SMEPA

denied the allegations and filed a motion for partial summary judgment on May 29, 2015.

The court denied the motion in an order entered January 19, 2016.

¶8. Together, the parties reached a partial settlement on the wrongful withholding claim

and subsequently dismissed the reformation claim voluntarily. Despite the previous denial,

on August 12, 2016, SMEPA filed another pre-trial motion for final summary judgment on

Saxon’s remaining claims that:

(1) SMEPA improperly withheld $250,000 as liquidated damages;

(2) SMEPA wrongfully back charged Saxon in the amount of $93,326.39 for incomplete work;

(3) SMEPA owes Saxon interest on monies paid to Hanover;

(4) Saxon is entitled to consequential damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pearlman v. Reliance Insurance
371 U.S. 132 (Supreme Court, 1962)
Young v. Robinson
538 So. 2d 781 (Mississippi Supreme Court, 1989)
ST. PAUL PROPERTY & LIABILITY v. Nance
577 So. 2d 1238 (Mississippi Supreme Court, 1991)
Mississippi Transp. Com'n v. SCI, INC.
717 So. 2d 332 (Mississippi Supreme Court, 1998)
Turner v. Terry
799 So. 2d 25 (Mississippi Supreme Court, 2001)
White v. Stewman
932 So. 2d 27 (Mississippi Supreme Court, 2006)
Bullock v. Life Ins. Co. of Mississippi
872 So. 2d 658 (Mississippi Supreme Court, 2004)
Great So. Nat. v. McCullough Env. Serv.
595 So. 2d 1282 (Mississippi Supreme Court, 1992)
Osborne v. Bullins
549 So. 2d 1337 (Mississippi Supreme Court, 1989)
Ford v. White
495 So. 2d 494 (Mississippi Supreme Court, 1986)
ROYER HOMES OF MS., INC. v. Chandeleur Homes, Inc.
857 So. 2d 748 (Mississippi Supreme Court, 2003)
Steele v. Inn of Vicksburg, Inc.
697 So. 2d 373 (Mississippi Supreme Court, 1997)
Chapel Hill, LLC v. SoilTech Consultants, Inc.
112 So. 3d 1097 (Court of Appeals of Mississippi, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
The Saxon Group Inc. v. South Mississippi Electric Power Association, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-saxon-group-inc-v-south-mississippi-electric-power-association-missctapp-2019.