The Peninsula at St. John's Center Condominium Association, Inc. v. Amerisure Insurance Company

CourtDistrict Court, M.D. Florida
DecidedMay 31, 2025
Docket3:22-cv-00792
StatusUnknown

This text of The Peninsula at St. John's Center Condominium Association, Inc. v. Amerisure Insurance Company (The Peninsula at St. John's Center Condominium Association, Inc. v. Amerisure Insurance Company) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Peninsula at St. John's Center Condominium Association, Inc. v. Amerisure Insurance Company, (M.D. Fla. 2025).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF FLORIDA JACKSONVILLE DIVISION

THE PENINSULA AT ST. JOHN’S CENTER CONDOMINIUM ASSOCIATION, INC.

Plaintiff,

v. Case No. 3:22-cv-792-ACC-LLL

AMERISURE INSURANCE COMPANY, and AMERISURE MUTUAL INSURANCE COMPANY,

Defendants.

ORDER This cause comes before the Court on cross-motions for summary judgment: (1) Defendants Amerisure Insurance Company and Amerisure Mutual Insurance Company’s (collectively, “Amerisure”) Motion for Summary Judgment Against Plaintiff (Doc. 308), to which Plaintiff the Peninsula at St. John’s Center Condominium Association, Inc. (the “Association”) responded in opposition (Doc. 322), and Amerisure filed a reply (Doc. 338); and (2) the Association’s Motion for Partial Summary Judgment (Doc. 310), to which Amerisure responded in opposition (Doc. 317), and the Association filed a reply (Doc. 339). For the following reasons, the Court will grant Amerisure’s Motion for Summary Judgment and will deny the Association’s Motion for Partial Summary Judgment.

INTRODUCTION This case arises out of the construction of a condominium project called The Peninsula at St. John’s (the “Project”) located in Jacksonville, Florida occurring

from 2005 through 2008. (Doc. 308-1 ¶¶ 15–16). The Association previously litigated the underlying construction defect issues years ago in a state court lawsuit brought against the general contractors, sureties, and subcontractors involved in the original Project construction (the “Underlying Litigation”). 1 The Underlying

Litigation culminated in a series of settlement agreements, including one nearly global agreement for approximately $39 million between the Association and some of the contractors, sureties, and subcontractors working on the Project. Separately,

the Association settled claims for additional millions of dollars with some other subcontractors of Auchter Company, Inc. (“Auchter”), the first general contractor working on the Project before it defaulted. In addition to the foregoing settlement agreements, the Association entered into a Coblentz agreement with Auchter in the

amount of $8.5 million in damages.2 (Doc. 308-37).

1 The Peninsula at St. John’s Center Condominium Association, Inc. v. The Auchter Company, et al., Case No. 2013-CA-6582, Circuit Court of the Fourth Judicial Circuit in and for Duval County, Florida.

2 “The term ‘Coblentz agreement’ refers to a settlement agreement entered into between an insured and a claimant in order to resolve a lawsuit in which the insurer has denied coverage In a Coblentz agreement, following an insurer’s alleged wrongful refusal to defend, the insured (in this case, Auchter) negotiates a settlement with the claimant

(in this case, the Association) in an underlying action wherein the parties agree to entry of a consent judgment fixing liability and damages amounts. As part of this agreement, the insured (Auchter) assigns to the claimant (the Association) the right

to collect in a subsequent lawsuit from its insurance company (Amerisure). This is that subsequent lawsuit. The Association, standing in the shoes of Auchter, seeks to collect $8.5 million under commercial general liability (“CGL”) policies issued by Amerisure to Auchter effective during some, but not all, of the Project’s

construction. The Court must decide whether the Association can recover from Amerisure under this agreement. FACTUAL BACKGROUND

I. Construction of the Peninsula Project In 2005, Auchter was hired by the Project’s developer to serve as the general contractor on the Project. (Doc. 31 ¶ 12; Doc. 32 ¶ 12). Auchter contracted with the following relevant subcontractors. Blanchard Caulking & Coating (“Blanchard”)

was hired to furnish dampproofing over the cement masonry units (“CMU”) behind the brick masonry at the parking garage. (Doc. 308-2 at 22–23). Cummings Masonry

and declined to defend.” Trovillion Const. & Dev., Inc. v. Mid-Continent Cas. Co., No. 6:12-cv- 914, 2014 WL 201678, at *3, n.2 (M.D. Fla. Jan. 17, 2014) (citing Coblentz v. Am. Sur. Co. of N.Y., 416 F.2d 1059, 1063 (5th Cir.1969)). Co. (“Cummings”) was hired to furnish and install the masonry work including the CMU and brick veneer at the parking garage. (Doc. 308-3 at 22–23). Per the

Cummings’ contract, this included “all required masonry CMU block, brick, mortar, sand, masonry wall wire reinforcing, flashing, weeps,” brick veneer, all wire reinforcing, and all precast concrete lintels. (Id.) Sterling Dula Arch. a/k/a Kane Mfr.

Corp. (“Kane”) was hired to design, furnish, and install the garage screens, balcony railings, and balcony posts. (Doc. 308-4 at 22–23). CECO Concrete Construction, LLC (“CECO”) was hired to install the balcony slabs. (Doc. 308-5 at 22–23). Two years into the Project, on or about April 25, 2007, Auchter informed the

Project developer that it was financially unable to complete its work as the general contractor and advised that it was terminating its construction contract with the developer. (Doc. 308-6). The parties agree that by August 2007, the developer and

Auchter’s sureties (the “Sureties”) entered into a Takeover Agreement under which the Sureties would take over the Project, and Skanska USA, Inc. (“Skanska”) was substituted in as a contractor in place of Auchter.3 (Doc. 308-1 at 10–11; Doc. 322 at 7; Doc. 310 at 306). The Takeover Agreement provides that Skanska would enter

3 The Association labels Skanska as a “subcontractor” but does not provide any evidence supporting that Skanska would be a subcontractor rather than assuming the work that was intended to be performed by Auchter. The Takeover Agreement references that Skanska will be an independent contractor to the Sureties but also that Skanska will merely be a subcontractor to the Association, presumably because Skanska was contracting directly with the Sureties and not the Association. (Doc. 310 at 307). into a completion agreement (the “Completion Agreement”) and perform the terms of the original construction contract. (Doc. 310 at 307). Skanska, utilizing

Blanchard, Cummings, and Kane, among other subcontractors, subsequently completed the Project, and the Certificate of Occupancy was issued on July 30, 2008. (Doc. 308 at 2, 4; Doc. 308-1 at 9–10; Doc. 205-5).

The parties dispute how much, if any, of the dampproofing, masonry, garage screens, and balcony work was completed at the time of Skanska’s takeover in August 2007 and as of the expiration of the relevant Amerisure policies on January 1, 2008. It is undisputed that the Project’s Certificate of Occupancy was issued on

or about July 30, 2008. (Doc. 308-1, Ex. F). The Project was turned over to the Association’s control on or about November 10, 2011. (Id. ¶ 50). It is undisputed that the Association’s discovery of defects occurred years

after the Amerisure policies expired on January 1, 2008. The earliest record evidence includes the identification of issues in the Turnover Evaluation Report issued on April 26, 2013, which identified certain construction deficiencies at the Project following inspections that had occurred in 2012 and 2013. (Doc. 308-22).

The Association observed various issues as follows: in 2012, rubber gaskets on the aluminum balcony railings were deteriorating and were replaced pursuant to work orders (Doc. 308-33, Deposition of Thamir Massraf (“Massraf. Dep.”) at 34–

39; Doc. 308-34); in 2013, anchoring cement utilized at some balcony railing posts showed signs of weathering (Doc. 308-22); and in 2016, the Association observed cracking and spalling in the brick veneer and CMU work performed by Cummings.

(Doc. 308-23 at 6, 18-23, 308-24 at 12, 35, 44).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cohen v. United American Bank
83 F.3d 1347 (Eleventh Circuit, 1996)
Shotz v. City of Plantation, FL
344 F.3d 1161 (Eleventh Circuit, 2003)
Terry Gilmour v. Gates, McDonald & Co.
382 F.3d 1312 (Eleventh Circuit, 2004)
Burnette v. Taylor
533 F.3d 1325 (Eleventh Circuit, 2008)
Norfolk Southern Railway Co. v. Groves
586 F.3d 1273 (Eleventh Circuit, 2009)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lawyers Title Insurance Corp. v. Jdc (America) Corp.
52 F.3d 1575 (Eleventh Circuit, 1995)
Janet Feliciano v. City of Miami Beach
707 F.3d 1244 (Eleventh Circuit, 2013)
Goldschmidt v. Holman
571 So. 2d 422 (Supreme Court of Florida, 1990)
Keller Industries, Inc. v. Emp. Mut. Liab. Ins. Co.
429 So. 2d 779 (District Court of Appeal of Florida, 1983)
Sinni v. Scottsdale Insurance
676 F. Supp. 2d 1319 (M.D. Florida, 2010)
J.B.D. Construction, Inc. v. Mid-Continent Casualty Company
571 F. App'x 918 (Eleventh Circuit, 2014)
Hugh A. Carithers v. Mid-Continent Casualty Company
782 F.3d 1240 (Eleventh Circuit, 2015)
Highland Holdings, Inc. v. Mid-Continent Casualty Company
687 F. App'x 819 (Eleventh Circuit, 2017)
Jacob Horn v. Liberty Insurance Underwriters, Inc.
998 F.3d 1289 (Eleventh Circuit, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
The Peninsula at St. John's Center Condominium Association, Inc. v. Amerisure Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-peninsula-at-st-johns-center-condominium-association-inc-v-flmd-2025.