WALKER, Circuit Judge.

The appellee libeled the steamship Olga S. for the amount of damages sustained in consequence of the loss of 34 mahogany logs delivered alongside that vessel at Frontera, Mexico, on April 1, 1922, under a contract of affreightment, the pertinent provisions of which are: “The logs to be delivered alongside steamer in reach of ship’s tackle, in the water. Logs to be delivered at Frontera free of expense to the steamer, as fast as steamer can receive, Sundays and legal holidays excepted.”

The evidence showed as follows: The vessel arrived at Frontera on March 28, 1922, and anchored about two miles off shore, in the Frontera open roadstead. Appellee’s logs were then assembled in a canal at Frontera ready for shipment. Upon the ship’s arrival at Frontera, appellee’s representative, accompanied by the ship’s agent, went aboard and spoke to the captain in reference to lifting appellee’s logs. Upon the captain being informed that some of the logs weighed over three tons, he said he did not know whether his booms could lift over three tons or not, whereupon the appellee’s representative and the ship’s agent told the captain that a boom owned by the ship’s agent could be obtained, and the captain agreed to put on appellee’s logs if the appellee’s representative paid the expense of furnishing the ship agent’s boom, and appellee’s representative agreed to pay that expense, which was incurred. During the afternoon of March 30th the captain in writing notified appellee’s representative that the former was then ready to start loading appellee’s logs, and requested that ihe logs be brought alongside. The next morning, Friday, after the ship’s agent’s boom had been installed, two rafts of logs were delivered alongside the ship, and wore loaded on the ship that day. During that day the base of the ship’s agent’s boom broke, with the result that that boom had to bo repaired, and was out of commission from about noon, Friday, until late Saturday afternoon. During the forenoon of Saturday two rafts of logs were towed out by a motorboat and delivered alongside the ship, and the master gave receipts therefor to appellee’s representative. Each raft was made up by driving into each log an iron pin, having an eye at the upper end and called a “dog” or “ring dog,” through which a chain was passed. When the rafts were brought alongside, they were made fast to the [230] ship by means of ropes. The loading of the logs proceeded on Saturday, a number of logs weighing more than three tons being put aboard by means of the ship’s boom. The appellee had no part in the loading, which was in charge of the ship. When the stevedores engaged in loading the logs stopped work about 5 o’clock Saturday afternoon, 35 of appellee’s logs remained in the water, alongside the ship, and 34 of them went adrift during the night and were lost. The- appellee’s representative left the ship about 5 o’clock Saturday afternoon, returning to shore on the boat which had brought the rafts to the ship’s side. He was not asked to. resume charge of any of the logs or to have them carried back into the canal. That night the wind increased, and there was a heavy swell, which after midnight caused the logs alongside to bump violently against the side of the ship and the propeller, causing the pins in some of the logs to be pulled out, with the result that logs were lost as above stated. The weather conditions during that night were not unusual.

The claim asserted by the libel was resisted on the grounds: (1) That the logs were not delivered to the ship in accordance with the agreement of the master and appellee’s representative, and were at the risk of the appellee when they were lost; (2) that the logs were not delivered to the ship in accordance with the provision of the contract of affreightment, “as fast as stegmer can receive,” but faster, with the result that they remained at the risk of the appellee, the shipper; and (3) that the logs were lost either through a peril of the sea or through the negligence of the appellee in improperly rafting the logs. The court ruled against those defenses, and rendered a decree in favor of the appellee for the stipulated value of the lost logs and interest.

In this court the appellant relied on each of the above-mentioned defenses. As the logs were brought to the ship’s side pursuant to the master’s express request, and were receipted for by the master without any question being raised as to the time, speed, or manner of the delivery and without any suggestion that the delivery of any of the logs be delayed until the completion of the repairs on the special boom, the accepted delivery of the logs had the effect of putting them at the ship’s risk. Bulkley v. Maumkeag Steam Cotton Co., 24 How. 386, 16 L. Ed. 599; The Gracie D. Chambers (C. C. A.) 253 F. 182; Id., 248 U. S. 387, 39 S. Ct. 149; 63 L. Ed. 318. The master’s unconditional acceptance of the delivery of the logs was inconsistent with the contention that they remained at the shipper’s risk until'actually loaded on the ship.

Free access — add to your briefcase to read the full text and ask questions with AI

The Olga S., 25 F.2d 229, 1928 U.S. App. LEXIS 2922, 1928 A.M.C. 831 (5th Cir. 1928).

25 F.2d 229 (The Olga S.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related