The Newaygo

205 F. 178, 1913 U.S. Dist. LEXIS 1539
CourtDistrict Court, E.D. Michigan
DecidedFebruary 20, 1913
DocketNo. 5,049
StatusPublished
Cited by2 cases

This text of 205 F. 178 (The Newaygo) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Newaygo, 205 F. 178, 1913 U.S. Dist. LEXIS 1539 (E.D. Mich. 1913).

Opinion

TUTTLE, District Judge.

The Great Lakes Towing Company made a contract with H. W. McMorran to furnish all towing and wrecking services required by the boats under his management from July, 1903, -¿o the end*of the season, at a discount of 20 per cent, from the regiilar tariff, which contract included the boats owned by the Mills Transportation Company, of which boats said McMorran was manager, and as such authorized to make the contract. On November 11, 1903, the steamer Newaygo (one of the boats owned by the 'Mills Transportation Company) was stranded on the reef known as “Devil's Island Shoal,” in Georgian Bay, and telegrams were sent to the Great Lakes Towing Company, directing them to send the tug Favorite to the assistance of the Newaygo. In compliance with these requests, and acting under the contract, they sent the tug Favorite on November 17th, at 5:05 p. m. from Cheboygan to the Newaygo. The tug arrived at Tobermoray on November 18, 1903, at 5:45 p. m., and from then until November 26, 1903, made every effort to release the Newaygo. By the assistance of the Checotah, the tow barge of the Newaygo, which was also owned by the Mills Transportation Company, two pumps were placed on board on November 25th; but it was found impossible to lower the water, and on November 26th all further efforts were abandoned, and the tug started for Cheboygan with the crew of the Newaygo on board, where she arrived on November 27th at 8:15 p. m. The Newaygo was a total loss, except for articles to> the value of about $156. During this period of time in question, and on November 23d, the Favorite pulled the Strathcona off Flower Pot Island, where she was stranded. The Strathcona was owned by a third party. The time spent on the Strathcona by the Favorite was 3 hours, and a charge of one day’s time was made by the Favorite to the Strathcona. This work was done on the Strathcona at a time when there was nothing that could be done by the Favorite to assist the Newaygo. Many additional facts are stated in the opinion of the Circuit Court of Appeals in considering this case on the petition of the Mills Transportation Company for limitation of liability. 155 Fed. 11. 83 C. C. A. 607, 22 L. R. A. (N. S.) 769.

The Great Lakes Towing Company rendered a bill charging for 10 days’ use of the tug Favorite, at $350 per day, and for 10 days’ use of two pumps, at $50 each per day; the same being according to the regular tariff price. From this amount a discount of 20 per cent, was allowed according to contract. Various small items for extras actually furnished, amounting to $127.43, made the total amount of the claim as presented $3,727.43. The Great Lakes Towing Company [180]*180claims that the time computed according to contract was 11 days, but that one day was deducted for the 23d day of November, when the tug- was employed in pulling the Strathcona off Flower Pot Island where she was stranded. The Mills Transportation Company claims that 10 days, the time as originally charged in the bill presented, would be correct, if no work had been done on the Strathcona, but that one day should be deducted, leaving the bill for 9 days. The commissioner has sustained the contention of the Mills Transportation Company in this regard.

The court cannot agree with this finding. The regular tariff for the steamer Favorite was $350 per -day, with minimum charge of one day, and all fractions of days counted the same as whole days. This time should be computed from the time the Favorite left Cheboygan on November 17th, at 5:05 p. m., until she reached Cheboygan on November 27th, at 8:15 p. m., a period of 10 days, 3 hours and 10 minutes, which under the schedule should be computed as 11 days, except for the fact that the Favorite did 3 hours’ work on the Strathcona 'during that period of time. If the actual time spent on the ' Strathcona be deducted, the balance of the time is a few minutes more than 10 days. If a whole day (the time charged to the Strathcona) be deducted, it leaves 9 days and a fraction of a day, so that on either theory, and under any proper computation, claimant was entitled under the tariff to charge for 10 days. It was not necessary for the Great Lakes Towing Company to mention the work done on the Strathcona in presenting its bill. It presented an itemized bill, showing what work had been done for the Newaygo, giving dates, hours and minutes. It carried out the amount at 10 days, when by dates and items given in its bill it would be entitled to charge for 11 days. It made out the bill correctly, and made the proper reduction. No fault can be found because it did not state why the reduction was made, and it would not be proper to permit the reduction of another day at this time. The pumps were not used on the Strathcona. No charge was made to the Strathcona for pumps, and there is nothing in that connection which should alter the amount to be charged the Mills Transportation Company for the use of pumps.

It therefore follows that the first and second exceptions of the Great Lakes Towing Company to the report of the commissioner are sustained, and the Great Lakes Towing Company will be allowed for 10 days’ services of the steamer Favorite, at $350 per day, and for 10 days’ use of two pumps, at $50 per day for each pump, less the 20 per cent, discount provided for in the contract.

[1] The commissioner has allowed interest on the claim at 5 per cent, from September 4, 1912, the date of filing the report, and the Gireat Lakes Towing Company has excepted because the commissioner did not allow interest at the rate of 6 per cent., and from January 27, 1904, the time when the claim was presented for payment. In fixing, the amount of. the claim, the court has been compelled to construe the. contract strictly, which gives the claimant a larger sum than the court would allow for the services rendered under all the circumstances, except for the price agreed upon in the contract. Counsel on each side have spent much time in trying to convince the court that the opposite [181]*181party is responsible for tlie 9 years which have elapsed since the services in question were performed without an adjustment of the claim. Each has in a measure been successful, and the court is satisfied that the responsibility rests in some degree on both parties, and that such delay would not have been possible, had either party pressed the matter diligently all the time.

■Because of the fact that under the contract the court is compelled to allow the claim at a larger amount than the services were worth, the court feels bound to exercise its discretion as to the date from which interest should be computed in favor of the Mills Transportation Company. The long and unnecessary delay should also be considered. It is a matter for the discretion of the court. In-the exercise of that discretion the court finds that interest should be computed from September 4-, 1912, the date of filing the report. In the opinion of the court this loss of interest to claimant and corresponding gain by the Mills Transportation Company makes the amount of the claim which is now allowed just and fair.

[2] It has been argued that the rate of interest should be fixed at 6 per cent., on the theory that such is, or ought to be, the uniform rate in admiralty cases, without reference to the laws of the state in which the court is sitting. Some support for this argument may be found in The Aleppo, 7 Ben. 120, Fed. Cas. No. 158, and The Oregon (D. C.) 89 Fed. 520, which are predicated upon Hemmenway v. Fisher, 20 How. 255, 15 L. Ed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cambria S. S. Co. v. Pittsburgh S. S. Co.
212 F. 674 (Sixth Circuit, 1914)
The Silver Star
207 F. 600 (D. Maine, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
205 F. 178, 1913 U.S. Dist. LEXIS 1539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-newaygo-mied-1913.