The Myrtie M. Ross

160 F. 19, 1908 U.S. App. LEXIS 4169
CourtCourt of Appeals for the Sixth Circuit
DecidedMarch 2, 1908
DocketNo. 1,720
StatusPublished
Cited by6 cases

This text of 160 F. 19 (The Myrtie M. Ross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Myrtie M. Ross, 160 F. 19, 1908 U.S. App. LEXIS 4169 (6th Cir. 1908).

Opinion

KNAPPEN, District Judge

(after stating the facts as above). Rule 11 of the Circuit Court of Appeals (150 Eed. xxvii, 79 C. C. A. xxvii) requires the appellant, in assigning the errors, to “set out separately and particularly each error asserted and intended to be urged.” Under the repeated decisions of this court, and of others of the Courts of Appeals the assignments of errors presented are too vague and indefinite to comply with this rule. P. P. Mast & Co. v. Superior Drill Co., 154 Fed. 45, 50, 83 C. C. A. 157; Deering Harvester Co. v. Kelly, 103 Fed. 261, 43 C. C. A. 225; McFarland v. Golling, 76 Fed. 23, 22 C. C. A. 23; Smith v. Hopkins, 120 Fed. 921, 57 C. C. A. 193; United States v. Fee Yen Tai, 113 Fed. 465, 51 C. C. A. 299; United States v. Ferguson, 78 Fed. 103, 24 C. C. A. 1; Grape Creek Coal Co. v. Farmers' Loan & Trust Co., 63 Fed. 891, 12 C. C. A. 350; Doe v. Waterloo Mining Co., 70 Fed. 455, 17 C. C. A. 190. The rule, however, provides that “the court at its option may notice a plain error not assigned.” We have exercised this option, and have examined the record for the purpose of determining whether appellant is entitled to relief under the rule.

1. What was the contract between the parties? This is purely a question of fact, and is so conceded by counsel for both sides. The evidence as to what occurred at the interview between Nowlin and Dief-fenbach, on November 27th, is conflicting, the former claiming that an agreement was reached for the raising of the boat that fall, leaving only the question of whether McMorran would take less than $1,000, while Dieffenbach claims that no terms were agreed upon. The question must largely be decided by reference to the correspondence between and conduct of the parties, and the practical construction thereby placed by' them respectively, thereon. ■ Considering this correspondence and conduct of the parties, we are satisfied that the contract made by McMorran was not to raise the boat in any event that fall, but to attempt to so raise and deliver her, weather and ice permitting. Among'the considerations which prompt us to this conclusion are these: The suggestion in Nowlin’s letter of November 30th, that McMorran should proceed to raise the boat at once, scarcely accords with the existence of a guaranty to raise the boat at all hazards during that season. McMorran’s letter of December 1st, in which he states merely that he will attempt to raise, and deliver the boat, weather and ice permitting, is out of harmony with an alleged understanding on his part that he has guaranteed to immediately raise and deliver the boat. A recognition of McMorran’s construction of the contract is further evidenced by the fact that no protest was made by Nowlin against the quitting of the work on December 15th, even upon the receipt of McMorran’s letter of December 19th, stating that no more work could be done that fall, and especially in view of the fact of Brown’s report to Nowlin of the wrecking operations. We are further impressed by the fact that Dieffenbach had, at the time of his interview with Nowlin, no actual knowledge of the condition of the wreck or of the work to be done upon it, and with the im[23]*23probability that, without such knowledge, and in view of the lateness of the season and the danger of immediate stoppage of the work by weather and ice, an experienced wrecker would have been so apparently imprudent as to enter into a guaranty to raise the boat in any event. It is sufficient to say, without further detail of reasons prompting the conclusion, that, in our opinion, the district judge rightly construed the contract between the parties.

2. Was the failure to raise the boat during the fall due to a lack of diligence in the wrecker? It was certainly the wrecker’s duty to exercise reasonable diligence toward effecting the raising of the boat. What is reasonable diligence must be measured by the attending circumstances, taking into account the lateness of the season and the liability to interruption by storm and ice. In this case a higher degree of diligence was required than would have been necessary earlier in the season. The only respects in which it can seriously be suggested that the wrecker failed in his duty of diligence is in not employing two divers for work' at the same time, in not carrying on the work of putting chains under the wreck during the night as well as. day, and in not having the pontoons available, so as to avoid interruption of the work by going after them. Upon the question of the reasonable requirement of two divers and of a double equipment for day and night work, the testimony of those experienced in the business is conflicting. On the part of the appellant several witnesses testified that in their judgment, at that season of the year and under the circumstances shown, two divers should have been used at the same time and the work carried on both night and day. On the contrary, an equal number of witnesses (aside from Dieffenbach) and of apparently equal competency, testified that under the circumstances shown, and during the work of putting the chains under the boat, preparatory to lifting, it would have been unusual and extraordinary to work two divers at once and to work nights; the drift of some of this testimony being that two divers could not well work to advantage together, and that jetting could not well be carried on at night; some of the witnesses drawing a distinction in those regards between wrecking by means of lightering or patching and deep-water wrecking by pontoons, such as employed here. Upon the whole, we are the more impressed with the contention of the appellee, and are inclined to the view that there was not such apparent exigency as to require what would apparently have been an unusual degree of expedition. Several considerations, apart from the direct testimony of the experts, fortify us in this view: It was greatly to the interest of the appellee to finish the work as speedily as practicable. On December 1st, immediately upon the acceptance of McMorran’s terms, the latter started promptly for the wreck, without waiting for reply to his communication, and there is no room for complaint that time was lost by failing to work nights, except during the work of putting the chains under the boat. The testimony does not satisfy us, either through the amount of compensation provided or otherwise, that the parties contemplated the unusual night work by divers.

As to the pontoons: Manifestly, had Dieffenbach taken the pontoons with him when he first went to the wreck, the work of getting [24]*24the chains under the Ross would have been delayed by practically the time required to pump out the pontoons, and by the additional time that would be required in getting to the wreck with them, as the Groh or some other boat was evidently needed for pumping out the pontoons, and the small distance between Port Huron and the wreck required but little time for traveling, and this was done nights. The preparation of the pontoons required an entire day and the greater part of the following night. There is, moreover, apparently some force in the suggestion that it could not be surely known until the wreck was examined whether the pontoons could certainly be used, although their use was contemplated; and the work at the wreck would apparently have been hampered to some extent by the necessity of caring for the pontoons while awaiting their use. Unless, therefore, the circumstances were such as to have made it incumbent on the appellee to provide an additional tug and crew for preparing and taking charge of the pontoons, it would not appear that appellee unnecessarily delayed the raising of the Ross by going back after the pontoons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

New York Life Ins. v. Roufos
83 F.2d 620 (Sixth Circuit, 1936)
Hickman County v. Nashville Bridge Co.
66 F.2d 174 (Sixth Circuit, 1933)
United States v. Bowling
261 F. 657 (Eighth Circuit, 1919)
Ulmer v. United States
219 F. 641 (Sixth Circuit, 1915)
Walter Baker & Co. v. Gray
192 F. 921 (Eighth Circuit, 1911)
City of Memphis v. St. Louis & S. F. R. Co.
183 F. 529 (Sixth Circuit, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
160 F. 19, 1908 U.S. App. LEXIS 4169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-myrtie-m-ross-ca6-1908.