The Metropolitan Government of Nashville and Davidson County v. Barry Construction Company, Inc.

CourtCourt of Appeals of Tennessee
DecidedFebruary 24, 2011
DocketM2010-00219-COA-R3-CV
StatusPublished

This text of The Metropolitan Government of Nashville and Davidson County v. Barry Construction Company, Inc. (The Metropolitan Government of Nashville and Davidson County v. Barry Construction Company, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Metropolitan Government of Nashville and Davidson County v. Barry Construction Company, Inc., (Tenn. Ct. App. 2011).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE November 17, 2010 Session

THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY v. BARRY CONSTRUCTION COMPANY, INC., ET AL.

Appeal from the Chancery Court for Davidson County No. 04-1167-III Ellen H. Lyle, Chancellor

No. M2010-00219-COA-R3-CV - Filed February 24, 2011

This matter is before the court for a second time. The Metropolitan Government of Nashville and Davidson County initiated suit to compel two developers to complete an unfinished portion of a road in a planned unit development or to recover damages equal to the cost of completing the road if it completed the road itself. The trial court dismissed the action, finding that the amended complaint did not provide a legal basis for requiring either developer to complete the road. On appeal this Court vacated the trial court’s order and remanded the case for the court to consider the appropriate allocation of responsibility for construction of the road between the two developers. While the appeal was pending, the Metropolitan Government acquired the land and subsequently completed the unfinished portion of the road. On remand, the trial court assessed costs of constructing the road to the developers equally, but assessed the land-acquisition costs entirely to one developer. The Metropolitan Government appeals. Finding no error in the trial court’s allocation of responsibility, we affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed.

R ICHARD H. D INKINS, J., delivered the opinion of the court, in which P ATRICIA J. C OTTRELL, P.J., M.S., and A NDY D. B ENNETT, J., joined.

Sue B. Cain, J. Brooks Fox and Christopher M. Lackey, Nashville, Tennessee, for the appellant, the Metropolitan Government of Nashville and Davidson County.

Shawn R. Henry, Nashville, Tennessee, for the appellee, JCH Development Company, Inc.

1 OPINION

I. Facts and Procedural History

The Metropolitan Government of Davidson County (“Metro”) initiated this action in 2004 to compel JCH Development Company, Inc. (“JCH”) and Barry Construction Company, Inc. (“Barry”) (collectively referred to as “the developers”), developers of a planned unit development, to complete a one-thousand foot portion of Smith Springs Parkway.1 The trial court dismissed the complaint, finding that Metro failed to provide any legal basis for requiring the developers to complete the road. Metro appealed.

On February 2, 2006, while the case was on appeal, Metro entered into an agreed order with Barry, owner of that portion of the development upon which Smith Springs Parkway was located, to acquire the property to complete the missing portion of the road; JCH was not a party to the condemnation proceeding or the settlement. Metro paid Barry $32,487.00 for the property; that same year, Metro completed Smith Springs Parkway on its own initiative.

On appeal this Court held that “Metro’s amended complaint recites an adequate legal basis of requiring both developers to complete Smith Springs Parkway” and remanded the case “for consideration of the appropriate allocation of responsibility for the construction between the two developers.” Metro. Gov’t of Nashville and Davidson County v. Barry Constr. Co. and JCH Dev. Co., 240 S.W.3d 840, 853 (Tenn. Ct. App. 2007) (“Barry I”).2 JCH filed a Petition for Rehearing, contending that, because it contracted the responsibility to complete the road to Barry, it was no longer legally responsible for completing the road. This Court denied the petition, stating the following:

. . . Nothing in our February 21, 2007 opinion states that [JCH] could not contract with a third party like [Barry Construction] to complete the improvements. However, when it does so, it remains ultimately liable to [Metro] for the completion of the improvements. The question regarding the allocation of liability between [the developers] was not directly before the trial court because both developers

1 The master plan for the planned unit development called for the construction of Smith Springs Parkway as a new road designed to mitigate the traffic impacts of the development on the surrounding area.

2 The earlier opinion contains a more detailed history of the development of the project as well as the relationship between and involvement of each of them in the project.

2 were insisting that they had no obligation to complete the road. Now that we have determined that [Metro] has stated a claim against both [JCH] and [Barry] for the completion of the road, the allocation of liability between them will be a matter for the trial court to take up following remand.

The case was returned to the Chancery Court on October 19, 2007.

On November 30, 2007, JCH filed a Cross Claim against Barry seeking to be indemnified in the event the trial court allocated any financial liability to JCH. On April 16, 2009, JCH filed an Amended Cross Claim and Third Party Complaint which, inter alia, added Barry Zeitlin as a party defendant and sought to hold him personally responsible for any financial liability found on behalf of JCH. On August 14, 2009, the trial court granted a default judgment on the amended cross claim and the third party claim, holding that Barry Construction was “fully liable to JCH for damages assessed against JCH in this case,” and that “Barry Zeitlin is individually and personally liable to JCH for all damages . . . as indemnitor and unconditional guarantor of the . . . payment obligations of Barry Construction.” 3

On October 15, 2008, Metro moved for summary judgment and on November 5, 2008, Barry also filed a motion for summary judgment. On December 18, 2008, the court entered an order denying both motions; however, the court ruled that “Barry and JCH are jointly and severally liable to Metro for the costs of completing the road, whatever that amount may be determined at trial.”

A hearing was held on August 31 through September 1, 2009 to determine Metro’s costs in completing Smith Springs Parkway. On October 16 the trial court issued a Memorandum and Order granting Metro judgment in the amount of $182,733.19 jointly and severally against Barry Construction and JCH; Metro was granted judgment in the amount of $32,637.00, representing the cost of land acquisition, solely against Barry Construction. Metro appeals, asserting the following issue: “Whether the trial court erred by not finding JCH liable for Metro’s costs in completing Smith Springs Parkway.”

II. Discussion

In a non-jury case we review the record de novo with a presumption of correctness as to the trial court’s determination of facts, and we uphold those factual findings unless the evidence preponderates to the contrary. Tenn. R. App. P. 13(d). The trial court’s

3 The record does not contain the motion seeking a default judgment against Barry Construction.

3 conclusions of law, however, are accorded no presumption of correctness. See Staples v. CBL Associates, Inc., 15 S.W.3d 83, 88 (Tenn. 2000); Bain v. Wells, 936 S.W.2d 618, 622 (Tenn. 1997).

Metro contends that the trial court did not abide by this Court’s Order when it failed to assign the land acquisition costs to JCH and Barry jointly and that the failure to do so contradicts our previous ruling that JCH “remains ultimately liable” for the costs of completion of the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Staples v. CBL & Associates, Inc.
15 S.W.3d 83 (Tennessee Supreme Court, 2000)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
The Metropolitan Government of Nashville and Davidson County v. Barry Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-metropolitan-government-of-nashville-and-david-tennctapp-2011.