The Lane Construction Corporation v. Skanska USA Civil Southeast, Inc.

CourtDistrict Court, M.D. Florida
DecidedMay 3, 2024
Docket6:21-cv-00164
StatusUnknown

This text of The Lane Construction Corporation v. Skanska USA Civil Southeast, Inc. (The Lane Construction Corporation v. Skanska USA Civil Southeast, Inc.) is published on Counsel Stack Legal Research, covering District Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Lane Construction Corporation v. Skanska USA Civil Southeast, Inc., (M.D. Fla. 2024).

Opinion

UNITED STATES DISTRICT COURT MIDDLE DISTRICT OF FLORIDA ORLANDO DIVISION

THE LANE CONSTRUCTION CORPORATION,

Plaintiff,

v. Case No. 6:21-cv-164-RBD-DCI

SKANSKA USA CIVIL SOUTHEAST, INC.; and GRANITE CONSTRUCTION COMPANY,

Defendants,

v.

SALINI IMPREGILO S.P.A.; and SKANSKA-GRANITE-LANE,

Third-Party Defendants. ____________________________________

MEMORANDUM OPINION AND ORDER This cause is before the Court following a ten-day bench trial that concluded on October 27, 2023, and ripened for decision on February 15, 2024. Having considered the evidence, argument, and authority and assessed the credibility of witnesses, the Court resolves the merits under Federal Rule of Civil Procedure 52. INTRODUCTION Since February 2022, Central Florida drivers have benefited from the new I-4 express lanes running through Orlando. While these drivers no doubt noticed the construction on the highway for the preceding seven years, most probably do not know the turmoil that took place behind the scenes in the process of this project

becoming a reality. This case tells that story. Nearly a decade ago, in 2013, the Florida Department of Transportation announced the State of Florida’s largest construction project ever: a six-year,

$2 billion reconstruction of more than twenty miles of a notoriously congested section of I-4, spanning from Longwood through downtown Orlando and down past the turnpike toward the attractions. This massive “I-4 Ultimate Project” involved the top-to-bottom overhaul of fifteen exits, dozens of bridges, and

multiple general use traffic lanes—plus the construction of four express toll lanes. But the original projections for the Project proved wildly off the mark. It ended up taking a year longer and costing the State $125 million more than anticipated. And

rather than profiting off this historic Project, the three contractors who built it ended up $500 million in the hole. All of them sued each other, bringing us here. The broad strokes of the dispute are these. The Project was structured as a

public-private partnership, financed partially by the State and partially by a private concessionaire that would profit by maintaining the road over time. After a bidding process, in 2014, the State engaged I4MP—an entity made up of Skanska ID and John Laing—as the concessionaire. I4MP then engaged a design-

builder, the joint venture SGL—made up of majority partner Skanska SE and minority partners Granite and Lane—to do the construction. The construction world is a small one, and the three SGL partners had worked together before.

The partners’ relationship was cordial when construction began in 2015. But by the beginning of 2018, the Project was dramatically over budget and behind schedule. During the same period, Lane was bought out by foreign company

WeBuild, which threw a wrench into the partners’ dynamic. As the Project’s losses grew and the partners faced multimillion-dollar monthly capital calls to keep it going, they grasped for strategies to stem the tide. SGL ultimately focused on two divergent options: option #1 involved negotiating a global resolution with the

State for more funding and an extension of the Project’s completion date, while option #2 involved demanding that the concessionaire give notice to the State to terminate the Project.

SGL’s lawyers told them that the termination option would lead to ruined reputations and protracted litigation—while costs and work would continue unabated as the dispute ran its course. So at the end of 2018, all three partners

decided to pursue option #1 (settlement). But when negotiations with the State began to bear fruit, Lane—with its purse strings pulled tight by guarantor WeBuild—reversed course and decided it wanted to pursue option #2 (termination). Skanska SE and Granite disagreed, choosing—over Lane’s

objection—to accept settlement with the State at the beginning of 2020. This settlement resulted in a $125 million payment from FDOT and a near year-long extension of the completion date. Despite these concessions, the losses kept

mounting. So at the beginning of 2021, with over a year left on the Project, Lane stopped paying its share of the capital calls and sued Skanska SE instead. Lane claimed that

Skanska SE, as SGL’s managing partner, breached its fiduciary duties by acting against the best interests of the partnership in accepting the settlement over Lane’s objection. Lane’s theory was that Skanska SE was working in favor of Skanska ID, part of concessionaire I4MP, in rejecting the termination option to SGL’s

detriment. Skanska SE countersued Lane for breaching SGL’s partnership agreement by failing to pay the capital calls needed to keep the Project afloat. All three partners, the partnership, and Lane’s guarantor ended up in the suit.

Skanska SE and Granite kept funding the Project, which was completed in 2022. The Court found before trial that Lane breached the partnership contract by failing to pay capital calls. The Court conducted a bench trial in late 2023 on the

issues of whether Skanska SE breached its fiduciary duties and how much Lane owed its partners for breaching the contract. The evidence did not prove Lane’s fiduciary breach theory at trial. Rather, the overwhelming evidence established that Skanska SE acted in the best interest of SGL and its partners in rejecting the

termination option, which likely would have been ruinous for all involved, and pursuing settlement, which ended up with a very favorable deal for the partners. The evidence also established that Lane owes its partners about $80 million that it

should have paid in the first place. So we end up here, with the parties’ relationships broken but the Project completed. With that foundation, the Court makes these findings of fact and

conclusions of law. FINDINGS OF FACT1 I. The Players 1. Skanska-Granite-Lane (“SGL”) is the joint venture (“JV”) at the center

of this litigation, formed between Skanska USA Civil Southeast, Inc. (“Skanska SE”), Granite Construction Company (“Granite”), and Lane Construction Corporation (“Lane”). Salini Impregilo S.p.A. n/k/a WeBuild S.p.A.

Inc. (“WeBuild”) is Lane’s parent company. Skanska SE, Granite, Lane, SGL, and WeBuild are the parties. (JPS,2 ¶¶ 1, 8–9.) 2. Skanska SE’s President was Rich Cavallaro until October 2018; he was replaced by Don Fusco. Its in-house counsel was Michael DiPaolo, and its outside

counsel was Bruce Meller of Peckar & Abramson. (Doc. 527, p. 149:4–6; Doc. 531,

1 These facts have been established by a preponderance of credible evidence. See also infra note 8. To the extent that any of these factual findings represent conclusions of law, the Court adopts them as such, and vice versa. 2 JPS refers to the parties’ agreed facts in their Joint Pretrial Statement. (Doc. 427, pp. 33– 40.) pp. 36:20–37:23, 54:17–18, 59:6–15.) 3. Granite’s President and CEO was Jim Roberts. (Doc. 526, p. 78:13–14.)

4. Lane’s CEO was Robert Alger until June 2019; he remained on as Chairman of the Board until June 2020. (Id. at 5:20–6:2, 8:1–20; Doc. 528, pp. 130:21– 131:5, 154:18–155:6.)

5. SGL’s outside counsel were Ben Subin of Holland & Knight (“H&K”) and Brad Copenhaver of Vezina, Lawrence & Piscitelli (“VLP”). (Doc. 530, p. 62:9– 17; Doc. 531, p. 159:16–18.) 6. WeBuild’s Deputy General Manager was Ignacio Botella. Its CFO was

Gianfranco Catrini. (Doc. 526, pp. 77:20–24, 101:16–23.) 7. The Florida Department of Transportation (“FDOT”) is the state entity that owns and contracted the public-private partnership (“P3”) construction

project called the I-4 Ultimate Project (“Project”). (JPS, ¶¶ 1, 10.) 8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Storfer v. Guarantee Trust Life Insurance
666 F.3d 1277 (Eleventh Circuit, 2012)
Gracey v. Eaker
837 So. 2d 348 (Supreme Court of Florida, 2002)
Brigham v. Brigham
11 So. 3d 374 (District Court of Appeal of Florida, 2009)
Sullivan v. Streeter
485 So. 2d 893 (District Court of Appeal of Florida, 1986)
Telemundo Network, Inc. v. Spanish Television Services, Inc.
812 So. 2d 461 (District Court of Appeal of Florida, 2002)
New Holland, Inc. v. Trunk
579 So. 2d 215 (District Court of Appeal of Florida, 1991)
Atlantic Coast Line Railroad v. Saffold
178 So. 288 (Supreme Court of Florida, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
The Lane Construction Corporation v. Skanska USA Civil Southeast, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-lane-construction-corporation-v-skanska-usa-civil-southeast-inc-flmd-2024.