The Kaiser Wilhelm der Grosse

106 F. 963, 1901 U.S. Dist. LEXIS 361
CourtDistrict Court, S.D. New York
DecidedJanuary 31, 1901
StatusPublished
Cited by8 cases

This text of 106 F. 963 (The Kaiser Wilhelm der Grosse) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Kaiser Wilhelm der Grosse, 106 F. 963, 1901 U.S. Dist. LEXIS 361 (S.D.N.Y. 1901).

Opinion

BROWN, District Judge.

Twenty-three harbor tugs claim salvage compensation in the above 19 libels, for services rendered to the steamship Kaiser Wilhelm der Grosse in extricating her-from fire at [964]*964the Hoboken docks at about 4 o’clock in the afternoon of June 30, 1900.'

The fire was one of the most rapid and destructive that has ever .occurred to the shipping in this port. It broke out at the docks of the North German Lloyd Steamship Company, in which many lives and much merchandise were lost, and three large steamers of the .company were almost wholly destroyed. The largest steamer, the Kaiser Wilhelm der Grosse, with the assistance of the libelants’ tugs, escaped with, but comparatively little damage. Some of the lifeboats on the hurricane deck were damaged and numerous glass ports were cracked before the vessel could get out of her slip. These damages amounted to but a few thousand dollars, and they were repaired in season to enable the -steamer to malee her regular trip, with passengers and freight, a few days later. The libelants contend that without ,the aid of the tugs the Kaiser would have become a wreck like the other three steamers of the company; the respondents claim that she could have got out by her own steam, somewhat later indeed, but probably without any very great damage. The value of the Kaiser and her contents was about $2,000,000; that of the 23 salving tugs, about $300,000.

The fire started among some cotton in a shed on the bulkhead at the shore end of the company’s pier No. 3. This shed extended northward continuously along the river front past pier 2 and pier 1 of the same company to the Thingvalla pier next above. In consequence of .the presence of inflammable materials, the fire soon after it started ran northward through the shed with great rapidity, almost as through a flue. As Hie fire advanced upwards, a brisk wind drove the flames into the sheds that ran down piers 2 and 1, so that within 10 or 15 minutes from the time the fire broke out the whole vicinity 'of the bulkheads was enveloped in smoke and flame, and the upper part of the sheds on piers 1 and 2 were ablaze. Four of the company’s steamships, were moored alongside of piers 1 and 2 with their bows in and nearly or quite up to the bulkhead. The Kaiser Wilhelm was on the south side of pier 1. The Salle and the Bremen, respectively on the,south and north sides of pier 2, and the Main, on the north side of pier 1, were in flames before either could be got out of the slips. The exit of the Main was obstructed by lighters which •were outside of her in the slip, and it is suggested that her bows’ were also aground. However this may have been she was a mass of flames before she could be removed and her officers and crew were driven overboard. On the Salle many persons were confined by the flames below deck before any word of danger came to them, and perished. Numerous persons on the piers and on the other three steamers, as the flames advanced, were driven down the piers and into the water or upon other boats in the slips, where most of them were ■picked up by the various tugs that arrived, though quite a number were drowned.

,.,The b.ow of the Kaiser Wilhelm der Grosse, on the south side of pier i, was nearly or quite up to the bulkhead. She was 650 feet long by 66 feet, beam, and she was at that'time breasted off by spars [965]*965about 20 feet from the southerly side of pier 1 in order to enable her to coal from boats on her starboard side. Pier 1 was covered with a wooden shed extending down about as far as to the stern of the Kaiser. An extension of 200 feet had been added to the original pier which was not covered by a shed, and pier 1 was so much longer than the piers to the north and south of it. The Are was noticed from the Kaiser about the time it broke out, and her officers perceiving a few minutes afterwards that the Are was spreading to the northward, ordered all the lines and spar braces to be cast off and that the ship should be worked astern out of the slip. The lines and STMirs were speedily east off, and a hawser running to the third bollard, about 110 feet from the outer end of the pier, was applied to the stern capstan, and the vessel was thereby very slowly warped astern nearly as far as to the third bollard. It was at about that time that the Easton, the Arst of the tugs, arrived. The only steam which the Kaiser then had on was in one of her 13 main boilers,; which was used instead of a donkey engine for all the general pur7 poses of the ship in port.

Most of the libelants’ witnesses say that when their tugs arrived, the Kaiser was still and not moving astern. I am satisAed, however, from all the evidence, that this is a mistake and that even when the Easton arrived the Kaiser was moving astern, though very slowly; that the Are was already attacking the shed on pier 1, and that the great heat from this and the burning bulkhead had set Are to the forward starboard boats on her hurricane deck, though this was quickly extinguished by her own hose. Her officers and men, however, were soon driven aft. The Are on the bulkhead at that time was so strong that with the wind blowing directly toward the ship, there is no doubt that the Are would very soon have been running down the shed on the pier much faster than the Kaiser could move out by her own steam. The necessity for the assistance of tugs, therefore, to expedite her removal from the slip was very great. The anxiety of her officers for immediate assistance is sufficiently evident from their hails for help and their taking all ropes offered by the tugs on her port quarter, after six tugs were already pulling at her stern.

While it is impossible to say with certainty how great the damage to the Kaiser would have been without any help from the tugs, I have no doubt that their services in expediting her exit from the slip were of great value. She was unable to warp- astern by her aft capstans over 200 feet, i. e. less than one-third of her length, and her slow movement and the set of the ebb tide would probably have car-, ried her across the corner of pier 2 exposing her forward parts like' those of the Bremen to heavy damage. She indeed had a Are pump in perfect working order, which, as I have said readily extinguished the little Are that broke out in the boats upon her hurricane deck; but in the smoke, heat and Aame that rapidly extended down pier 1, she would have been utterly unable by her own Are pump to pre-; vent very great damage to the steamer, had her removal beyond the1 shed on pier 1 been delayed even a few minutes longer. :

[966]*966The moral certainty of large loss except for the assistance of the tugs, is in the present case the chief ground of a substantial award. None of the other recognized circumstances enhancing salvage allowances exist in the present case in any marked degree. There was little or no danger to the salving tugs or to the crews that manned them. They kept at a safe distance from the fire, outside of the Bremen’s stern, which was not burned,* and in the lee of the Kaiser’s huge bulk. The main service of the tugs was also very short, the Kaiser being hauled out into the river and out of actual danger in probably less than 15 minutes, though some further service was necessary in turning her around, head down stream, and coming soon after to anchor off Canal street; a number of the tugs also remained by her. until an hour or two afterwards, when, having got up more steam of her own, she went, attended by several of the tugs, to a better anchorage off Forty-Second street. A few remained by her, as requested, until the next morning.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brittingham v. Tugboat Underwriting Syndicate
277 A.2d 8 (Court of Appeals of Maryland, 1971)
The Johnson Lighterage Co. No. 24
248 F. 74 (Third Circuit, 1918)
The Johnson Lighterage Co. No. 24
240 F. 435 (D. New Jersey, 1917)
J. M. Guffey Petroleum Co. v. Borison
211 F. 594 (Fifth Circuit, 1914)
The Priscilla
153 F. 476 (S.D. New York, 1907)
The Bremen
111 F. 228 (S.D. New York, 1901)
The Coya
108 F. 413 (S.D. New York, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
106 F. 963, 1901 U.S. Dist. LEXIS 361, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-kaiser-wilhelm-der-grosse-nysd-1901.