The Interpublic Group Of Companies, Inc. v. On Mark Engineering Co.

381 F.2d 29
CourtCourt of Appeals for the First Circuit
DecidedJuly 26, 1967
Docket20645_1
StatusPublished
Cited by3 cases

This text of 381 F.2d 29 (The Interpublic Group Of Companies, Inc. v. On Mark Engineering Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Interpublic Group Of Companies, Inc. v. On Mark Engineering Co., 381 F.2d 29 (1st Cir. 1967).

Opinion

381 F.2d 29

The INTERPUBLIC GROUP OF COMPANIES, INC., a corporation,
McCann-Erickson, Inc., a corporation, and
Interpublic Inc., a corporation, Appellants,
v.
ON MARK ENGINEERING CO., a corporation, and Security First
National Bank, Appellees.

No. 20645.

United States Court of Appeals Ninth Circuit.

July 26, 1967.

Rodney K. Potter, O'Melveny & Myers, Los Angeles, Cal., for appellant.

Latham & Watkins, Los Angeles, Cal., Ira M. Price, Sheppard, Mullin, Richter & Hampton, Los Angeles, Cal., for appellees.

Before WASHINGTON,* MERRILL, and ELY, Circuit Judges.

ELY, Circuit Judge:

In this opinion the three appellants, defendants below, will, collectively, be called 'McCann.' Their relationship is set forth in the margin.1 They were adjudged to be liable in damages for breach of contract. The principal appellee, plaintiff below, will be referred to as 'On Mark.' The other appellee is a national banking association, which, as plaintiff in intervention, seccessfully asserted its claim under an assignment from On Mark. It will be called 'Bank.' The jurisdiction of the District Court rested upon the diverse citizenship of the parties and the requisite amount in controversy. 28 U.S.C. 1332. Our power of review is conferred by the provisions of 28 U.S.C. 1291.

The contract in question is evidenced by two written agreements. One is entitled 'Lease Agreement,' and the other is entitled 'Option to Purchase Aircraft.' The two documents were executed concurrently on July 10, 1959, and the District Court determined, pursuant to stipulation, that the two were intended by the parties to be construed together and to 'constitute a single, entire agreement.' The purpose of the writings was to define the rights of On Mark and McCann in connection with an airplane which was the subject of the contract.

The background of the written contract is revealed by the testimony, some of which was received over objection. On Mark was engaged, generally, in the business of buying and selling airplanes. McCann desired, for its own use, a plane of the luxurious type, one described by the parties as an executive aircraft. In early 1959, discussions were begun between representatives of McCann and On Mark, the discussions centering upon the acquisition by McCann of an A-26 military aircraft to be remodeled, or converted, by On Mark according to the specifications of McCann. After detailed specifications were supplied, On Mark first quoted a purchase price of $400,000. Later, after the quoted price had been reduced to $385,000, McCann communicated its preference for a lease arrangement, coupled with an option to purchase. To this, On Mark's representative replied, in effect, that there would be no objection 'so long as (his company) was substantially financially rewarded in the same manner as the sale.' Subsequently, On Mark sent a telegram in which it confirmed its offered price of $385,000 and added, 'Will furnish very attractive lease with option to purchase to cover five (5) year period.' When, thereafter, McCann requested a quotation of rentals for a 60-month lease period, On Mark made inquiry of a leasing company concerning formulae. It then informed McCann's representative, orally, that the rental would be $7,747 per month for 60 months and that McCann would be given 'an option purchase price at the end of the lease when the sixty-month rentals had been paid, for $32,950.' There followed the preparation of the two documents which constitute the contract.

The lease agreement called for the quoted monthly rental payments of $7,747 for 60 months, a total of $464,820. The rental payments for the first two months and the last three months of the 60-month term were payable with the execution of the lease. The payments thereafter were to commence on a date two months after the delivery of the aircraft 'and monthly thereafter on the day of the month said delivery shall have been made, until three months prior to the end of the term. * * *' On Mark agreed to deliver the aircraft to McCann for flight testing no later than October 14, 1959, and finally to deliver the aircraft no later than October 24, 1959; however, it was provided that On Mark, so long as it applied its best efforts, should not be in default if it should be prevented from delivering the plane on the agreed date by factors beyond its control. Actual delivery to McCann was not accomplished until December 18, 1959, but McCann accepted the plane and retained its possession and operated it until June 28, 1962.

Under the terms of the option agreement, McCann might purchase the plane for $32,950 by giving On Mark 15 days' prior written notice of its intention to exercise the option. It was provided that the option should be exercised 'between July 15, 1964 and August 15, 1964.'

On February 8, 1960, following the delivery of the plane approximately seven weeks before, On Mark borrowed $375,000 from the Bank, exchanging its promissory note and, as security, a chattel mortgage on the aircraft and an assignment, for the necessary period, of the moneys payable by McCann.

From the foregoing, it is seen that, had On Mark delivered the plane to McCann in October, 1959, as originally scheduled, the last monthly rental payment would have been made in July, 1964. This fact becomes relevant in considering that provision of the option agreement specifying that McCann might exercise the option between July 15, 1964 and August 15, 1964.

After taking delivery of the plane on December 18, 1959, McCann made the rental payments required by the contract and, as previously noted, used the plane until June 28, 1962. On that day, the aircraft, while being operated by McCann, was involved in an accident. The agreement provided that McCann was obliged to maintain the plane and to keep it in good condition. The agreement also provided that, should the plane be damaged, On Mark should make repairs promptly if it should determine that repair was economically feasible. Insurance against damage to the plane had been procured and maintained by McCann pursuant to the agreement.

After the accident, the plane was disassembled and transported to On Mark's plant in California, and On Mark began to make the necessary repairs. It advised McCann that it would complete its work and have the plane available for redelivery on February 22, 1963. Thereafter, McCann, claiming that On Mark had failed to perform its contractual obligations as they pertained to the repair, refused to accept redelivery of the aircraft. There is ample evidence to support the District Court's finding that 'shortly after the occurrence of the accident, without disclosing its intention to On Mark, McCann determined that it would not again take possession of the A-26 aircraft whether or not it was later repaired and also determined to secure another plane for its permanent use in place of the A-26 aircraft leased from On Mark.'

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
381 F.2d 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-interpublic-group-of-companies-inc-v-on-mark-engineering-co-ca1-1967.