The Ingalls Iron Works Company v. Fruehauf Corporation

518 F.2d 966, 1975 U.S. App. LEXIS 12876
CourtCourt of Appeals for the Fifth Circuit
DecidedSeptember 4, 1975
Docket73-3943
StatusPublished
Cited by23 cases

This text of 518 F.2d 966 (The Ingalls Iron Works Company v. Fruehauf Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Ingalls Iron Works Company v. Fruehauf Corporation, 518 F.2d 966, 1975 U.S. App. LEXIS 12876 (5th Cir. 1975).

Opinion

JOHN R. BROWN, Chief Judge:

This is a contract action brought by The Ingalls Iron Works Company (In-galls), an Alabama subcontractor supplying structural steel, against Fruehauf Corporation (Fruehauf), a Michigan Cor *967 poration constructing a building in Alabama, for the $10,556.56 balance due on the purchase order and for $6,965.00 due for extra work performed. Without a trial the District Judge found that a novation transferring to the general contractor both the rights and contract duties of Fruehauf vis-a-vis Ingalls had been effected by the parties and granted Fruehauf’s motion for summary judgment. Because the contract language itself and the affidavits submitted by the parties create a genuine issue as to one if not more material facts in the case, we find that summary judgment was inappropriate and reverse.

At the time judgment was rendered, the District Judge had before him the pleadings, the contract provision, the affidavits and counter affidavits offered by the parties. To support the judgment on appeal, the same materials must be sufficient to eliminate altogether the likelihood that the material allegations of Ingalls’ complaint are true or that there are unresolved questions of fact in Fruehauf’s defense of novation. F.R. Civ.P. 56; Guidry v. Continental Oil Co., 5 Cir., 1965, 350 F.2d 342; Smoot v. State Farm Mutual Automobile Ins. Co., 5 Cir., 1962, 299 F.2d 525.

Looking at the case then from the view most favorable to Ingalls, the evidence demonstrated that Fruehauf sought bids on the structural steel components prior to letting the general contract. Specifically, an Invitation to Bid was issued 1 containing this provision:

INVITATION TO BID

You are invited to submit a proposal to perform work for the complete Fruehauf Division, Sales and Service Building. . . .

Sealed bids are to be delivered or postmarked no later than midnight May 29, 1969. . . .

Contract documents will be written with the General Contractor listed as Prime Contractor. The Structural Steel, Steel Joists, Metal Decking, Plumbing, Heating, Ventilating, Sprinklers, and similar other trades needed for the performance of all phases of the work, will be considered as Subcontractors. The Prime Contractor will be held responsible for performance of all Subcontractors; excepting the Subcontractor for structural steel, steel joists, metal decking and miscellaneous iron unless the responsibilities of this Subcontractor are assigned to the General Contractor under conditions cited on Page IB-2. The Prime Contractor will handle all negotiations directly with the Owner. .

In the interest of expediting the availability of Structural Steel, Steel Joists, Metal Decking and Miscellaneous Iron, the Owner is awarding a separate contract for these materials. The contract for this work is to be assigned, if the Owner elects to do so, to the successful bidder, after opening the bids for general construction. The successful bidder will then include this supplier as one of his Subcontractors and will thereafter be responsible for all aspects of this work as though he had negotiated directly with the supplier involved. The cost, if any, for inclusion of this Subcontractor’s work into the General Contract Work is to be included in the basic proposal for performing all aspects of the work.

The name of the successful structural steel contractor will be forwarded directly to each General Contractor immediately upon award of the structural steel contract. [Emphasis added.]

In accepting the quoted bid of Ingalls, Fruehauf replied with a purchase order that included this provision:

In accordance with the bidding specifications, this order may be assigned to the General Contractor at the Owners [sic] option. You will be formally ad *968 vised of the Owners [sic] decision on this item very shortly.

However, the boilerplate provisions of the purchase order contained a non-assignment clause. 2 Lastly, the purchase order contract contained payment terms that required payments to be made monthly less retainage with final payment on acceptance and receipt of all releases. 3

Ingalls agreed to the purchase order dated April 23, 1969 and was operating under it when Fruehauf let the general contract on September 8, 1969 to Earl A. Boudrow & Sons (Boudrow). 4 As the Invitation for Bids contemplated, Boudrow’s bid included an express willingness for the assignment to it of Ingalls’ structural steel contract for which it was to receive a 5% override. 5 And responsively, the general contract contained its own language of prospective assignment, 6 although Ingalls was never formally advised by Fruehauf that the steel contract had been assigned to Boudrow despite the language prescribing that formal notice would be given at the time of assignment to the general contractor.

But Ingalls for all practical purposes recognized the appointment of the general contractor and throughout September and October- — while the structural work was drawing to completion — In-galls invoiced Friiehauf and Boudrow jointly. These invoices were sent to Fruehauf’s home office in Detroit. In-galls asserts that these invoices exclude any possibility that it intended to release Fruehauf and create a novation with Boudrow.

In response Fruehauf submitted to the Court copies of two mechanics lien releases 7 issued by Ingalls to Fruehauf. *969 Fruehauf contends that these releases demonstrate Ingalls’ assent to the novation.

To counter this argument, Ingalls points to the contract terms (see note 3, supra) requiring the final payment to be made after the owner had received “all releases.” This provision made such releases a precondition to final payment. Furthermore, Ingalls contends that Alabama law requires the Courts to look further than the mere mechanics lien releases to determine the intent of the parties. 8 And a formal release expressly required as a precondition to payment which on that hypothesis was still unpaid could not have the effect of extinguishing the debt for which the release was exacted. See also Mitchell v. Cobb, 270 Ala. 346, 118 So.2d 918 (1960). At least it would present questions of fact.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ward Conner v. LaFarge North America, Inc.
343 F. App'x 537 (Eleventh Circuit, 2009)
Provident Life & Accident Insurance v. Goel
274 F.3d 984 (Fifth Circuit, 2001)
In Re Jones
206 B.R. 569 (M.D. Alabama, 1997)
Hale v. Townley
Fifth Circuit, 1994
Amerinet, Inc. v. Xerox Corp.
972 F.2d 1483 (Eighth Circuit, 1992)
Amerinet, Inc. v. Xerox Corporation
972 F.2d 1483 (Eighth Circuit, 1992)
Welch v. Celotex Corp.
951 F.2d 1235 (Eleventh Circuit, 1992)
Welch v. Celotex Corporation
951 F.2d 1235 (Eleventh Circuit, 1992)
DuPont v. Yellow Cab Co. of Birmingham
565 So. 2d 190 (Supreme Court of Alabama, 1990)
Downing v. Dial
426 N.E.2d 416 (Indiana Court of Appeals, 1981)
Hemisphere National Bank v. District of Columbia Insurance Guaranty Ass'n
412 A.2d 31 (District of Columbia Court of Appeals, 1980)
Boswell v. Lyon
401 N.E.2d 735 (Indiana Court of Appeals, 1980)
Nardone v. Reynolds
538 F.2d 1131 (Fifth Circuit, 1976)
Davis v. Davis
526 F.2d 1286 (Fifth Circuit, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
518 F.2d 966, 1975 U.S. App. LEXIS 12876, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-ingalls-iron-works-company-v-fruehauf-corporation-ca5-1975.