The Industrials v. Federal Energy Regulatory Commission

426 F.3d 405, 368 U.S. App. D.C. 134, 168 Oil & Gas Rep. 693, 2005 U.S. App. LEXIS 22162, 2005 WL 2582020
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 14, 2005
DocketNos. 04-1250, 04-1253, 04-1257
StatusPublished
Cited by1 cases

This text of 426 F.3d 405 (The Industrials v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Industrials v. Federal Energy Regulatory Commission, 426 F.3d 405, 368 U.S. App. D.C. 134, 168 Oil & Gas Rep. 693, 2005 U.S. App. LEXIS 22162, 2005 WL 2582020 (D.C. Cir. 2005).

Opinions

STEPHEN F. WILLIAMS, Senior Circuit Judge.

Firms that ship gas on pipelines sometimes take more — or less — gas out of the pipeline at the end of the shipment than they had delivered upstream. Periodically (usually monthly), the resulting imbalances are adjusted by a “cash-out.” But the cash-out price may create perverse incentives. Specifically it may create an incentive to “game” the system, deliberately taking more or less gas when it appears likely that the ultimate cash-out price will be such as to make deviations profitable. For example, if the cash-out price is set at the average monthly price (as was true for the pipeline involved in this case, Northern Natural, before the orders at issue here),1 and prices have been rising for the month’s first 25 days, there is a considerable likelihood that the end-of-the-month price will be above the monthly average. Shippers may respond by deliberately taking extra gas from the system, reselling it in the spot market, and paying for it in the cash-out at the lower (monthly average) rate. Northern’s system took account of the problem to some degree by calculating the average monthly price on a 10-day lag (from the 11th day of the month to the 10th day thereafter), Joint Appendix (“J.A.”) 73, 83, but even this left some incentive for arbitrage at the very end of the month.

Where such temptations to arbitrage exist, the pipeline’s net imbalances are naturally likely to rise. Although the pipeline can recover the net expense in its rates, individual shippers will not bear the resulting cost in the proportion that their conduct caused the expense. In an extreme case, the imbalances could make it hard for the pipeline to manage its load.

In 2003 Northern filed a proposal under § 4 of the Natural Gas Act, 15 U.S.C. § 717c, to change its cash-out mechanism so as to eliminate this arbitrage opportunity. Under the proposal a shipper that took more gas than it delivered in the course of a month would pay Northern for the net excess at the highest of the five weekly average prices applying to that month. If a shipper took out less than it delivered, Northern would pay the shipper at the lowest of the five weekly averages.

In two orders the Federal Energy Regulatory Commission approved a slightly modified version of Northern’s proposal. Northern Natural Gas Co., 105 FERC ¶ 61,172 (2003), order on reh’g, 107 FERC ¶ 61,252 (2004). Various consumers of gas that is delivered on Northern, buyers of Northern’s transportation services, and producers of natural gas petition here for [136]*136review. They attack the orders as inconsistent with the principles the Commission had developed in Order No. 637, Regulation of Short-Term Natural Gas Transportation Services, and Regulation of Interstate Natural Gas Transportation Services, FERC Stats. & Regs. [Regs. Preambles 1996-2000] (CCH) ¶ 31,091 (2000) (“Order No. 637”), order on reh’g, Order No. 637-A, FERC Stats. & Regs., [Regs. Preambles 1996-2000] (CCH) ¶31,-099 (2000) (“Order No. 637-A”), order on reh’g, Order No. 637-B, 92 FERC ¶ 61,-062 (2000), particularly claiming that Order No. 637 requires that any “penalties” be justified by a need to protect system reliability. They also assert deviation from later Commission decisions purporting to apply Order No. 637. Because of these claimed deficiencies the orders are said to be arbitrary and capricious. See 5 U.S.C. § 706(2)(A). Further, petitioners claim that the Commission lacked substantial evidence. 15 U.S.C. § 717r(b). We deny, the petitions.

* * * * $ *

In Order No. 637 the Commission adopted what is now codified as 18 C.F.R. § 284.12(b)(2)(v), stating that a pipeline may include penalties in its tariff “only to the extent necessary to prevent the impairment of reliable service.” But Order No. 637 also says that pipelines “may be able to change the methods by which they cash-out imbalances to eliminate the incentives for shippers to borrow gas from the pipeline because the cash-out price is less than the market price for gas.” Order No. 637 at 31,314-15. This suggests at least that pipelines may adjust their cash-out mechanisms to “eliminate” arbitrage incentives without showing that the change is necessary to prevent the impairment of reliable service. And in Order No. 637-A the Commission said that the existence of arbitrage “demands that pipelines revise the level and structure of their penalty provisions to minimize the opportunities for arbitrage.” Order No. 637-A at 31,-607. This language indicates that “penalty” is not a magic word that automatically triggers the system-reliability criterion. Rather, the Commission’s point is that pipelines may properly seek to deter arbitrage. Yet, lest cash-out rules unduly limit shipper flexibility, pipelines’ efforts against arbitrage should not go too far. As we shall see, petitioners have failed to show that the present orders deviated from those principles.

Commission decisions after Order No. 637 add some specificity as to when pipelines have gone too far in the effort to reduce arbitrage incentives. For example, the Commission has rejected mechanisms that provided cash-outs for imbalances measured over periods much shorter than a month. ANR Pipeline Co., 103 FERC ¶ 61,252, 2003 WL 21246921 (2003), order on reh’g, 105 FERC ¶ 61,236, 2003 WL 22718896 (2003) (five days); Williams Gas Pipelines Central, Inc., 100 FERC ¶ 61,232, 2002 WL 2017167 (2002), order on reh’g, 102 FERC ¶ 61,119 (2003) (daily). The shorter the period of calculation, the more stringent the sanction is likely to be, as the shipper gets less benefit from the netting out of short-term positive and negative imbalances. As a result, the proposals went too far in reducing arbitrage incentives. And the Commission has similarly rejected systems that would have used as benchmarks the high/low of average prices from periods of less than one week, as in Transcontinental Gas Pipe Line Corp., 91 FERC ¶ 61,004, 2000 WL 341109 (2000).

No Commission decision has passed on a proposal identical to Northern’s. But one comes close. In Gulf South Pipeline Co., 97 FERC ¶ 61,069, 2001 WL 1282893 (2001), order on reh’g, 98 FERC ¶ 61,068, 2002 WL 180900 (2002), the pipeline al[137]*137ready used a mechanism similar to Northern’s proposal here (imbalance calculation each month, using the high/low of weekly averages). Gulf South proposed the addition of a fifth week in order to curtail the arbitrage incentive created by the mechanism’s end-of-the-month days, during which the cash-out price could be known to a penny. In the presence of an obvious arbitrage incentive and evidence of substantial resulting imbalances, the Commission approved the change.

Much of the parties’ discussion revolves around a set of orders relating to Texas Gas. Texas Gas Transmission Corp., 95 FERC ¶ 61,093, 2001 WL 419176 (2001), order after tech, conf, 96 FERC ¶ 61,318, 2001 WL 34076575 (2001), order on reh’g, 97 FERC ¶ 61,349 (2001).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Indust v. FERC
426 F.3d 405 (D.C. Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
426 F.3d 405, 368 U.S. App. D.C. 134, 168 Oil & Gas Rep. 693, 2005 U.S. App. LEXIS 22162, 2005 WL 2582020, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-industrials-v-federal-energy-regulatory-commission-cadc-2005.