The Howard P. Foley Company v. Phoenix Engineering & Supply Co.

819 F.2d 60, 4 U.C.C. Rep. Serv. 2d (West) 1041, 1987 U.S. App. LEXIS 6438
CourtCourt of Appeals for the Fourth Circuit
DecidedMay 18, 1987
Docket86-3975
StatusPublished

This text of 819 F.2d 60 (The Howard P. Foley Company v. Phoenix Engineering & Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Howard P. Foley Company v. Phoenix Engineering & Supply Co., 819 F.2d 60, 4 U.C.C. Rep. Serv. 2d (West) 1041, 1987 U.S. App. LEXIS 6438 (4th Cir. 1987).

Opinion

*61 ERVIN, Circuit Judge:

I.

Appellant, The Howard P. Foley Company (“Foley”), sought to recover contract damages from appellee, Phoenix Engineering & Supply Company (“Phoenix”), in the United States District Court for the Eastern District of Virginia. Foley is a District of Columbia corporation with its principal place of business in Alexandria, Virginia. Phoenix is a New Jersey corporation with its principal place of business in Engle-wood, New Jersey. Foley is an electrical contractor; Phoenix supplies electrical fixtures.

In the summer of 1984, Foley bid on the electrical work for the renovation of the Willard Hotel in Washington, D.C. The general contractor for the Willard Hotel was the George Hyman Construction Company. Foley was simultaneously involved as a subcontractor in the Prudential Office Building project, a separate job.

Part of the electrical work for the Willard Hotel, on which Foley bid, was the installation of fluorescent lighting fixtures. A representative of Foley testified that the original bidding documents required bidders to submit two prices for these fixtures. One price assumed the use of brand name “Keene” fixtures; the other price assumed the use of brand name “Day-brite” fixtures. The owner of the hotel reserved the right to make the final decision on which brand of fixture would be supplied in the actual renovation. Foley was awarded the contract for the Willard Hotel in September, 1984.

In late August or early September, 1984, a Phoenix sales representative, Joseph McGarty, discussed the Willard Hotel project with William Hayden, an assistant manager at Foley. The two companies, Foley and Phoenix, were negotiating at the same time on the Prudential Office Building project. Phoenix sent a bid to Foley for work identified as “Your inquiry: Willard Hotel Office Building” and dated “9/12/84”. 1 This bid, for a total of $395,-000 worth of lighting fixtures, listed each item that Phoenix would supply and was prefaced by the statement: “Gentlemen: We submit the following with manufacturers on which we guarantee approval.” The bid then specifically listed “Keene” fixtures in a number of places. However, beside each entry that referred to “Keene” fixtures was an asterisk and the statement: “We reserve the privelege [sic] to furnish the specified DAY-Brite fixtures in lieu of Keene fixtures.”

On November 11, 1984, Hayden of Foley met with McGarty of Phoenix to discuss the Phoenix offer for the Willard Hotel project. The Foley representative testified that the purpose of the meeting was to confirm that Phoenix was willing to supply “Keene” fixtures at the indicated price. The district court judge found, however, based on the testimony of McGarty, that Phoenix indicated at this meeting that it would try to get the “Keene” fixtures approved by the owner but “did not indicate that Phoenix was waiving its right to furnish substitutions as provided in their ... quotation.” The judge found further that McGarty initialed estimate sheets which showed “Keene” fixtures, but that McGarty left the meeting believing that Phoenix still had the privilege to substitute other types of fixture.

Two days later, Foley sent Phoenix a purchase order for the Willard Hotel job. The purchase order called for “Keene” fixtures to be supplied at a total contract cost of $421,000. The purchase order indicated that it was “confirming Mac Hayden to Joe McGarty”; it also had printed on the bottom of every page, “You are to notify us at once if you cannot comply with all the terms of this order. The terms and condi *62 tions printed on the reverse side of this order are an integral part hereof.” The reverse side of each page set forth a number of conditions that would be relevant to this litigation, if this purchase order were deemed to embody the contract between the parties. 2 Phoenix did not object to anything in the purchase order, although it did respond in writing to Foley on November 20, 1984, thanking Foley for the orders and requesting credit information “so we can review the credit terms.”

The judge below concluded that, at this point in the negotiations between Foley and Phoenix on the Willard Hotel job, there was no contract, because the parties’ minds had not “met” on the question of which light fixtures would be provided. The district court viewed Phoenix’s reservation of the privilege to supply “Day-Brite” fixtures as integral to the Phoenix offer, while the court viewed the Foley purchase order as a purported acceptance of the “unconditional offer to supply ‘Keene’ fixtures and only ‘Keene’ fixtures.”

This view of the evidence cannot readily be squared with the ensuing events. In February, 1985, Phoenix submitted shop drawings for the Willard Hotel specifically requesting the use of “Day-Brite” fixtures instead of “Keene” fixtures. Foley did not object to Phoenix’s attempt to have “Day-Brite” fixtures approved. Indeed, the communications regarding the attempt to gain approval for “Day-Brite” fixtures appear to have flowed through Foley. The project architect, in a letter of March 28, 1985, to the general contractor, that was passed in turn to Foley, determined that the “Day-Brite” fixtures were not of the same quality as the “Keene” fixtures and did not meet the specifications for the Willard Hotel project. The district court’s view, that Foley’s purchase order of November 13, 1984, was unconditionally premised on Phoenix’s supplying “Keene” fixtures, is belied by the fact that Foley cooperated in the later attempt to have Phoenix supply “Day-Brite” fixtures. Clearly, the agreement between Phoenix and Foley was something other than what the court below understood it to be.

On April 4,1985, Phoenix informed Foley that it would not supply the “Keene” fixtures unless Foley increased the purchase price from $421,000 to $509,000. Foley refused and demanded that Phoenix supply “Keene” fixtures at the contract price. When Phoenix refused to do so, Foley covered in the market. Foley purchased the “Keene” fixtures for $523,300, or $121,463 more than the original price under the contract with Phoenix. Foley estimated that it incurred $13,421 in additional expenses caused by the delay in installing the fixtures, although since the court below concluded that no contract ever existed between the parties, it did not determine damages.

II.

Under Virginia law, which the court below applied and the relevance of which the parties do not contest, the question of what representations were made in a contract negotiation is a question for the fact-finder, but the ultimate issue of contract vel non is a question of law. See Jessee v. Smith, 222 Va. 15, 278 S.E.2d 793 (1981); Valjar, Inc. v. Maritime Terminals, Inc, 220 Va. 1015, 265 S.E.2d 734 (1980); Main-Atlantic *63 Corp. v. Francis I. DuPont & Co., 213 Va. 180, 191 S.E.2d 211 (1972).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jessee v. Smith
278 S.E.2d 793 (Supreme Court of Virginia, 1981)
Main-Atlantic Corp. v. Francis I. duPont & Co.
191 S.E.2d 211 (Supreme Court of Virginia, 1972)
Valjar, Inc. v. Maritime Terminals, Inc.
265 S.E.2d 734 (Supreme Court of Virginia, 1980)
Durham v. National Pool Equipment Co.
138 S.E.2d 55 (Supreme Court of Virginia, 1964)
Shpilberg v. Merrill Lynch, Pierce, Fenner & Smith, Inc.
535 S.W.2d 227 (Kentucky Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
819 F.2d 60, 4 U.C.C. Rep. Serv. 2d (West) 1041, 1987 U.S. App. LEXIS 6438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-howard-p-foley-company-v-phoenix-engineering-supply-co-ca4-1987.