THE HOLDER GROUP, INC. VS. PIKE CONSTRUCTION, CO., LLC (L-4909-15, ESSEX COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedNovember 6, 2019
DocketA-5098-17T1
StatusUnpublished

This text of THE HOLDER GROUP, INC. VS. PIKE CONSTRUCTION, CO., LLC (L-4909-15, ESSEX COUNTY AND STATEWIDE) (THE HOLDER GROUP, INC. VS. PIKE CONSTRUCTION, CO., LLC (L-4909-15, ESSEX COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
THE HOLDER GROUP, INC. VS. PIKE CONSTRUCTION, CO., LLC (L-4909-15, ESSEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2019).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-5098-17T1

THE HOLDER GROUP, INC.,

Plaintiff-Appellant,

v.

PIKE CONSTRUCTION CO., LLC, and JEFFREY L. ABRAMS,

Defendants-Respondents. ____________________________

Argued September 17, 2019 – Decided November 6, 2019

Before Judges Yannotti, Hoffman and Currier.

On appeal from the Superior Court of New Jersey, Law Division, Essex County, Docket No. L-4909-15.

Jeffrey S. Mandel argued the cause for appellant.

John D. Horowitz argued the cause for respondents.

PER CURIAM

Plaintiff, a construction management firm owned by Andrew Holder, filed

this action in July 2015, alleging that defendants breached a joint venture agreement. Plaintiff appeals from Law Division orders granting summary

judgment in favor of defendants and denying its motion for partial summary

judgment. Plaintiff also challenges the trial court's rulings on various pretrial

motions. For the reasons that follow, we affirm.

I.

In 2011, plaintiff made contact with The Pinnacle Companies (Pinnacle),

a developer hired by DCH Montclair (DCH) to help obtain "new entitlements"

for the construction of two buildings in Montclair (the Project); in addition,

Pinnacle had the responsibility of selecting a general contractor who could

competently provide preconstruction services. During an initial meeting, Holder

informed Brian Stolar, Pinnacle's president, that "in order for [plaintiff] to

participate in construction of [a] project of this magnitude[, plaintiff] would

have to joint venture with somebody else that has bonding capacity and

experience . . . ." Holder then contacted defendants, Pike Construction Co., LLC

(Pike) and Jeffrey Abrams (Pike's part-owner), in an attempt to form a joint

venture with Pike to compete for the Project.1

1 At his deposition, Stolar testified he "had already been referred to" Pike by a partner. A-5098-17T1 2 At his deposition, Holder testified that he called Abrams, and the two

agreed

that we'd be a joint venture partnership[;] that we would be 50/50 partners based on a concept that each [of the parties] would be responsible for their own respective home office expenses, including principals[;] that we'd be financially equally responsible for the [p]roject[;] that we would participate in terms of construction responsibilities on [an] equal basis[;] and that Pike would bring their bonding capacity to the [P]roject and [plaintiff] would make the introduction to the client.

It is undisputed there was never a written agreement between plaintiff and

defendants, nor was there a written agreement between plaintiff and Pinnacle,

or between the alleged joint venture and Pinnacle.

In a certification, Abrams recalled the phone call with Holder, but stated

in his deposition that he "never agreed to the alleged terms proposed by Holder,

as set forth." He stated the parties "had an understanding that we were pursuing

the . . . [P]roject and other projects with Pinnacle together"; however, he "was

skeptical of [plaintiff's] ability to perform and fully expected that [Pike] would

end up carrying the ball . . . on this," because plaintiff did not "possess . . . the

experience necessary to build a project like this or the financial capability . . . ."

Abrams' partner, David Weiner, similarly testified that plaintiff lacked "the

financial wherewithal" and "the experience" necessary to complete the Project.

A-5098-17T1 3 In May 2011, Holder and Abrams attended a preconstruction meeting with

representatives of Pinnacle – a senior vice president at Pinnacle recalled walking

"away with the understanding that [plaintiff] and Pike Construction were going

to work together as joint venture partners." In June 2011, plaintiff emailed

Abrams a two-page document titled "division of responsibility," which consisted

of a chart connecting plaintiff and Pike to Pinnacle through a "joint venture

partnership"; the document also provided a check list regarding project

administration.

However, at his deposition, Stolar dismissed the "division of

responsibility" document as

a list with checks on it . . . [eighty] percent of the checkmarks are in both [plaintiff's and Pike's] columns. . . . [T]here were . . . dark checks and light checks. I'm like, what's the dark check and the light check? And the dark check is more emphasis and the light check is less emphasis, and with all due respect I'm building a very expensive project and I need a little more specificity . . . .

Stolar certified that "Pinnacle was not going to agree to the 'division of

responsibility' . . . therefore, that entire document became meaningless, and I

do not believe that it was ever discussed again."

At his deposition, Stolar stated that once Holder said he did not have the

bonding capacity to perform the Project, it "became a clear undeniable inability

A-5098-17T1 4 to work on this project," and "because he never worked on a project of anything

like this scale[, Pinnacle] would not consider him to work on [the] [P]roject." 2

Stolar did not believe plaintiff and defendants were engaged in a joint

relationship.

According to plaintiff, on "September 1, 2011, [plaintiff] provided

[d]efendants with . . . budget estimates for the project." Plaintiff cites to an

email from an employee of plaintiff to Weiner, with "attached information

regarding the budget estimates for [t]he Pinnacle [c]ompanies." None of the

attachments are included in the record, and defendants point out the

"[a]ttachments" section of the email included a document titled "Westfield

ground floor sketch plan." According to defendants, "Westfield" is a wholly

different (and much smaller) project than the Project at issue here. Thus,

defendants argue plaintiff's claim that plaintiff "provided . . . budget materials

for the project" "is a provably false representation."

Stolar also certified that "[o]n or about January 24, 2012, a [plaintiff]

employee sent [Pinnacle] an email suggesting that Pinnacle had verbally agreed

2 Prior to 2013, plaintiff had served on only six out-of-the-ground construction projects – those requiring excavation – and none exceeded $5,000,000 in contract price. In contrast, Pike had served as a general contractor for more than thirty years, during which it completed out-of-the-ground construction projects ranging from $10,000,000 to $150,000,000. A-5098-17T1 5 to pay . . . a fee for preconstruction services, which was not correct." According

to Stolar, "Contrary to [plaintiff's]'s assertion, there was a specific verbal

agreement among Pinnacle, Pike and [plaintiff], that Pike and [plaintiff] were

not charging Pinnacle any preconstruction fees." Later that day, "Holder

apologized for [plaintiff] having wrongfully claimed that Pinnacle verbally

agreed to pay for preconstruction fees, when no such fee existed – and in fact,

the exact opposite agreement was reached between" the parties and Pinnacle.

Notwithstanding Holder's apology, Stolar felt plaintiff's email "reflected

[plaintiff's] lack of credibility, and at that point . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Mustilli v. Mustilli
671 A.2d 650 (New Jersey Superior Court App Division, 1995)
Sullivan v. Jefferson, Jefferson & Vaida
400 A.2d 836 (New Jersey Superior Court App Division, 1979)
Grober v. Kahn
219 A.2d 601 (Supreme Court of New Jersey, 1966)
Rivers v. LSC PARTNERSHIP
874 A.2d 597 (New Jersey Superior Court App Division, 2005)
Bender v. Adelson
901 A.2d 907 (Supreme Court of New Jersey, 2006)
Wittner v. Metzger
178 A.2d 671 (New Jersey Superior Court App Division, 1962)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
Brill v. Guardian Life Insurance Co. of America
666 A.2d 146 (Supreme Court of New Jersey, 1995)
Kurth v. Maier
31 A.2d 835 (Supreme Court of New Jersey, 1943)
Interchange State Bank v. Rinaldi
696 A.2d 744 (New Jersey Superior Court App Division, 1997)
Liberty Surplus Insurance v. Amoroso
916 A.2d 440 (Supreme Court of New Jersey, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
THE HOLDER GROUP, INC. VS. PIKE CONSTRUCTION, CO., LLC (L-4909-15, ESSEX COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-holder-group-inc-vs-pike-construction-co-llc-l-4909-15-essex-njsuperctappdiv-2019.