The Hartford Rfg. Co. v. T. of Thompson, No. Cv98 0578575 S (Apr. 30, 1998)

1998 Conn. Super. Ct. 5317
CourtConnecticut Superior Court
DecidedApril 30, 1998
DocketNo. CV98 0578575 S
StatusUnpublished

This text of 1998 Conn. Super. Ct. 5317 (The Hartford Rfg. Co. v. T. of Thompson, No. Cv98 0578575 S (Apr. 30, 1998)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Hartford Rfg. Co. v. T. of Thompson, No. Cv98 0578575 S (Apr. 30, 1998), 1998 Conn. Super. Ct. 5317 (Colo. Ct. App. 1998).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.]MEMORANDUM OF DECISION ON INJUNCTION This is an action brought by Hartford Roofing, Inc. seeking a temporary and permanent injunction restraining the defendants, Town of Thompson and its Board of Education, from executing a contact with the defendant Silktown Roofing, Inc. for re-roofing work to certain school buildings because such contract would violate the competitive bidding provisions of General Statutes § 10-287 (b). The parties were heard in this court April 14, 1998, at which time before the taking of evidence, the court denied defendants' motion to dismiss dated April 9, 1998.

— I —

The parties have stipulated to the following facts. In early 1998, by public advertising, notice and distribution of its Project Manual For Roofing and Associated Work, Thompson put the project out for public competitive bidding. Thompson hired an architectural and planning firm, The Lawrence Company, to assist it with the bidding process. Thompson's package for sealed bids called for separate prices on a base bid and four alternate bids. Bidders, however, were instructed not to include the cost of lead paint removal in their original bids, and that any additional cost for lead based paint removal would be addressed by Change Order.

The Project Manual included an Invitation to Bid which provided that "subject to the rights reserved to the Owner in paragraph 11 below, the contract shall be awarded to the lowest responsible qualified bidder."

Paragraph 11 of the Invitation to Bid provides as follows:

The Owner shall have the right to reject any or all Bids and in particular to reject a Bid not accompanied by any required bid security or data required by the Bidding Documents or a Bid in any way incomplete or irregular. The Owner shall have the right to waive any informality or irregularity in any Bid received.

CT Page 5319

Thompson reserved the right to reject any or all bids. In addition, Thompson reserved the right "to accept Alternates in any order or combination . . . and to determine the low Bidder on the basis of the sum of the Base Bid and Alternates accepted."

Along with four other bidders Hartford Roofing timely submitted a sealed bid which complied with all the bidding and contract requirements. Shortly thereafter, on February 26, 1998, the five sealed bids were publicly opened, indicating that Hartford Roofing's bid was the lowest on the base bid as well as on the total bid, comprising the base bid plus four alternate bids. Defendant Silktown's base bid was second lowest being some $13,000 higher than that of Hartford Roofing.

In order to clarify certain information contained in the submitted bids, on March 10, 1998, Richard S. Lawrence of The Lawrence Associates, sent out a memorandum to the five bidders seeking such clarification and providing the following additional statement in paragraph 5:

Owner has had Mystic Air Quality Consultants, Inc. take test samples on the existing paint around the facia and chimney where the Bidding Documents call for "scraping and re-painting". Enclosed is a copy of those results with their accompanying report. Please provide an amount to be added to your Base Bid for the necessary lead based paint abatement, containment, operations and disposal.

On March 16, 1998, Bruce M. Rauluatis, Silktown's Project Manager, wrote to the Town: "Silktown Roofing has the cost of the lead paint abatement and has propose [sic] the following changes: Silktown Roofing proposes a DEDUCT COST of $15,000.00 to perform the lead paint abatement. . . ." (Capitals in original.)

On March 16, 1998, Jason B. Woz, Hartford Roofing's Project Manager, wrote to the Town: "Alternate for lead abatement . . . $25,000." In addition, he clarified a portion of the Alternate Number 2 bid submitted on February 26, 1998, regarding walk paths, writing: "Clarification: Bid was for a three foot wide walkway. Specified Carlisle locking pads are two feet wide. Our original price of $29,500.00 is for a 4 foot wide walk. We believe that the other bidders price is based on only a 2 foot CT Page 5320 walk pad, as noted in the specification, and not the 3 foot wide that is noted in Detail 1/A-10. If two feet wide is acceptable, decrease this alternate by $14,750.00." (Emphasis in original.)

After the original bids were adjusted to include the cost of the lead paint abatement, Silktown's total bid, comprising the base bid, four alternate bids, and the lead paint abatement, became the lowest.

On March 17, 1998, Lawrence reported the following data to the Thompson Building Committee:

CONTRACTOR BASE BID B/B + 4 LEAD CLARIFY ALTERNATES PAINT WALKWAY

HARTFORD Roofing $604,000 $840,150 +$25,000 -$14,750

SILKTOWN Roofing $616,758 $853,937 -$15,000

Concerned about the lead paint abatement estimates submitted, Lawrence opined: "The cost quotations for the removal of the lead based paint are suspect now that all contractors know each others prices for the main portion of the project. In some cases we believe these do not reflect the actual cost and were modified to place their combined price in a more competitive position to the lowest bidders."

Lawrence then advised the building committee: "We suggest the Committee consider awarding the Project on the basis of the Bids opened on 2-26-98 and ask that Bidder to obtain for your consideration three lead paint removal contractor's bids, OR re-bid the entire project with the lead base paint included as part of the Base Bid."

On March 17, 1998, the building committee met to discuss the bids and voted "to accept the bid from Silktown Roofing; Silktown Roofing's bid to include their base bid, all four alternatives; and their cost adjustment for the removal of lead based paint as per their proposal dated 3/16/98; the total amount to be $838,937 for construction costs subject to local funding approval."

Thereafter, on March 19, 1998, Hartford Roofing sent a letter protesting the decision to award the contract to Silktown.

— II — CT Page 5321

Defendants' Motion to Dismiss, which was denied prior to the taking of evidence on April 14, 1998, was based in large part on the contention that as an unsuccessful bidder, plaintiff did not have standing to challenge the award to Silktown. This court found that the allegations made by plaintiff were sufficient under Connecticut law to confer standing on the plaintiff. After hearing the evidence, this court finds that the actions of the defendants so undermined the objective and integrity of the bidding process as to confer standing on the plaintiff in accordance with the exception carved out by our Supreme Court inArdamore Construction Co. v. Freedman, 191 Conn. 497, 504, 505 (1983) and Spiniello Construction Co. v. Manchester,189 Conn. 539 (1983)

— III —

Plaintiff claims that on February 26, 1998 when all the bids were opened, it was the lowest qualified bidder, both on the base bid as well as on the total bid comprising the base bid and the four alternative bids, which was the bid selected by the Town. It claims the Town violated the dictate of its own Addendum No. 1, when instead of accounting for any additional costs for lead based paint removal by post award change order, it-did not award the contract to plaintiff but invited additional bids for the lead based paint removal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spiniello Construction Co. v. Town of Manchester
456 A.2d 1199 (Supreme Court of Connecticut, 1983)
John J. Brennan Construction Corporation, Inc. v. Shelton
448 A.2d 180 (Supreme Court of Connecticut, 1982)
Ardmare Construction Co. v. Freedman
467 A.2d 674 (Supreme Court of Connecticut, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
1998 Conn. Super. Ct. 5317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-hartford-rfg-co-v-t-of-thompson-no-cv98-0578575-s-apr-30-1998-connsuperct-1998.