The Florida Paraplegic Assoc. v. Uccello Immobilie

227 F.3d 1347, 10 Am. Disabilities Cas. (BNA) 1802, 2000 U.S. App. LEXIS 23634, 2000 WL 1370739
Court of Appeals for the Eleventh Circuit·Decided September 22, 2000·No. 99-13156·Published

Opinions

PER CURIAM:

Uccello Immobilien, GMBH (“Defendant”), seeks to reverse a liquidated damages award ordered pursuant to a settlement agreement with Edward Resnick (“Plaintiff’),1 and to reverse the denial of a motion to extend the time of performance. Because the liquidated damages award was punitive, and because the district court did not abuse its discretion in denying the motion to extend time of performance, we vacate in part and affirm in part.

A.

Plaintiff and Defendant entered into a settlement agreement to bring Defendant’s office building into compliance with the American with Disabilities Act (“ADA”), 42 U.S.C. § 12182, et seq.2 The settlement required Defendant to begin construction for the accommodations 30 days after the district court approved the settlement (subject to Defendant obtaining the necessary building permits) and to complete the construction four months later. If Defendant could not complete the project in a timely fashion due to circumstances beyond its control, then Defendant would be afforded a reasonable delay upon agreement of the parties or by court order. Otherwise, delay in completion would result in liquidated damages of $100 per day plus costs and fees.

[1350]*1350On 4 December 1997, the district court approved the settlement and retained enforcement authority. See Kokkonen v. Guardian Life Ins. Co. of Amer., 511 U.S. 375, 114 S.Ct. 1673, 1677, 128 L.Ed.2d 391 (1994). Defendant did not apply for a building permit until August 1998. When Plaintiff visited the building in January 1999, he observed that the accommodations required by the settlement had not been completed; Plaintiff, however, was still able to transact his business in the building. At Plaintiffs request, an ADA consultant then inspected the building to confirm which accommodations required by the settlement remained incomplete.

Plaintiff on 2 March 1999 filed a Motion to Enforce the Settlement against Defendant. After filing four extensions to reply to Plaintiffs motion, Defendant responded in June 1999, at which time Defendant also moved to enlarge the time to satisfy the settlement.

The district court ordered Defendant to complete the accommodations, to pay Plaintiffs attorney’s fees and costs, and to pay liquidated damages of $18,500.003 to a charity as designated by Plaintiff. The court also denied Defendant’s motion for an extension of time to complete the accommodations. Defendant now appeals.

B.

We review a court’s decision to enforce a settlement agreement for an abuse of discretion. Hayes v. National Serv. Indus., 196 F.3d 1252, 1254 (11th Cir.1999). An error of law is an abuse of discretion per se. Alikhani v. United States, 200 F.3d 732, 734 (11th Cir.2000). Principles governing general contract law apply to interpret settlement agreements. Schwartz v. Florida Bd. of Regents, 807 F.2d 901, 905 (11th Cir.1987); Crosby Forrest Products, Inc. v. Byers, 623 So.2d 565, 567 (Fla.Dist.Ct.App.1993). And, even though this settlement agreement arose under the ADA, state contract law directs our analysis here.4 See Hayes, 196 F.3d at 1253 (applying state law to construction and enforceability of settlement agreement arising under Title VII); Schwartz, 807 F.2d at 905 (same).

Liquidated damages arising from breach of contract are appropriate when (1) damages from the breach are not readily ascertainable, and (2) the sum stipulated is not grossly disproportionate to the damages reasonably expected to follow from the breach. MCA Television Ltd. v. Public Interest Corp., 171 F.3d 1265, 1271 (11th Cir.1999); Hyman v. Cohen, 73 So.2d 393, 401 (Fla.1954) (en banc). But liquidated damages are inappropriate when they serve only to punish the breaching party. Lefemine v. Baron, 573 So.2d 326, 328-29 (Fla.1991).

For the first element, potential damages arising from breach of this settlement agreement are not readily ascertainable. Handicapped persons who are inconvenienced or harmed by Defendant’s failure to comply with the settlement [1351]*1351agreement may suffer some damage of varying degrees from Defendant’s potential breach of contract. Thus, some amount of liquidated damages might be appropriate in this context.

The amount of liquidated damages provided by the settlement agreement, however, is grossly, disproportionate to the damages reasonably expected to flow from the breach. While liquidated damages may or may not precisely compensate for the actual breach, the disparity may not be so great as to compensate minimal damages with substantial sums. See MCA Television Ltd., 171 F.3d at 1271 (“Parties may not [ ] use [liquidated damages] provisions as a way to secure for themselves greater damages in the event of a breach than contract law would normally allow.”).

In this case, Plaintiff entered the building in January 1999 and saw that the settlement requirements had not been met; he seemingly was not denied use of the building based on his handicap and was still able to complete his business there. Plaintiff has not alleged that he suffered monetary damages due to the breach; yet he seeks to enforce a $18,500 liquidated damages award. Absent the liquidated damages provision, Plaintiff would be entitled to minimal damages at best for the breach. The gross disparity between the stipulated amount of liquidated damages and the damages flowing from the beach causes the damages provision to fail.

That the district court ordered the damages award to be paid to a charity as directed by Plaintiff further establishes that this award was punitive and that Plaintiff suffered no actual damages from the breach. Plaintiff seeks no personal compensation for the breach; payment to the charity serves only to penalize Defendant for nonperformance, much like payment to a public entity for violation of a local ordinance.

Plaintiff and the district court rely on Six Cos. of Cal. v. Joint Hwy. Dist. No. 13, 110 F.2d 620 (9th Cir.), rev’d on other grounds, 311 U.S. 180, 61 S.Ct. 186, 85 L.Ed. 114 (1940), to argue that liquidated damages may be awarded when the breach inconveniences a group intended to benefit from the contract. In that case, the court awarded a municipality liquidated damages under a contract to build a highway and tunnel.

Free access — add to your briefcase to read the full text and ask questions with AI

The Florida Paraplegic Assoc. v. Uccello Immobilie, 227 F.3d 1347, 10 Am. Disabilities Cas. (BNA) 1802, 2000 U.S. App. LEXIS 23634, 2000 WL 1370739 (11th Cir. 2000).

227 F.3d 1347 (The Florida Paraplegic Assoc. v. Uccello Immobilie) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kobatake v. E.I. DuPont De Nemours & Co.
162 F.3d 619 (Eleventh Circuit, 1998)
MCA Television Ltd. v. Public Interest Corp.
171 F.3d 1265 (Eleventh Circuit, 1999)
Hayes v. National Service Industries
196 F.3d 1252 (Eleventh Circuit, 1999)
Alikhani v. United States
200 F.3d 732 (Eleventh Circuit, 2000)
Texas Industries, Inc. v. Radcliff Materials, Inc.
451 U.S. 630 (Supreme Court, 1981)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Louis Schwartz v. Florida Board of Regents
807 F.2d 901 (Eleventh Circuit, 1987)
Lefemine v. Baron
573 So. 2d 326 (Supreme Court of Florida, 1991)
Crosby Forrest Products, Inc. v. Byers
623 So. 2d 565 (District Court of Appeal of Florida, 1993)
Hyman v. Cohen
73 So. 2d 393 (Supreme Court of Florida, 1954)
MULTITECH CORP v. St. Johns Bluff Inv. Corp.
518 So. 2d 427 (District Court of Appeal of Florida, 1988)
Smith v. Newell
37 Fla. 147 (Supreme Court of Florida, 1896)