The Florida Paraplegic Assoc. v. Uccello Immobilie

227 F.3d 1347
CourtCourt of Appeals for the Eleventh Circuit
DecidedSeptember 22, 2000
Docket99-13156
StatusPublished

This text of 227 F.3d 1347 (The Florida Paraplegic Assoc. v. Uccello Immobilie) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Florida Paraplegic Assoc. v. Uccello Immobilie, 227 F.3d 1347 (11th Cir. 2000).

Opinion

[PUBLISH]

IN THE UNITED STATES COURT OF APPEALS FOR THE ELEVENTH CIRCUIT FILED ------------------------------------------- U.S. COURT OF APPEALS No. 99-13156 ELEVENTH CIRCUIT SEPTEMBER 22, 2000 -------------------------------------------- THOMAS K. KAHN CLERK D. C. Docket No. 97-00173-CV-DMM

EDWARD RESNICK, an individual,

Plaintiff-Appellee,

versus

UCCELLO IMMOBILIEN GMBH, INCORPORATED, a foreign corporation doing business in Florida, G & K INVESTMENTS MANAGEMENT, INC., a Florida corporation,

Defendants-Appellants.

---------------------------------------------------------------- Appeal from the United States District Court for the Southern District of Florida ---------------------------------------------------------------- (September 22, 2000)

Before EDMONDSON, BARKETT and RONEY, Circuit Judges.

PER CURIAM:

Uccello Immobilien, GMBH (“Defendant”), seeks to reverse a liquidated damages award ordered pursuant to a settlement agreement with Edward Resnick

(“Plaintiff”),1 and to reverse the denial of a motion to extend the time of

performance. Because the liquidated damages award was punitive, and because the

district court did not abuse its discretion in denying the motion to extend time of

performance, we vacate in part and affirm in part.

A.

Plaintiff and Defendant entered into a settlement agreement to bring

Defendant’s office building into compliance with the American with Disabilities

Act (“ADA”), 42 U.S.C. § 12182, et seq.2 The settlement required Defendant to

begin construction for the accommodations 30 days after the district court

approved the settlement (subject to Defendant obtaining the necessary building

permits) and to complete the construction four months later. If Defendant could

1 Four plaintiffs initially sued Defendant for alleged ADA violations. Resnick is the only plaintiff that moved to enforce the settlement agreement with Defendant; thus he is the only plaintiff for purposes of this appeal. 2 The accommodations required by the settlement agreement include these things: (1) on-site disabled parking spaces with a curb cut; (2) a passenger drop-off area with a curb cut; (3) an on- street disabled parking space with a curb cut; (4) a fire alarm system with 75 candela strobe lights; (5) lower bank counters with enough space for knee clearance; (6) accessible hardware on doors; (7) lower drinking fountains; (8) braille in the elevator and on door jambs; (9) a lower emergency telephone in the elevator; and (10) accessible restrooms with signs indicating such.

2 not complete the project in a timely fashion due to circumstances beyond its

control, then Defendant would be afforded a reasonable delay upon agreement of

the parties or by court order. Otherwise, delay in completion would result in

liquidated damages of $100 per day plus costs and fees.

On 4 December 1997, the district court approved the settlement and retained

enforcement authority. See Kokkonen v. Guardian Life Ins. Co. of Amer., 114 S.

Ct. 1673, 1677 (1994). Defendant did not apply for a building permit until August

1998. When Plaintiff visited the building in January 1999, he observed that the

accommodations required by the settlement had not been completed; Plaintiff,

however, was still able to transact his business in the building. At Plaintiff’s

request, an ADA consultant then inspected the building to confirm which

accommodations required by the settlement remained incomplete.

Plaintiff on 2 March 1999 filed a Motion to Enforce the Settlement against

Defendant. After filing four extensions to reply to Plaintiff’s motion, Defendant

responded in June 1999, at which time Defendant also moved to enlarge the time to

satisfy the settlement.

The district court ordered Defendant to complete the accommodations, to

pay Plaintiff’s attorney’s fees and costs, and to pay liquidated damages of

3 $18,500.003 to a charity as designated by Plaintiff. The court also denied

Defendant’s motion for an extension of time to complete the accomodations.

Defendant now appeals.

B.

We review a court’s decision to enforce a settlement agreement for an abuse

of discretion. Hayes v. National Serv. Indus., 196 F.3d 1252, 1254 (11th Cir.

1999). An error of law is an abuse of discretion per se. Alikhani v. United States,

200 F.3d 732, 734 (11th Cir. 2000). Principles governing general contract law

apply to interpret settlement agreements. Schwartz v. Florida Bd. of Regents, 807

F.2d 901, 905 (11th Cir. 1987); Crosby Forrest Products, Inc. v. Byers, 623 So. 2d

565, 567 (Fla. Dist. Ct. App. 1993). And, even though this settlement agreement

arose under the ADA, state contract law directs our analysis here.4 See Hayes, 196

3 The district court ordered Defendant to pay $100 per day for each day the improvements were not complete, dating back to 2 January 1999, four months after the city granted the building permit, until 7 July 1999, the day of the order. 4 We generally disfavor federal common law and apply it in only rare instances concerning “rights and obligation of the United States, interstate and international disputes implicating the conflicting rights of States or our relations with foreign nations, and admiralty cases.” Kobatake v. E.I. DuPont Nemours and Co., 162 F.3d 619, 624 n.3 (11th Cir. 1998) (quoting Texas Industries, Inc. v. Radcliff Materials, Inc., 101 S. Ct. 2061, 2067 (1981)); see also City of Huntsville v. City of Madison, 24 F.3d 169, 172 n.3 (11th Cir. 1994). Because this settlement agreement is between two private parties, federal common law does not apply. Cf. Brewer v.

4 F.3d at 1253 (applying state law to construction and enforceability of settlement

agreement arising under Title VII); Schwartz, 807 F.2d at 905 (same).

Liquidated damages arising from breach of contract are appropriate when

(1) damages from the breach are not readily ascertainable, and (2) the sum

stipulated is not grossly disproportionate to the damages reasonably expected to

follow from the breach. MCA Television Ltd. v. Public Interest Corp., 171 F.3d

1265, 1271 (11th Cir. 1999); Hyman v. Cohen, 73 So.2d 393, 401 (Fla. 1954) (en

banc). But liquidated damages are inappropriate when they serve only to punish

the breaching party. Lefemine v. Baron, 573 So. 2d 326, 328-29 (Fla. 1991).

For the first element, potential damages arising from breach of this

settlement agreement are not readily ascertainable. Handicapped persons who are

inconvenienced or harmed by Defendant’s failure to comply with the settlement

agreement may suffer some damage of varying degrees from Defendant’s potential

breach of contract. Thus, some amount of liquidated damages might be

appropriate in this context.

The amount of liquidated damages provided by the settlement agreement,

Muscle Shoals Bd. of Educ., 790 F.2d 1515, 1519 (11th Cir. 1986) (applying federal common law to interpret EEOC predetermination settlement agreement negotiated by EEOC); Eatmon v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kobatake v. E.I. DuPont De Nemours & Co.
162 F.3d 619 (Eleventh Circuit, 1998)
MCA Television Ltd. v. Public Interest Corp.
171 F.3d 1265 (Eleventh Circuit, 1999)
Hayes v. National Service Industries
196 F.3d 1252 (Eleventh Circuit, 1999)
Alikhani v. United States
200 F.3d 732 (Eleventh Circuit, 2000)
Texas Industries, Inc. v. Radcliff Materials, Inc.
451 U.S. 630 (Supreme Court, 1981)
Kokkonen v. Guardian Life Insurance Co. of America
511 U.S. 375 (Supreme Court, 1994)
Louis Schwartz v. Florida Board of Regents
807 F.2d 901 (Eleventh Circuit, 1987)
Lefemine v. Baron
573 So. 2d 326 (Supreme Court of Florida, 1991)
Crosby Forrest Products, Inc. v. Byers
623 So. 2d 565 (District Court of Appeal of Florida, 1993)
Hyman v. Cohen
73 So. 2d 393 (Supreme Court of Florida, 1954)
MULTITECH CORP v. St. Johns Bluff Inv. Corp.
518 So. 2d 427 (District Court of Appeal of Florida, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
227 F.3d 1347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-florida-paraplegic-assoc-v-uccello-immobilie-ca11-2000.