The City of Moorhead v. Bridge Company

2015 ND 189, 867 N.W.2d 339, 2015 N.D. LEXIS 205, 2015 WL 4597670
CourtNorth Dakota Supreme Court
DecidedJuly 30, 2015
Docket20140431
StatusPublished
Cited by2 cases

This text of 2015 ND 189 (The City of Moorhead v. Bridge Company) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The City of Moorhead v. Bridge Company, 2015 ND 189, 867 N.W.2d 339, 2015 N.D. LEXIS 205, 2015 WL 4597670 (N.D. 2015).

Opinion

SANDSTROM, Justice.

[¶ 1] Bridge Company appeals from a judgment ordering it to donate a toll bridge to the cities of Fargo, North Dakota, and Moorhead, Minnesota, free and clear of all liens. Because the district court did not err in interpreting the parties’ agreement and the court’s findings of fact are not clearly erroneous, we affirm.

I

[¶ 2] In May 1986, the cities and the Company entered into an agreement for the purpose of construction and operation of a private toll bridge over the Red River connecting 12th Avenue North in Fargo with 15th Avenue North in Moorhead. Section 2.3 of the agreement provided “[a]ny and all financing necessary for the construction, operation, and maintenance of the bridge is the responsibility of the Company.” Section 4.2 of the- agreement provided “[t]he bridge shall be owned and operated by the Company and costs of constructing the bridge shall be paid by the Company.” Section 5.3 of the agreement provided “[t]he bridge shall be maintained and repaired at the sole cost and expense of the Company in a state of good repair in accordance with the generally accepted standards by the Highway Departments for the States of North Dakota and Minnesota for similar structures.” The agreement allowed the Company to charge a toll for vehicular traffic on the bridge.

[¶ 3] The agreement further provided:

6.1. Term. The term of this Agreement shall be for a period of [25] years commencing with the day the Bridge commences operations. At the expiration of 25 years from the day the Bridge commences operations one of the following shall occur:
a) In the event the original debt incurred for the construction of the Bridge, including any refinancing or renegotiation of such debt, and any debt incurred for major maintenance and repairs to the Bridge, have been fully paid, the Company shall donate the Bridge to the Cities free and clear from any liens, and the Cities shall accept the Bridge for public use to be operated by the Cities as they may determine. It is expressly understood and agreed by and between the parties that any refinancing or additional financing which constitutes a lien or encumbrance on the Bridge which may be obtained more than five years after the original financing for the construction of the Bridge, shall be subject to the approval of the Cities. The amortization of any refinancing may not extend beyond 25 years from the commencement of the operation of the Bridge and the Company agrees it will not default on any loan secured by the Bridge. It is further agreed the Company will not permit or cause to be filed any lien or encumbrance on the Bridge other than a first lien for permanent financing and such liens or encumbrances as are necessary to secure interim construction financing.
b) In the event any portion of the original debt incurred for the construction of the Bridge, including any refinancing or renegotiation of such debt approved in advance by the Cities, or any portion of any debt incurred for major maintenance and repairs of the Bridge remains unpaid, the Cities shall have the option to either:
1. To pay or assume such outstanding indebtedness and, in such *342 event, the Company shall convey the Bridge to the Cities; or
2. Grant the Company the right to continue to operate the Bridge under the terms of this Agreement for an additional term of five (5) years, and upon the expiration of such extended term the Company shall donate the Bridge to the Cities free and clear from any liens and the Cities shall accept the Bridge for public use to be operated by the Cities as they may determine.
[[Image here]]
6.4. Suspension of Obligations to Perform. The Company’s obligation to construct, maintain, and operate the bñdge shall be suspended for reasons beyond the reasonable control of the Company, or by reason or [sic] acts of God, or force majeure, strikes, lock outs, labor troubles, or unavailability of building materials and the time for performance shall be extended for a period equal to the delays so caused.
[[Image here]]
7.9. Remedies. Upon the occurrence and continuance of an event of default of which the defaulting party has notice, the other party or parties shall have the right to enforce its rights by commencing judicial proceedings to:
[[Image here]]
b) enforce the terms of this Agreement or to seek injunctive relief, including a temporary restraining order, preliminary injunction, and specific performance without showing or approving any actual damage sustained and shall not thereby be deemed to have elected its remedies[.]

(Emphasis added.)

[¶ 4] The bridge was completed and started operations on June 1, 1988. The bridge was originally financed with publicly-sponsored bonds issued by Moorhead and capital from an investment firm. In 2004, the cities agreed to allow the Company to refinance the indebtedness, but the refinancing was required to be completely amortized by June 1, 2013, which was 25 years from the commencement of the operation of the bridge. The bank refinancing the debt required personal guarantees from the Company’s two shareholders.

[¶ 5] On May 29, 2013, Moorhead brought this declaratory judgment and specific performance action against the Company and Fargo seeking to have the Company either donate the bridge to the cities under section 6.1(a) of the agreement or allow the cities to take over operation of the bridge if any qualifying debt remained under section 6.1(b)(1). The Company responded that Fargo had already approved a five-year extension under section 6.1(b)(2) of the agreement and Moorhead had waived the early termination option under section 6.1(b)(1).

[¶ 6] As of June 1, 2013, the Company owed approximately $75,000 on the refinanced loan. In early September 2013, the Company’s two shareholders satisfied their personal guarantees for the debt, and as of September 6, 2013, none of the original indebtedness for construction of the bridge remained outstanding. During the 25-year time span, the Company’s records reflected $108,761 was paid for maintenance and repair of the bridge. All of these bills were paid by the Company before February 6, 2014. However, taxes remained owing to Cass County, North Dakota, and Clay County, Minnesota, and the unpaid taxes constituted a lien on the bridge.

[¶ 7] A bench trial was held on August 12, 2014. The district court found that during the 25-year period between June 1, 1988, and June 1, 2013, the bridge was closed 249 days because of flooding on the *343 Red River. Applying the Acts of God clause in section 6.4 of the agreement, the court ruled the 25-year period was extended 249 days to February 5, 2014, and because there was no qualifying debt in existence as of that date, the Company was required to donate the bridge to the cities free and clear of any liens.

[¶ 8] The district court had jurisdiction under N.D.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2015 ND 189, 867 N.W.2d 339, 2015 N.D. LEXIS 205, 2015 WL 4597670, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-city-of-moorhead-v-bridge-company-nd-2015.