The Chesapeake Bay Foundation v. Weyerhaeuser Company

580 F. App'x 203
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 31, 2014
Docket12-1515
StatusUnpublished
Cited by1 cases

This text of 580 F. App'x 203 (The Chesapeake Bay Foundation v. Weyerhaeuser Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Chesapeake Bay Foundation v. Weyerhaeuser Company, 580 F. App'x 203 (4th Cir. 2014).

Opinion

PER CURIAM:

The three plaintiffs in this diversity action — The Chesapeake Bay Foundation, Incorporated, SmithGroup, Incorporated, and Clark Construction Group, LLC (separately, “CBF,” “SmithGroup,” and “Clark,” and collectively, the “plaintiffs”) — appeal from the district court’s award of summary judgment to defendants Weyerhaeuser Company and Weyerhaeuser NR Company (together, “Weyerhaeuser”) on the ground that the plaintiffs’ various state law claims are time-barred. See Chesapeake Bay Found., Inc. v. Weyerhaeuser Co., 848 F.Supp.2d 570 (D.Md.2012) (the “Opinion”), ECF No. 109. 1 As explained below, we vacate and remand for further proceedings.

I.

A.

This litigation arose from the construction in 1999 and 2000 of CBF’s headquarters facility, the Philip Merrill Environmental Center (the “Merrill Center”), on the Chesapeake Bay in Annapolis, Maryland. 2 SmithGroup designed the Merrill Center, and Clark oversaw its construction. SmithGroup’s “green” design called for exposed structural wood members outside the envelope of the Merrill Center, including some that penetrated the building’s fagade. Under a March 3, 2000 purchase order that it entered into with Clark, Weyerhaeuser agreed to provide Parallam PSL columns and beams (“Parallams”) for use as the exposed wood members.

*205 Parallams, which have a rough-hewn appearance, are manufactured by bonding together strips of wood. The wood strips’ lack of uniformity creates channels, or “avenues,” that run longitudinally through the Parallams. Thus, water is expected to infíltrate Parallams used outdoors. To protect against rotting, Parallams are pressure-treated with a wood preservative intended to fully penetrate the avenues. Its contract with Clark required Weyer-haeuser to treat the Merrill Center’s Par-allams with the preservative PolyClear 2000. Weyerhaeuser engaged third party defendant Permapost Products Co. (“Per-mapost”) to apply the PolyClear 2000 treatment to a specified retention level, and Permapost provided certificates to Weyerhaeuser — later shared by Weyer-haeuser with the plaintiffs — verifying that such retention level had been reached.

Following completion of the Merrill Center in late December 2000, water began leaking through Parallams into the building. In 2001 and 2002, the leakage was investigated by two outside consultants hired by Clark; the first of those consultants, Wiss, Janney, Elstner Associates, Inc., issued a report on May 8, 2001 (the “2001 Report”), and the second, Vaughn Woodwork Consultants, released a report on May 24, 2002 (the “2002 Report”). The focus of the 2001 and 2002 Reports was on the cause of the leakage into the Merrill Center: water travelling from the exterior to the interior of the building through the avenues in the Parallams.

The 2001 Report also mentioned that such water could cause deterioration or rot in the Parallams themselves if they were not properly treated with a wood preservative. Although the 2002 Report could have been read to similarly warn about Paral-lam deterioration, its author had not considered such a possibility because he believed that the Merrill Center’s Parallams had been properly treated with PolyClear 2000. Indeed, three days before issuing the 2002 Report, he told the plaintiffs that Parallams were a “good durable product” and “as good as a [railroad] tie,” and that their “pressure treating [was] good,” so they would “not rot for a long period of time.” J.A. 671. Meanwhile, the plaintiffs worked closely with Weyerhaeuser on the leakage problem and shared with it the 2001 and 2002 Reports. In response, Weyerhaeuser assured the plaintiffs that the Merrill Center’s Parallams had been properly treated with PolyClear 2000 and were not at risk of premature deterioration. Moreover, at least three Weyerhaeu-ser representatives examined the Paral-lams and failed to note the presence of rotting.

After the leaking was stopped in 2004 with the use of sealants, the plaintiffs anticipated no further problems with the Parallams. During a routine inspection in July 2009, however, Parallams were found to be deteriorating. The plaintiffs subsequently learned that the Parallams had not been treated with PolyClear 2000 as certified, that PolyClear 2000 was not in any event well-suited to the job of preserving the Parallams, and that Weyerhaeuser had knowingly given false assurances to the contrary.

B.

The plaintiffs initiated this action in the Circuit Court for Montgomery County on December 3, 2010, and Weyerhaeuser filed a notice of removal in the District of Maryland on January 6, 2011. The complaint focused on the deterioration of the Merrill Center’s Parallams and sought damages for, inter alia, the costs of investigating and implementing remedial measures. According to the complaint, Weyerhaeuser breached its contract with Clark (Count I), owed common law indemnity (Count II) *206 and contribution (Count III) to Smi-thGroup and Clark, and was liable to CBF and SmithGroup for negligent misrepresentation (Count IV) and negligence (Count V).

On January 20, 2011, Weyerhaeuser answered the complaint, asserted counterclaims against the plaintiffs, and filed its third party complaint against Permapost. Following extensive discovery, Weyerhaeu-ser sought summary judgment on the plaintiffs’ claims, invoking the applicable statute of limitations. Weyerhaeuser and Permapost also made separate summary judgment motions with respect to Weyer-haeuser’s various cross- and counterclaims. By its Opinion and an accompanying Order of March 23, 2012, the district court granted Weyerhaeuser’s motion for summary judgment as to the plaintiffs’ claims and thus denied as moot all other summary judgment motions. The plaintiffs timely noted this appeal, and we possess jurisdiction under 28 U.S.C. § 1291.

II.

We review de novo a district court’s award of summary judgment, viewing the facts and inferences reasonably drawn therefrom in the light most favorable to the nonmoving party. See Core Commc’ns, Inc. v. Verizon Md. LLC, 744 F.3d 310, 320 (4th Cir.2014). A summary judgment award is appropriate only when the record “shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a). The relevant inquiry is “whether the evidence presents a sufficient disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 251-52, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

III.

In awarding summary judgment to Wey-erhaeuser, the district court concluded that the plaintiffs’ state law claims are time-barred. 3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
580 F. App'x 203, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-chesapeake-bay-foundation-v-weyerhaeuser-company-ca4-2014.