The Brooklyn Union Gas Company v. Federal Energy Regulatory Commission

893 F.2d 777, 1990 U.S. App. LEXIS 1506
CourtCourt of Appeals for the Fifth Circuit
DecidedFebruary 7, 1990
Docket88-4348
StatusPublished

This text of 893 F.2d 777 (The Brooklyn Union Gas Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
The Brooklyn Union Gas Company v. Federal Energy Regulatory Commission, 893 F.2d 777, 1990 U.S. App. LEXIS 1506 (5th Cir. 1990).

Opinion

JOHN R. BROWN, Circuit Judge:

As a fallout 1 from FERC Opinions 260 2 and 260A 3 the issue is whether the Commission could properly impose on Transco the mandatory use of a “3-day Peak” in cost allocation for D-l charges. We hold FERC could not do so and vacate the order and remand to the Commission for further proceedings.

In the Beginning

Way back in March 1942, Transco filed a proposed general rate increase under § 4(e) of NGA (15 U.S.C. § 717c). In its filing Transco allocated peak demand costs to its *779 3 rate zones 4 on the basis of customer contract entitlements, the same method consistently used by Transco for many years. By an order 5 April 1982, FERC accepted and suspended the filing and set the case for a hearing. After settlements not an issue herein there was reserved for hearing issues related to cost classification, cost allocation and design of Transco’s basic sales rates. 6 At the hearing held concerning these issues no party proposed a change in Transco’s longstanding method of allocating peak demand cost on the basis of customer’s contract entitlement.

Maximum daily contract entitlement represents the quantity of gas the firm customer has nominated based upon the customer’s own individual assessment of the quantity of gas that will be used by the markets it serves on the coldest days. Since, on the Transco System, it is the customers’ daily firm service reservation, rather than their annual reservations that determines the size, configuration, and cost of the facilities Transco installed and must maintain, providing firm services to Zones 1, 2, 3 amounts to the sum of customers nominated maximum daily contract entitlements that Transco has designed its system to provide.

The process of allocating costs to each zone is an important step in determining a pipeline’s rates. Since each customer’s contract gives the customer the right to demand service up to the contractual level, Transco has consistently allocated peak demand costs to each of its zones on the basis of sales customers’ peak contract entitlements.

Time Marches On

Progress was being made. The AU issued the initial decision September 1984. 7 The AU made no findings that Transco’s longstanding method of allocating peak demand costs based on contract entitlements was unjust, unreasonable or otherwise violated the NGA.

On December 30, 1986, FERC issued op. 260 (n. 2, supra) in which it adopted a Modified Fixed Variable (MFV) method of cost classification and rate design. The Commission in Op. 260 did not in any way indicate that it intended to alter Transco’s longstanding method of allocating peak demand costs. Indeed, it stated:

The demand costs allocated on the basis of peak usage would be assigned to D-l and the demand cost allocated on the basis of annual usage would be assigned to D-2.

37 FERC at ¶ 61,959.

With no challenge on rehearing to the method of allocation of peak costs, the Commission in op. 260A (n. 3, supra), made clear that no alteration in Transco’s longstanding peak demand cost allocation was intended or determined with respect to D-l costs. As FERC stated:

Under Opinion No. 260, the fixed costs in the D-l component are to be allocated on the basis of peak demand entitlement (contract billing units) and the fixed costs in the D-2 component are to allocated on the basis of test year volume.

40 FERC at 11 61,584.

The Commission expressly reversed its earlier decision that D-2 costs be allocated on the basis of test year volumes by requiring D-2 costs to “be allocated on the basis of the annual right to demand service”, 40 FERC at ¶ 61,585, which meant allocation on the basis of customer’s maximum contract entitlements on an annual basis. 8

*780 Finally, 3-day Peak

Following the issuance of Opinion No. 260-A, Transco filed revised tariff sheets. Transco’s compliance filing provided for the allocation of peak demand D-l costs on the basis of customers’ contract entitlements.

By a Letter Order October 19, 1987, the Director of the Commission’s office of Pipeline and Producer Regulation (DOPPR) rejected Transco’s filing for the reason that Transco has not:

(1) allocated transmission demand costs (D-l) to each zone under the MCF-mile methodology based on 3-day Peak volumes as required by Commission policy.

Petitioners filed an appeal of Staff action which appeal was denied by the Commission January 1988. 9

In response to then petitioners (which included Brooklyn Union Gas Co.) the Commission adopted the view of those supporting the Director’s Letter Order which followed the Commission’s claimed practice of allocating fixed transmission costs on the basis of peak day factors. Denying the appeal from the District Director’s letter order, the Commission stated:

Historically, it has been an established Commission policy that allocation of D-l cases should be on the basis 3-day peak usage. There is no reason to alter that Commission policy here. Opinion No. 260 states that ‘the demand costs alloct-ed on the basis of peak usage would be assigned to D 1 ... the resulting D 1 and D 2 amounts would then be used to design rates for Transco’s customers, with D-l charges determined on the basis of contract billing units. Petitioners incorrectly characterize the quoted language. Opinion No. 260 differentiated between cost allocation and rate recovery; the Commission held that D-l demand cost would be allocated to customers on the basis of peak usage and that the D-l charges would be recovered from customers on contract billing units.’

On the basis of this the Commission then summarized:

While the language and Opinion No. 260-A should have been more precisely written, it is clear, given the well-documented Commission policy on this issue and the fact that there was no D-l cost allocation issue in Opinion Nos. 260 and 260-A, that the language in Opinion No. 260-A did not signal a change in Commission policy.

And then, the Commission, probably unaware that it was about to concur in the petitioner’s contentions that cost classification and cost allocation are utterly different, concluded:

Rather, the language in Opinion No. 260-A should be construed as referring to the billing determinants to be used to recover D-l cost from customers, not cost allocation issues.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Permian Basin Area Rate Cases
390 U.S. 747 (Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
893 F.2d 777, 1990 U.S. App. LEXIS 1506, Counsel Stack Legal Research, https://law.counselstack.com/opinion/the-brooklyn-union-gas-company-v-federal-energy-regulatory-commission-ca5-1990.