The Avon Company v. Fareva Morton Grove, Inc.

District Court, S.D. New York·Decided September 21, 2023·No. 1:22-cv-04724·Unknown

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK

eee eee neeneneneeneneee OX THE AVON COMPANY f/k/a NEW AVON : LLC and LG H&H COMPANY, LTD., : ORDER GRANTING PARTIAL : SUMMARY JUDGMENT Plaintiffs, : -against- : 22 Civ. 4724 (AKH) FAREVA MORTON GROVE, INC. and : FAREVA §&.A,, : Defendants. : cen rene anne ne ene nee □□□□□□□□□□□□□□□□□□□□□□□□□ OX ALVIN K. HELLERSTEIN, U.S.D.J.: Plaintiffs The Avon Company, formerly known as New Avon LLC, and LG H&H Co., Ltd. (collectively “Avon”), sellers of beauty products, brought this suit against Defendants Fareva Morton Grove, Inc. and Fareva S.A. (collectively “Defendants”), seeking declaratory and injunctive relief and damages, caused by Fareva’s breach of a long-term Manufacturing and Supply Agreement (the “MSA”) (ECF No. 7-1). On June 30, 2023, Avon filed a motion for Partial Summary Judgment precluding Fareva from relying on a force majeure defense to excuse any breach of the MSA after May 4, 2020, or, in the alternative, compelling Fareva to respond to Avon’s Third Set of Interrogatories seeking information concerning Fareva’s force majeure defense. For the reasons discussed below, I hold that Fareva is precluded from asserting a force majeure defense to excuse any breach of the MSA between May 4, 2020 and December 17, 2022, BACKGROUND

I. The Manufacturing and Supply Agreement

Avon sold the Morton Grove facility to Fareva in December 2018 pursuant to an Asset Purchase Agreement. 20. The parties also simultaneously executed the MSA, under which Fareva agreed to manufacture, test, and supply virtually all of Avon’s beauty products for a 10-year period, with an option to extend for an additional five years. 20. The MSA provides terms favorable to Avon, including terms requiring Fareva to manufacture Avon’s products at a discount rate, in exchange for Avon’s sale of the Morton Grove Facility for a substantially lower price than the value of the facility,. The MSA contains a provision relieving Fareva of any liability for failing to perform if such non-performance is directly caused by a “Force Majeure Event,” which the MSA defines as follows: Neither Party shall be held liable or responsible to the other Party or be deemed to have defaulted under or breached this Agreement for failure or delay in fulfilling or performing any term of this Agreement to the extent such failure or delay directly results from fires, floods, earthquakes, embargoes, shortages, strikes, epidemics, quarantines, war, acts of war (whether war be declared or not), terrorist acts, insurrections, riots, civil commotion, acts of God, or acts, omissions, or delays in acting by any Governmental Authority, in each case to the extent beyond the reasonable control of the non-performing Party of any term of this Agreement (each, a “Force Majeure Event”). MSA § 14.10. Notice is required to invoke the force majeure provision: The non-performing Party shail notify the other Party of a Force Majeure Event promptly after the occurrence of such Force Majeure Event by giving written notice to the other Party stating the nature of such Force Majeure Event, its anticipated duration, and any action being taken to avoid or minimize its effect. The suspension of performance shall be of no greater scope and no longer duration than is necessary and the non-performing Party shall use commercially reasonable efforts to promptly remedy its inability to perform and recommence performance. id. The MSA requires “[a]ll notices and communications” given to Avon to be delivered to specific parties, including Avon’s COO, Head of Supply Chain, and General Counsel. /d. § 14.4.

To ensure that Fareva’s resources are not applied to other of its customers during a Force Majeure Event and a timely resumption of production to satisfy Avon’s purchase orders, Section 3.5 provides in relevant part: If [Fareva] reasonably believes that a... Force Majeure Event affecting Supplier is imminent or likely to occur in the future, [Fareva] shall notify Purchaser thereof as soon as commercially practicable, In the event ofa... Force Majeure Event, (i) [Fareva] shall resume supply of the affected Products as soon as commercially practicable, (ii) [Fareva] shall not allocate any capacity to other Persons unless and until one hundred percent (100%) of [Avon’s] Orders are being consistently fulfilled, (iii) [Fareva] shall keep [Avon] regularly apprised of the status of [their] efforts to resume supply of the affected Products, [and] (iv) at [Avon’s] request, [Fareva] shall use commercially reasonable efforts to engage an alternative supplier of the affected Products .. .. MSA § 3.5. Finally, Section 14.2 provides that New York law governs. MSA § 14.2. Il. Fareva’s April 2020 Force Majeure Notice and Termination On April 9, 2020, Fareva notified Avon that it was “experiencing disruption of [its] labor force & supply-chain due to the global coronavirus pandemic and the measure issued by the state of Illinois . . . [that] require[d] all Illinoisans to stay at home[.]” Fareva said it was “working hard on it in order to carry on with [its] activities as soon as possible.” Approximately one month later, on May 4, 2020, Fareva, declaring the Force Majeure Event as terminated, sent another letter to Avon, stating: As per our letter dated April 9th 2020, we informed you of the occurrence of a Force Majeure event affecting activities and our business relationship as of April 9th, 2020. We are pleased to inform you that our site is back to nearly normal operation and not under a Force Majeure situation anymore from the May 4th 2020 on. We therefore declare the Force Majeure event as terminated and proceed to resume our activities and the complete performance of your orders. [cite]. The letter also informed Avon that some of Fareva’s suppliers were still experiencing manufacturing difficulties activities affecting Fareva’s supply chain. Jd. Ill. Fareva’s Termination of the MSA and Failure to Invoke Force Majeure

On March 29, 2022, citing Avon’s failure to pay a November 2021 invoice, Fareva gave Avon 30-day’s written notice of early termination of the MSA. Although the MSA required six months of transition support (the “Transition Period”), Fareva notified Avon that if they failed to pay somewhere between $8 and $21 million by June 3, 2022, Fareva would cease production of Avon’s products. In response, Avon filed this suit and sought an injunction requiring Fareva to continue performing its contractual obligations. Fareva raised several arguments in opposition. None were based on the occurrence of a Force Majeure Event. At oral argument on Avon’s motion for a preliminary injunction on June 8, 2022, Fareva explicitly stated that a Force Majeure Event had not occurred. | entered a preliminary injunction order on June 21, 2022, requiring Fareva to continue performing its duties under the MSA through the ends of the Transition Period on October 21, 2022. (ECF Nos, 27, 33.) Avon filed a motion for contempt in August 2022, alleging that Fareva failed to perform as required by the preliminary injunction. Again, Fareva did not argue that a Force Majeure Event had occurred, nor did they notify Avon that they were invoking the force majeure provision of the MSA. When Avon renewed its contempt motion in November 2022, once again Fareva chose not to argue that performance was excused under the MSA due to a Force Majeure Event. On December 5, 2022 I held oral argument on Avon’s second contempt motion. | repeatedly asked Fareva’s counsel why Fareva had not declared force majeure: THE COURT: Why did [Fareva] not call force majeure? MR. LACY: Your Honor, because calling force majeure isn't going to result in the material suppliers providing the materials any sooner so it’s not going to solve the supply chain issues. (ECF No. 136-7, at 15:20-24.)

THE COURT: So, I don’t understand, Mr. Lacy, why you didn’t invoke Section 14.10...

Free access — add to your briefcase to read the full text and ask questions with AI

The Avon Company v. Fareva Morton Grove, Inc., (S.D.N.Y. 2023).

The Avon Company v. Fareva Morton Grove, Inc. (The Avon Company v. Fareva Morton Grove, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Johnson v. Killian
680 F.3d 234 (Second Circuit, 2012)