Tharpe & Brooks, Inc. v. Arnott Corp.
This text of 406 So. 2d 1 (Tharpe & Brooks, Inc. v. Arnott Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
THARPE AND BROOKS, INC.
v.
ARNOTT CORPORATION, et al.
Court of Appeal of Louisiana, First Circuit.
*2 A. Morgan Brian, Jr., New Orleans, for plaintiff.
*3 Judith Atkinson Chevalier, Baton Rouge, for Davidson Sash and Door, defendants.
Bernard S. Smith, Covington, for intervenors.
James R. Strain, Slidell, for Dossman, Keller, and St. Tammany Elec.
Patrick J. Berrigan, Slidell, for Radcliff Materials, and Slidell Refrig.
J. Patrick Beauchamp, Metairie, for Cancienne.
Before ELLIS, LOTTINGER and PONDER, JJ.
PONDER, Judge.
These appeals involve a ranking between plaintiff mortgagee and seven intervening lien claimants on a private construction project.
The issues are: res judicata, no right and no cause of action, ranking of mortgage, involving particularly the validity of the affidavit attesting no work had begun or materials furnished to the building site prior to the mortgage recordation, hearsay testimony and the ranking of intervening lien claimants.
Defendant, Arnott Corporation, contracted with Bakerfield Electric, Inc., as prime contractor, to build a motel. Plaintiff, Tharpe and Brooks, Inc., agreed to supply defendant with interim financing. The note was executed on September 17, 1973. On December 18, 1973, plaintiff received an affidavit from a registered land surveyor attesting that no work had begun or materials delivered to the building site. That same day plaintiff filed in the mortgage records the site inspection affidavit, the mortgage and the building contract with an addendum.
In early 1974, Arnott severed relations with Bakerfield and thereafter itself endeavored to finish the project. When, in late 1974 and early 1975, Arnott defaulted on its obligations, claims against the project were recorded. Plaintiff filed executory proceedings to foreclose its mortgage. Several lien claimants intervened in the suit. Plaintiff then filed a rule to rank, which was dismissed on oral motion when plaintiff's then counsel failed to appear on the hearing date. The property passed by Sheriff's deed to plaintiff and was later sold by plaintiff to a third-party, Midland. Thereafter, plaintiff filed another rule to rank all the recorded claims and the mortgage. The court denied the intervenors' exceptions of res judicata, and no right and no cause of action and held that plaintiff's mortgage had priority over all liens except those for the labor of Doyle Dossman, George J. Neumiller d/b/a Delmar Plumbing and Leon Koury.[1] Plaintiff appeals as do intervenors Washington, East, Eddie Knippers and Associates, Inc., and Lavergne.
We amend and affirm.
It is asserted that the trial court's dismissal of the first motion of rank liens forecloses Tharpe's second motion to rank. Louisiana Code of Civil Procedure Articles 2596 and 1672.[2] In the absence of any indication to the contrary, the oral order for dismissal was without prejudice, an interlocutory judgment, that left the plaintiff free to bring another action. LeBlanc v. Travelers Indemnity Co., 262 La. 403, 263 So.2d 337 (1972). The trial court was correct in denying the exception of res judicata.
Intervenors' exception of no right of action on the grounds that Tharpe was not the owner of the property at the time it filed the renewed rule to rank is without merit. The trial judge was correct in finding *4 that Tharpe, as vendor of the property had the duty to warrant the sale and thus had the right to file the rule to test the liens. Louisiana Civil Code, Article 2501. La.R.S. 9:4821, relied on by appellants, added in 1976, does not have the effect of preventing one not the owner to prosecute the action if he has an interest.
Intervenors also assert that the foreclosure was invalid because Tharpe did not produce proper authentic evidence, specifically, proof of the corporate mortgagee's authority to execute the mortgage. The proper methods to raise procedural objections to executory process are suspensive appeal and injunction. Louisiana Code of Civil Procedure, Article 2642.[3] The trial court correctly denied the exceptions of no cause or right of action.
Intervenors asserted that the trial court erred in allowing a brother to identify the deceased surveyor's signature on the affidavit of no work. However, the witness' familiarity with his brother's signature was sufficiently established; the signature was adequately identified. Although intervenors contend that the affidavit is deficient due to lack of a seal required by LSA-R.S. 37:695, as it read at the time the affidavit was made, there is no requirement under LSA-R.S. 9:4819(A)(3) that a seal be placed on the affidavit of "no work". We find no error.
Intervenors further contend that Tharpe's mortgage was not valid under LSA-R.S. 9:4812 because there was no proof of the date of pledge of the collateral mortgage note. The date of pledge was adequately proven in the record.
Tharpe could rely on the affidavit of no work, even though work had previously occurred and been "undone" prior to the inspection, in the absence of a showing of fraud on the part of Tharpe.[4] The trial judge was not manifestly incorrect in finding Tharpe did not have knowledge that work had occurred on the site.
We therefore conclude, as did the trial court, that only laborer's liens took precedence over the mortgage to Tharpe.
Intervenors complain of the exclusion of testimony of Horace Womack, the president of the prime contractor as to a telephone conversation with Mr. Hinton, who represented Arnott Corporation, in which Mr. Hinton purportedly told Womack of a conversation with defendant's attorney. This testimony was clearly hearsay; the trial court was correct in sustaining the objection.
Intervenors' contention that the trial judge erred in failing to allow testimony as to the payment of certain invoices becomes irrelevant, when we conclude that only labor liens would prime Tharpe's mortgage.
Intervenors' final contention was that the trial court erred in not finding that each claimant was a laborer and thus primed Tharpe's mortgage. A subcontractor is not subrogated to the rights of a laborer for the wages he has paid his laborers, but, the fact that he has signed a contract does not prevent him from claiming a laborer's privilege if he meets the *5 other qualifications. Pringle Associated Mortgage Corporation v. Eanes, 208 So.2d 346 (1st Cir. 1968), amended in part 254 La. 705, 226 So.2d 502.
Robert Washington entered into a contract to do electrical work for Arnott Corporation for $51,000.00, covering labor, materials, overhead and profits. While he may have performed some of the labor himself, he testified that over $6,000.00 of his lien was for wages paid to his employees and that approximately $2,000.00 of the lien was for materials. We do not believe the purpose of the laborers' lien priority covers this example. Furthermore, his conclusion that the remaining $4,200.00 should be given him as laborer's wages is not warranted; he was unable to substantiate his claim with specific information as to the hours he worked, the amount of his overhead or the measure of his profit.
Robert East, who contracted with Arnott Corporation to provide heating, air conditioning and ventilation work, filed a lien in the amount of $21,445.00. The trial court found that although East had a lien, it was not a laborer's lien that primed Tharpe's mortgage.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
406 So. 2d 1, 1981 La. App. LEXIS 5562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tharpe-brooks-inc-v-arnott-corp-lactapp-1981.