Thach v. Durham

208 P.2d 1159, 120 Colo. 253, 11 A.L.R. 2d 690, 1949 Colo. LEXIS 206
Supreme Court of Colorado·Decided July 11, 1949·No. No. 15,956.·Published·Cited by 5 cases

Opinion

Mr. Justice Stone

delivered the opinion of the court.

Thach made written agreement with Durham for sale of sheep and received a cash down payment thereon. Durham brought this action, alleging refusal by Thach to deliver’ the sheep in accordance with their contract and resultant damage, including expenses incurred and loss of profits under agreements which he had made for resale of the sheep. The prayer was for recovery of the damages alleged and refund of the down payment. Thach by answer alleged willingness and ability on his part at all times to perform and the refusal of plaintiff to perform; the fall of market price; inability to sell, and damage in the amount of the down payment, together with special damages, consisting of expenses incurred by reason of plaintiff’s breach of the contract, and loss and injury through separation of the young lambs from their *255 mothers in driving and shipment altogether in excess of the amount of the down payment. The court found inter alia that the specific language of the contract “1550 head of ewes” could not be varied by parole testimony and that the contract called for the delivery of exactly 1550 head of ewes; that there was no provision in the contract that the down payment of $3100 was to be treated as a forfeiture or as liquidated damages; “that the plaintiff had made up his mind prior to the date of June 14, 1946, the date when delivery was to be made by reason of the extension period, to terminate the contract, * * * that the contract was breached by the defendant when the defendant attempted to deliver a greater number of sheep than was called for by the contract, although the plaintiff had theretofore previously marked all of the sheep either as acceptable or as rejected, and made no effort to go to the pens to inspect the sheep, or to ascertain whether or not the sheep he had previously marked were there in the herd, and made no demand for the delivery of the sheep, so marked; * * * that there is insufficient evidence as to whether the plaintiff had made up his mind to terminate the contract a sufficient time before June 14, 1946, to have enabled him to notify the defendant that he would not accept delivery, and consequently only items of damage alleged and proved by the defendant, that arose after the sheep were in the stockyards at Walsenburg, will be considered, and these items of damage are based on the conclusion of the Court that prior to June 14,1946, the plaintiff had made up his mind not to receive delivery of the sheep and lambs.” Pursuant to said findings the court gave judgment to plaintiff in the amount of the down payment of $3100, less the amount of certain of the items of damage claimed and proved by defendant.

The questions brought here for review by specifications and cross specifications are: (1) Which party breached the contract; (2) right to forfeiture of down *256 payment, and (3) right to recover certain items of damage alleged. Further question is raised by defendant in error as to breach of contract by Thach through alleged delay in making delivery of the sheep. The court found against him on-this issue. There is abundant evidence to the effect that the delay was caused by Durham rather than Thach, and in any event Durham waived the default by failure to give notice of recission and by pleading his readiness to receive the sheep up to and including the date of their attempted delivery.

Free access — add to your briefcase to read the full text and ask questions with AI

Thach v. Durham, 208 P.2d 1159, 120 Colo. 253, 11 A.L.R. 2d 690, 1949 Colo. LEXIS 206 (Colo. 1949).

208 P.2d 1159 (Thach v. Durham) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Massey v. Love
478 P.2d 948 (Supreme Court of Oklahoma, 1971)
Perino v. Jarvis
312 P.2d 108 (Supreme Court of Colorado, 1957)