T&G Corporation v. United Casualty & Surety Insurance Company

CourtDistrict Court, S.D. Florida
DecidedFebruary 9, 2021
Docket0:20-cv-61589
StatusUnknown

This text of T&G Corporation v. United Casualty & Surety Insurance Company (T&G Corporation v. United Casualty & Surety Insurance Company) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T&G Corporation v. United Casualty & Surety Insurance Company, (S.D. Fla. 2021).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA CASE NO. 20-61589-CIV-ALTMAN/Hunt T&G CORPORATION,

Plaintiff, v.

UNITED CASUALTY & SURETY INSURANCE COMPANY,

Defendant. ________________________________/ ORDER

The Plaintiff, a general contractor, sued the Defendant, its subcontractor’s surety, in state court after the subcontractor defaulted and the surety (allegedly) failed to fulfil its obligations under the contract. Because the two parties—Plaintiff and Defendant—are diverse, and given that the case involves hundreds of thousands of dollars, the surety removed the action to this Court. The Plaintiff now wants to join the subcontractor as a second defendant. The problem, of course, is that the subcontractor is—like the Plaintiff—a citizen of Florida. Since there’s no federal question here, the subcontractor’s appearance would force the Court to remand the case to state court. Federal courts admittedly review these kinds of requests with suspicion. Often, the plaintiffs have no legitimate reason—other than remand—to add the non-diverse defendants. Here, though, the Plaintiff did have a good reason for leaving the subcontractor out of the original complaint. When the Plaintiff first sued the Defendant in state court, all indications were that the subcontractor would enter bankruptcy. The Plaintiff thus justifiably feared that the bankruptcy court’s ensuing stay would preclude its claims against the subcontractor. Since then, however, the subcontractor (who didn’t end up declaring bankruptcy) demanded payment from the Plaintiff—a demand it’s been unwilling to set aside. Some portion of that demand includes the very same payment the Defendant is here seeking to “offset” against the Plaintiff’s potential damages. The Plaintiff also owes the subcontractor money on another project. That wouldn’t matter much except that the governing subcontracts contain “cross- default” provisions, which appear to allow the Plaintiff to “stack” the balance from one project on top of the other. This is important because, without this “stacking,” the Plaintiff would be subject to a stringent damages cap that could sharply curtail its recovery in this case. If this all sounds a bit confusing, that’s because it is. This case straddles the muddled

intersection between several complex contractual provisions signed by three different parties—all of whom should be permitted to resolve their outstanding issues in one case, rather than in two separate cases. Unfortunately for the Defendant, that means this case cannot proceed in federal court. As this summation makes plain, the Plaintiff’s motion for leave to amend its complaint, to add a non-diverse defendant, and to remand is GRANTED. BACKGROUND The Plaintiff, T&G Corporation, d/b/a T&G Constructors (“T&G”), entered into a contract with the School Board of Broward County to renovate the Morrow Elementary School building in Broward County, Florida (the “Morrow Project”). See Compl. [ECF No. 1-3] ¶ 5. T&G subcontracted the electrical work on the project to Celeiro Electrical Contractor LLC (“Celeiro”). Id. ¶ 6. The Morrow Subcontract required Celeiro to obtain two bonds from the Defendant, United Casualty & Surety Company. Id. ¶ 7. Those bonds, which named T&G as obligee and beneficiary, required the

Defendant (1) to “pay in full for all losses, damages, expenses, costs, and attorney’s fees, including all appellate proceedings, that [T&G] sustains because of a default by [Celeiro] under the Subcontract,” and (2) to “pay in full all claimants . . . and to indemnify [T&G] for all damages attorney’s fees and costs it incurred, or will incur.” Id. ¶¶ 7, 12, 23. We refer to these obligations, respectively, as the “Performance Bond” and the “Payment Bond”—together, simply, “the Bonds.” In July of 2020, T&G filed this Complaint against the Defendant in state court, alleging that the Defendant failed to fulfill its obligations under the Bonds after Celeiro defaulted on the Morrow Subcontract. Id. ¶¶ 13–14, 16, 24. Relying on this Court’s diversity jurisdiction, the Defendant removed the case on August 5, 2020, see Notice of Removal [ECF No. 1] ¶ 5. Once in federal court, the Defendant answered with counterclaims of its own, alleging that (1) T&G owed the Defendant for claims the Defendant had paid out under the Payment Bond, see Answer and Counterclaim [ECF No.

6] ¶¶ 7–8, and that (2) as subrogee to Celeiro’s contractual rights, the Defendant was entitled to certain offsets and attorneys’ fees under the Morrow Subcontract, see id. ¶¶ 9–18. A few days after the Court entered a Scheduling Order [ECF No. 12], T&G moved to amend the Complaint to add Celeiro as a defendant. See Motion for Leave to Amend to Add Non-Diverse Defendant and Remand (“Motion”) [ECF No. 14]. Because Celeiro, like T&G, is a citizen of Florida, the proposed amendment would strip the Court of subject-matter jurisdiction and compel a remand to state court. See id. ¶¶ 1, 8. In support of the Motion, T&G says that it didn’t name Celeiro in the original Complaint because, at the time, it believed that Celeiro would enter bankruptcy—just as Celeiro’s principal, Roberto Celeiro Albar, had done. Id. ¶ 2. Moreover, according to T&G, after Mr. Albar’s bankruptcy, Celeiro began demanding payment for work it had completed on the Morrow Project. Id. ¶ 3. This, in turn, is the very same money the Defendant is now seeking to offset as Celeiro’s subrogee in this case.

Id. T&G would thus prefer to include Celeiro as a co-defendant because, otherwise, T&G could find itself in the unenviable position of having to defend itself against identical claims in two different fora. Id. at 5. What’s worse, T&G notes that Celeiro is also demanding payment for work it completed on another project—renovations at the Tamarac Elementary School (the “Tamarac Project”). See Reply at 2. And, T&G says, this second claim—which T&G doesn’t really dispute—is subject to a “cross- default” provision that, in essence, permits outstanding claims from the Morrow and Tamarac Projects to be calculated together. See Affidavit of Joe Easton (“Easton Aff.”) [ECF No. 16-1] ¶ 4. This claim agglomeration is important because it would (theoretically) allow T&G to exceed the Performance Bond cap of $404,000 that would otherwise govern T&G’s claims against the Defendant. See Hearing; see also Performance Bond, No. UCSX372X1063, Document 00620 (“Performance Bond”) [ECF No. 14-3], Ex. 2-A, at 1. The Defendant, of course, would prefer to stay here, in federal court. In its view, T&G has no

real claims against Celeiro—as evidenced by T&G’s decision not to sue Celeiro in the first instance. See Defendant’s Response in Opposition to Plaintiff’s Motion for Leave (“Response”) [ECF No. 15] ¶¶ 1, 2, 18–20. And, given that T&G filed its Motion soon after removal—but before any discovery had taken place—the Defendant insists that T&G is using the specter of an unlikely Celeiro claim to get what it really wants: a remand to state court. Id. The Defendant also tries to parry T&G’s thrusts by pointing out that Celeiro had not actually filed for bankruptcy in July of 2020—and, therefore, could have been sued, see id. ¶ 20; that this case could easily proceed without Celeiro both because T&G has its own case files and because any Celeiro-centric evidence could be obtained through third- party discovery, see id. ¶ 27; that T&G won’t be prejudiced by Celeiro’s absence because the Defendant is solvent and can satisfy any adverse judgment, see id. ¶ 28; that T&G can still sue Celeiro in state court, see id. ¶ 29; that T&G’s proposed amended complaint doesn’t seek a declaratory judgment— and so, doesn’t actually dispute that Celeiro is entitled to the offsets, see id. ¶ 30; and that Celeiro is

willing to release any claims it may have against T&G, see id. ¶ 31.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
T&G Corporation v. United Casualty & Surety Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tg-corporation-v-united-casualty-surety-insurance-company-flsd-2021.