Texas Const. Co. v. Dearing

296 S.W. 1112, 1927 Tex. App. LEXIS 531
CourtCourt of Appeals of Texas
DecidedMay 12, 1927
DocketNo. 1983.
StatusPublished
Cited by4 cases

This text of 296 S.W. 1112 (Texas Const. Co. v. Dearing) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texas Const. Co. v. Dearing, 296 S.W. 1112, 1927 Tex. App. LEXIS 531 (Tex. Ct. App. 1927).

Opinion

PELPHREY, C. J.

Appellees, R. H. Dearing, W. R. Dearing, and Roy E. D'earing, partners doing business under the name of R. H. Dear-ing & Sons, brought this suit ip the 101st district court of Dallas county, Tex., against the Texas Construction Company, a corporation, and the Dallas Power & Light Company, a corporation, for the recovery of $24,422, with legal interest thereon from January 1, 1924. Appellees alleged that the two appellants were in fact the same entity in that the Texas Construction Company was a mere agency of the Dallas Power & Light Company.

Appellees alleged that they had entered into a written contract with appellant Texas Construction Company to drill a deep water well on the property of appellant Dallas Power & Light Company, in Dallas, Tex.; that they had performed the contract, and that the completed well had been accepted by appellants; that thereafter the casing in said well collapsed without fault of appellees; that upon agreement of the parties another well was drilled by appellees; that they had been paid the sum of $24,054.50; and that appellants refused to pay the balance due them of $24,422.00. Appellees made the written contract a part of their petition.

Appellants answered by general demurrer, special exceptions, general denial, and by special pleas, alleging that the well had not been completed and finished as provided in the contract, but that before it had been cleaned out and tested, before it had been delivered to appellants, or had been accepted by them, the casing had collapsed, from no fault of appellants, and thereby rendered useless; that the well had not been fully completed and accepted by both appellants, as provided for in the contract, before the collapse occurred ; that appellees were engaged in making a requested test of the well at the time of its destruction; that appellant Texas Construction Company had exercised its option, ‘ under the contract, and had demanded that appellees install a strainer casing from the ■ lower extremity of the 8%-inch casing to the ' bottom of the well, and that appellees had wholly failed to make such installation; that appellees had, in attempting to get the casing past a rock encountered in drilling, damaged the casing to such an extent as to render it unfit and thereby caused it later to collapse; that in cleaning and testing the well appellees had either permitted too much air to get into the pipe or had failed to lower the air line to a proper depth, and thereby caused the destruction of the well; and that appellees were negligent in failing to cut off the air pressure in the air line when they discovered that the water had ceased to flow through the water line.

Appellees also filed a cross-action alleging that they were entitled to recover of appellants the sum of $5,967.50 for a delay of 155 days over and above the time specified in the contract, at the rate of $38.50 per day, same being the amount provided for in the contract as liquidated damages.

Appellants filed a supplemental petition generally denying the averments contained in appellees’ answer and alleging that if appellants failed or refused to accept the first well, such failure or refusal was unreasonable and amounted to a breach of the contract; that the officers and agents of appellants were on the ground every day during the drilling of the well, knew what materials were being used and how the work was being done and approved and accepted same, measured the well, made no objection as to the materials used or the manner in which the work was done, and that they are estopped to say that they did not intend to and did not accept the well; that, under the contract, appellants had no right to request a test of the well to be made by appellees after they had completed the drilling through the Paluxy sand.

Appellees further specially denied that they were engaged in making a test of the well at the, time the casing collapsed, but allege that the test was being conducted by appellants.

They further specially allege that the casing, which was damaged in trying to lower it past the rock obstruction in the well, was withdrawn and repaired by appellees and as repaired was accepted by the officers and agents of appellants; that the test was being made by appellants, and that any negligence in not cutting off the air when» the water ceased to flow through the water line was the' negligence of appellants; that the appellants waived the placing of the strainer casing in the well; that appellants are receiving benefits from the drilling of the first well in that the water from the first well flows into the second well and has increased the capacity of the second well; and that appellants, at the time the agreement was made as to the drilling of the second well, without prejudice to *1114 the rights of either party, waived their right to any claim for penalty or liquidated damages under and by virtue of the contract. Appellants by supplemental answer denied generally the allegations in the supplemental petition of appellees, and specially denied that the drilling of the first well increased the water supply in the second well.

The case was submitted to the jury on special issues, and the jury found in response thereto as follows:

(a) That appellees completed the well in accordance with the provisions of the written contract.

(b) That neither of the appellants informed the appellees, after the well was started and before the casing collapsed, that they wanted the strainer casing installed.

(c) That neither of appellants requested a test to be made of the well by appellees while the same was being drilled after the Paluxy sands were encountered.

(d) That the collapse of the casing was not caused by appellees’ churning the casing up and down, attempting to get it past a rock ledge.

(e) That the appellants, prior to the collapse of the casing, had waived the right to have the well shot by appellees before accepting same.

(f) That the time had not expired for appellants to request that the well be shot by appellees, prior to the collapse of the easing.

(g) That the well had been delivered to appellants before the casing collapsed.

Upon these findings the court rendered judgment in favor of appellees against appellants for $27,861.93, and against appellants on their cross-action. From that judgment this appeal has been perfected.

Opinion.

That a better understanding may be had of the questions involved, we here quote such parts of the written contract as we consider pertinent to the issues:

(2) “Said well to be drilled and cased from 24 inches above the normal ground surface of the earth adjacent to the well down to and through all of the Paluxy sands; but in no event to be drilled to a greater depth than 1,800 feet. From the surface of the earth down to a depth of 500 feet said well shall be cased with 22-inch inside diameter 75 pound per lineal feet steel easing, which shall be welded where joined. Said casing shall be set in such manner as to case out all shaly, sand or mud formations, and also all waters above.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiFrancesco v. Houston General Insurance Co.
858 S.W.2d 595 (Court of Appeals of Texas, 1993)
Dallas Hotel Co. v. Lackey
203 S.W.2d 557 (Court of Appeals of Texas, 1947)
Minnesota Mut. Life Ins. Co. v. Newman
157 S.W.2d 667 (Court of Appeals of Texas, 1941)
Wyatt C. Hedrick, Inc. v. Ratcliff
63 S.W.2d 877 (Court of Appeals of Texas, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
296 S.W. 1112, 1927 Tex. App. LEXIS 531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texas-const-co-v-dearing-texapp-1927.