Texaco Exploration & Production Inc. v. Amclyde Engineered Products Co.

323 F. App'x 345
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 29, 2009
Docket08-30528
StatusUnpublished

This text of 323 F. App'x 345 (Texaco Exploration & Production Inc. v. Amclyde Engineered Products Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Texaco Exploration & Production Inc. v. Amclyde Engineered Products Co., 323 F. App'x 345 (5th Cir. 2009).

Opinion

PER CURIAM: *

On December 3, 1998, a crane failed during the construction of the Compliant Tower at the Petronius oil and gas production facility (“Petronius Project”), causing the South Deck Module (“SDM”) to fall into the ocean. Plaintiffs-Appellants Texaco Exploration and Production, Inc. and Marathon Oil Company (collectively “Texaco”) initiated suit against several entities to recover damages caused by the SDM’s loss; specifically, Texaco sued to recover consequential damages from Defendants-Appellees AmClyde Engineered Products Company, Inc. and AmClyde Engineered Products, Inc. (collectively “AmClyde”). The district court found that AmClyde was a “subcontractor” for purposes of the relevant contract. Because the contract limited subcontractor liability, Texaco could not recover against AmClyde for any consequential damages it sustained due to Am-Clyde’s alleged negligence on the Petroni-us Project. Texaco appeals the district court’s ruling. We affirm.

I. FACTUAL AND PROCEDURAL BACKGROUND

A. Factual Background

Texaco hired contractor J. Ray McDer-mott, Inc. (“McDermott” or “Contractor”) to construct the Compliant Tower for the Petronius Project. The Compliant Tower is a platform that is fixed permanently to the Outer Continental Shelf adjacent to the Alabama shore and is designed to flex with the forces of wave, wind, and current. During the installation of the SDM to the Tower, a main load line on a crane failed, causing the SDM to fall into the Gulf of Mexico. The failure resulted in a complete loss of the SDM and a fifteen-month delay to the Project.

Texaco and McDermott entered into a contract (the “Petronius Contract” or *347 “Contract”) relating to the construction of the Compliant Tower and the installation of two modules on the Tower. See Texaco Exploration & Prod., Inc. v. AmClyde Engineered Prods. Co. (Texaco II), 448 F.3d 760, 765-66 (5th Cir.2006) (providing further detail on the factual basis of this suit). The Petronius Contract contains a clause providing that a valid subcontractor on the Petronius Project is not liable for any consequential damages. Specifically, Section 29 of the Petronius Contract states,

To the extent not covered by Builder’s Risk and Difference in Conditions insurance and notwithstanding any other provisions of this Agreement, Texaco and Contractor waive and release any claim against the other for consequential damages, however and whenever arising under this Agreement or as a result of or in connection with the Work and whether based on negligence, unseaworthiness, breach of warranty, breach of contract, strict liability or otherwise.

Section 4 of the Petronius Contract defines “Contractor” as follows:

“Contractor” means Contractor, and its parents, subsidiaries, and affiliates, the agents, employees and subcontractors of any of them.

Finally, Section 14 of the Contract, in pertinent part, addresses “subcontractors”:

If Contractor shall cause any part of the Work hereunder to be performed by a subcontractor, the provisions of this Agreement shall apply to such subcontractor and his or its employees in all respects as if he were employees of Contractor, and Contractor shall be liable for the Work of the subcontractor accordingly. No subcontract shall be made without the prior written approval of Texaco of both the subcontract and the subcontractor (such approval shall not be unreasonably withheld), but no such approval shall affect the provisions of this Agreement.

In addition to the Petronius Contract, McDermott had a pre-existing contract with AmClyde, which provided that Am-Clyde was the subcontractor on all work that McDermott was obligated to perform for third parties. It is undisputed that AmClyde designed a deep water lowering system for use on the underwater installation of the Compliant Tower’s support structure and rendered a technical analysis of the peculiarities of the lift modules used on the Petronius Project.

B. Procedural Background

This is the third time that this court has addressed questions stemming from the loss of the SDM. See Texaco II, 448 F.3d at 776-77 (recounting the procedural history of the case up to its consideration of the issues in May 2006); see also Texaco Exploration & Prod., Inc. v. AmClyde Engineered Prods. Co. (Texaco I), 243 F.3d 906 (5th Cir.2001). This court in Texaco II addressed, inter alia, whether the district court correctly concluded that AmClyde was a “subcontractor” under the terms of the Builder’s Risk Policy (“the Policy”), an insurance policy covering the Petronius Project. Id. at 766. We conducted a two-part inquiry. We first held that AmClyde was a subcontractor as the term was commonly understood under either Texas or Louisiana law. Id. at 778-79. We found that a subcontractor was “ ‘one who takes a portion of a contract from the principal contractor or another subcontractor,’ ” id. at 778 (citation omitted), and that the work AmClyde performed “in designing the lowering system used to install the support structure of the compliant tower and in calculating the hook eccentricity, a requisite part of the lifts, was integral to and required for compliant tower construction,” id. at 779. Accordingly, we held *348 that the district court correctly concluded that AmClyde was a “subcontractor” because it performed work assigned to the Contractor under the Petronius Contract. Id. We also considered whether the Policy altered the common understanding of the term “subcontractor,” and held that it did not. Id.

After remand, AmClyde sought summary judgment, asserting that the prior panel’s holding in Texaco II — that Am-Clyde was a “subcontractor” — meant that AmClyde was entitled to a waiver of consequential damages. The district court determined that Texaco II did not cover the instant dispute because the issue addressed therein related solely to the definition of “subcontractor” under the Policy, not the Petronius Contract. That is, it found that we did not decide whether Am-Clyde was a “subcontractor” under the Petronius Contract. Nevertheless, the district court concluded that AmClyde was a “subcontractor” under the terms of the Petronius Contract and was therefore entitled to a waiver of consequential damages. First, the court concluded that under Alabama’s general definition of “subcontractor,” AmClyde was a subcontractor on the Petronius Project. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
323 F. App'x 345, Counsel Stack Legal Research, https://law.counselstack.com/opinion/texaco-exploration-production-inc-v-amclyde-engineered-products-co-ca5-2009.