Tesoro Refining & Marketing Co. v. Pacific Gas & Electric Co.

146 F. Supp. 3d 1170, 2015 U.S. Dist. LEXIS 158066, 2015 WL 7350446
CourtDistrict Court, N.D. California
DecidedNovember 20, 2015
DocketCase No. 14-cv-00930-JCS
StatusPublished

This text of 146 F. Supp. 3d 1170 (Tesoro Refining & Marketing Co. v. Pacific Gas & Electric Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tesoro Refining & Marketing Co. v. Pacific Gas & Electric Co., 146 F. Supp. 3d 1170, 2015 U.S. Dist. LEXIS 158066, 2015 WL 7350446 (N.D. Cal. 2015).

Opinion

ORDER DENYING MOTION FOR PARTIAL SUMMARY JUDGMENT

JOSEPH C. SPERO, Chief Magistrate Judge

I. INTRODUCTION

This case concerns.a power outage at the Golden Eagle Refinery (the “Refinery”) owned by Plaintiff Tesoro Refining & Marketing Company LCC (“Tesoro”). Defendant Pacific Gas and Electric Company (“PG&E”) moves for summary judgment on Tesoro’s negligence and breach of contract claims, arguing that a tariff rule approved by the California Public Utilities Commission (“CPUC”) absolves PG&E of liability because the incident was a “transmission related outage.”

The Court held a hearing on October 16, 2015, and on October 20, 2015 issued an order requesting that the CPUC address the scope of the tariff rule. The CPUC has since responded and offered assistance, but advised that Tesoro would need to' file an administrative complaint and the Court would need to stay the case and continue the trial date to allow time for administrative proceedings. The Court thanks the CPUC for its offer and respects its need for time to address the issue. However, as no party has requested a stay or continuance, the Court proceeds to resolve the Motion. For the reasons discussed below, the Court holds that the limitation of liability provision does not apply to the facts of this case (viewed, as they must be in the present context, in the light most favorable to Tesoro) and DENIES PG&E’s Motion for Partial Summary Judgment.1

II. BACKGROUND

A. Factual Background

The following summary recounts the facts as construed in the light most favorable to Tesoro for the purpose of resolving PG&E’s present Motion. This Order should not be interpreted as resolving any disputed issues of fact.

[1173]*11731. Configuration of Facilities and Systems

Tesoro primarily receives electrical power for the Refinery from a cogeneration plant (the “Cogen”) operated by non-parties Foster Wheeler Martinez, Inc. and Martinez Cogen Limited Partnership (collectively, “FWM”),2 but also maintains an agreement for standby electrical service from PG&E’s grid, which Tesoro’s predecessor entered into in 1988. 1st- Am. Compl. (“FAC,” dkt. 28) ¶ 16 & Ex. A; Answer (dkt. 35) ¶ 16; Sias Deck (dkt. 80) Ex. 2 (Kromer Dep.) 42:12-16 & Ex. 3 (Carloni Dep.) 52:22-53:6. The Refinery is connected to the PG&E grid through the Cogen, which is connected to PG&E’s Tidewater Substation (“Tidewater,” or the “Substation”) by two 230 kilovolt lines. Sias Deck Ex. 1 (Carloni Dep.) 47:17-22; id. Ex. 2 (Kromer Dep.) 40:5-10. Those connections allow the Cogen to sell electricity to the grid when it produces more than the Refinery draws from it, and' also allow the Refinery to draw power from the grid when the Cogen does not produce enough power to meet its needs. See Sias Deck Ex. 3 (Carloni Dep.) 53:3-6. Tidewater — which, in addition to the Cogen and Refinery, also serves PG&E’s customers in Concord, California — is connected to' the larger grid by two 230 kilovolt transmission lines, the Pittsburg and El Sobrante lines. Sias Deck Ex. 6 at 4; Begland Deck Ex. 6 (Kromer Dep.) 67:11-12; Nie Deck (dkt. 81) ¶ 2. '

A meeting took place between PG&E and a' predecessor to FWM (hereinafter referenced as FWM for convenience) in 1986. See Begland Deck Ex. 17. During that meeting, PG&E and FWM discussed frequency settings for the Cogen, and PG&E assured FWM that PG&E’s' load shedding system would activate before the grid frequency dropped to levels dangerous to the Cogen. Id. Tesoro’s expert Brian Rahman testified that the load shedding systems at the Substation “had been disabled for some time, so they were no longer functioning” at the time of the 2010 outage. Begland Deck Ex. 7 (Rahman Dep.) 53:4-7.’

2. Pre-Outage Identification of Risks

a. Synch Switches

Controls at the Tidewater Substation included a number of synchronization switches, or “synch switches.” Based on the configuration of the transmission lines at the Substation, placing more than one of the switches in the “on” position at the same time could result in a loss of power. Accordingly,

PG&E standard synch switch installation currently includes both of the following design mechanisms intended to prevent the incorrect operation of the synch switches:
1. The switch is operated by a removable keyed handle. There is a mechanical interlock that only allows the handle to be removed in the “OFF” position.
2. There is one and only one keyed handle per substation control room.

Nie Deck Ex. 1 (PG&E Root Cause Analysis) at PG&E0736.3 In other words, whenever one switch is in' the “on” position, there is no way to turn any other switch to the “on” position without first turning the first switch off so that the handle can be moved to the second switch.

[1174]*1174Richard White, who participated in an inspection of the Substation sometime in 2010 before the outage, testified that at the time of the inspection, he informed “the team that was involved” that the synch switches at Tidewater did not have a mechanical interlock feature. Begland Decl. Ex. 8 (White Dep.) 41:9-25. He also testified that the lack of that feature was a “fairly” serious design defect, and that he did not recall discussing the urgency of remedying the defect. Id. 54:1-8, 56:22-57:1. He did not recall any other instance in which he identified synch switches at a PG&E substation lacking the mechanical interlock feature. Id. 43:22-44:2. PG&E’s “Substation Switching Procedures” provide that when a circuit breaker is equipped with a synch switch, the final step in operating the circuit breaker is to return the synch switch to the “off’ position, Begland Decl. Ex. 10.

b. Risk of Islanding

In April of 2010, PG&E engineer Sebastian Fiala prepared a “Load at Risk Notification” reporting that if the Tidewater Substation became isolated or “islanded” from the grid as a whole, “[t]he majority of the time, loading at Tidewater will exceed generation at [the Cogen], and will likely cause [the Cogen] to trip offline.” Begland Decl. Ex. 1. Such notifications are normally “sent to a fairly wide audience within PG&E.” Begland Decl. Ex. 3 (Van Rem-oortere Dep.) 20:8-9. The same notification was distributed again twelve days before the planned maintenance on November 10, 2010. Begland Decl. Ex. 4. Tesoro’s expert Brian Rahman later testified that “good utility practice” would require PG&E to notify FWM and Tesoro that it identified that risk. Begland Decl. Ex. 7 (Rahman Dep.) 160:1-163:2.

3. The Outage

PG&E routinely notified FWM when maintenance or other circumstances required PG&E to disconnect either of the transmission lines running to Tidewater. Id. 67:2-14. On October 29, 2010, PG&E notified. FWM that it intended to disconnect a line for maintenance on November 9, 2010, thus placing the Cogen (and other Tidewater customers) “on a single source” from the grid. Begland Decl. Ex. 4 at PG&E07647. The maintenance ultimately took place on November 10, 2010, and required temporarily disconnecting the El Sobrante line. Sias Decl. Ex. 6 at 4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Lamie v. United States Trustee
540 U.S. 526 (Supreme Court, 2004)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
Harris v. County of Orange
682 F.3d 1126 (Ninth Circuit, 2012)
Pacific Gas & Electric Co. v. G. W. Thomas Drayage & Rigging Co.
442 P.2d 641 (California Supreme Court, 1968)
Waters v. Pacific Telephone Co.
523 P.2d 1161 (California Supreme Court, 1974)
Langley v. Pacific Gas & Electric Co.
262 P.2d 846 (California Supreme Court, 1953)
Cole v. Pacific Telephone & Telegraph Co.
246 P.2d 686 (California Court of Appeal, 1952)
Pacific Gas & Electric Co. v. Zuckerman
189 Cal. App. 3d 1113 (California Court of Appeal, 1987)
Stern v. General Telephone Co.
50 Cal. App. 3d 538 (California Court of Appeal, 1975)
Trammell v. Western Union Telegraph Co.
57 Cal. App. 3d 538 (California Court of Appeal, 1976)
Transmix Corp. v. Southern Pacific Co.
187 Cal. App. 2d 257 (California Court of Appeal, 1960)
Pink Dot, Inc. v. Teleport Communications Group
107 Cal. Rptr. 2d 392 (California Court of Appeal, 2001)
Southern California Edison Co. v. Public Utilities Commission
124 Cal. Rptr. 2d 281 (California Court of Appeal, 2002)
Morey v. Vannucci
64 Cal. App. 4th 904 (California Court of Appeal, 1998)
King v. Burwell
135 S. Ct. 2480 (Supreme Court, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
146 F. Supp. 3d 1170, 2015 U.S. Dist. LEXIS 158066, 2015 WL 7350446, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tesoro-refining-marketing-co-v-pacific-gas-electric-co-cand-2015.