Terry v. Riverside Transportation Co.

8 Mass. App. Dec. 74
CourtMassachusetts District Court, Appellate Division
DecidedNovember 10, 1954
DocketNo. 368161
StatusPublished

This text of 8 Mass. App. Dec. 74 (Terry v. Riverside Transportation Co.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terry v. Riverside Transportation Co., 8 Mass. App. Dec. 74 (Mass. Ct. App. 1954).

Opinion

Ad low, }.

This is an action of contract or tort in which William J. Terry, doing business as the Boston Machinery and Tool Company, hereinafter referred to as the Shipper, and the Williams Machine Company, Inc., of Poultney, Vermont, hereinafter referred to as the Consignee, claim damages for injury to a lathe during transit from Boston, Massachusetts, to Poultney, Vermont.

There was evidence that on February 10, 1953, the Shipper sold to the Consignee a lathe that was then located at the plant of the Atlantic Works in East Boston; that upon completion of the sale, the [75]*75Shipper arranged with Joseph Sacco, treasurer of the Riverside Transportation Company, and hereinafter referred to as the Carrier, with respect to shipping the lathe to the plant of the Consignee in Poultney, Vermont. Several days before the lathe was transported to Vermont the Shipper saw the Carrier’s employees placing skids under it preparatory to its being loaded on a trailer. The skids were six inches wide, eight inches high and forty feet long, and had been put under the legs that hold the bed of the lathe. They had been securely fastened to the machine by lag bolts. This lathe was forty-two feet long overall, with a thirty inch gear. It was made up of head stock, tail stock, bed and legs, the bed being the main casting of the whole body of the machine. This lathe was forty-two feet in length overall, and consisted of two sections; there was a twelve foot section at the tail stock, and a thirty foot section at the other end. Two bolts on each side of the lathe joined the sections where they came together. The bolts had no heads on them but were fastened by nuts on both ends.

The Shipper testified that he telephoned to the Treasurer of the Carrier company and complained that the skids were not heavy enough to support the machine over the road, but that the Treasurer replied that they were heavy enough and that he would take the responsibility for transporting the lathe. There was other evidence to indicate that the Shipper was unhappy about the size of the skids, but that Sacco, the Treasurer, assured him at the time with the words, "Ill take care of it.” The lathe weighed about fifteen tons. At the time that the arrangement for the transportation was made with the Carrier, it was expressly agreed that the lathe would be unloaded by the Consignee at Poultney, Vermont.

Pursuant to the arrangement, and after the skids had been attached to the legs of the lathe, the lathe was placed on a trailer which was drawn over the road to the plant of the Consignee in Vermont. The [76]*76bill of lading was signed by the Treasurer of the Consignee corporation, while the lathe was still on the trailer and after a representative of the Consignee corporation had examined the lathe. Thereafter, the employees of the Consignee took complete control of the lathe and proceeded to unload it into the machine shop of the Consignee.

Thomas Barrington, a rigger in the employ of the Consignee, testified that he examined the machine when it arrived; that there was an overhang of twelve feet of the machine beyond the rear end of the trailer, but that the machine had been reinforced for purposes of transportation by a shoulder which supported a chain which extended to that part of the lathe which overhung the trailer. After the Consignee’s agents took control of the situation under the directions of the rigger, Barrington, they proceeded to back the trailer up to the front entrance of the shop and to build a ramp from the rear of the trailer into the shop which ramp would permit the unloading of the lathe. Five or six men assisted Barrington in this task.

Tlie ramp was forty-five to forty-eight feet long: it was made up of cribbing and five by eight inch timbers. It started at the floor of the shop and went up gradually to the height of the trailer platform, which was about four feet. After this, Barrington and his assistants jacked up the lathe six inches or so and put six inch by four foot rollers under it. The rollers were long enough to go under the skids. There were probably five rollers under the lathe on the trailer before they proceeded to unload it. After that, they ran a line from a truck that was backed up to a side door of the shop and the line was brought to the rear of the lathe and fastened about six or eight feet from the end of it. The truck to which this line was attached was started in motion and the lathe was eased out onto the ramp. A set of blocks was hitched to the front end of the lathe and to the front end of the trailer so as to snub the lathe down the [77]*77ramp, in this way easing the machine down while on the rollers.

As the lathe moved toward the rear of the trailer, the rollers which the lathe already passed over were removed, and reinserted at the other end. When all but eight feet of the lathe teas off the ramp there was a loud noise and Barrington noticed the lathe sag over a space of about thirty-four feet where the machine teas suspended between the ramp and the floor. He then noticed a crack on the side of the lathe. The noise that he heard was "as if you hit a piece of casting with a big hammer.” To relieve the strain on the crack, Barrington took the rollers out from under the head stock and let the lathe down, in this manner eliminating the sag. The next day he made a more careful examination of the lathe and found that three of the four nuts on the two bolts on one side of the lathe which held the two sections together were loose. The other nut on the side where the crack occurred was tight. Barrington had not examined the nuts prior to the time when the crack occurred, nor did he examine the nuts until the day following,

Barrington testified that before unloading the lathe it was necessary to jack it up. This was accomplished by putting timbers in the space between the bottom of the lathe and the top of the skids. These timbers extended out beyond the skids about eight inches, and the jacks were put under the ends of these timbers. 'When the lathe was jacked up high enough the rollers were put under the skids. He also testified that the first time he saw any crack in the lathe was after he heard the loud noise. It was Barrington’s opinion that if ten by ten inch skids were used on the lathe, there wouldn’t have been so much sag and that if he had to do the job he would have had a heavier skid under the lathe. He testified that the ten inch by ten inch skid wouldn’t be very much stronger or give much more support to the machine.

Barrington testified that in his opinion the crack [78]*78was caused by the fact that two of the nuts on the inside and one nut on the outside of the bed were loose, while the upper outside nut was tight, with the result that the strain of the whole machine when suspended over the ramp was on the single tight nut. In his own words, "The weakness happened to be on that one side, so that’s why it cracked, it had no support from the other side at all. The one side sustained the load. If the nuts had been tight you’d have both sides for strength.” He also stated that "you would depend more on the bed (of the lathe) itself to sustain the weight than you would on the skids at that particular point,” and that he depended on the strength of the machine rather than on the skids to withstand the suspension that he anticipated. It was his opinion that the skids wouldn’t give unless the machine gave.

A witness, Austin F.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carter v. J. H. Lockey Piano Case Co.
58 N.E. 476 (Massachusetts Supreme Judicial Court, 1900)
Malinoski v. D. S. McGrath, Inc.
186 N.E. 225 (Massachusetts Supreme Judicial Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
8 Mass. App. Dec. 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terry-v-riverside-transportation-co-massdistctapp-1954.