Terry Ray Construction, Inc. v. Cenco Corporation, D/B/A Central Plumbing & Electric Supply Co.

CourtCourt of Appeals of Texas
DecidedFebruary 1, 2001
Docket13-99-00430-CV
StatusPublished

This text of Terry Ray Construction, Inc. v. Cenco Corporation, D/B/A Central Plumbing & Electric Supply Co. (Terry Ray Construction, Inc. v. Cenco Corporation, D/B/A Central Plumbing & Electric Supply Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terry Ray Construction, Inc. v. Cenco Corporation, D/B/A Central Plumbing & Electric Supply Co., (Tex. Ct. App. 2001).

Opinion



NUMBER 13-99-430-CV


COURT OF APPEALS


THIRTEENTH DISTRICT OF TEXAS


CORPUS CHRISTI

____________________________________________________________________

TERRY RAY CONSTRUCTION, INC., Appellant,

v.


CENCO CORPORATION, D/B/A CENTRAL

PLUMBING & ELECTRIC SUPPLY CO., Appellee.

____________________________________________________________________

On appeal from the County Court at Law Number 1
of Hidalgo County, Texas.

____________________________________________________________________

O P I N I O N


Before Justices Hinojosa, Yañez, and Chavez(1)
Opinion by Justice Hinojosa


Appellee, Cenco Corporation d/b/a Central Plumbing & Electric Supply Co., filed a sworn account suit against appellant, Terry Ray Construction, Inc. Appellant filed a counterclaim alleging that: (1) the parties had an agreement that Cenco would not charge more than $45,600 for plumbing supplies and (2) interest charged by Cenco was usurious. After a bench trial, the trial court denied appellant's counterclaim and granted a judgment in favor of appellee. By two issues, appellant contends the evidence is legally and factually insufficient to support the trial court's failure to find Cenco's interest charges usurious and failure to enforce the agreement between the parties.

A. Factual and Procedural History

The undisputed facts are that in 1995, appellant was awarded a contract for construction work at two schools in Brownsville. The project was referred to as the Stell and Faulk kitchen additions. Appellant subcontracted with RC Plumbing ("RC") to perform the plumbing work on the project. RC contracted with Cenco to supply all the plumbing fixtures necessary for the project. As work progressed, Cenco had problems getting RC to timely pay for the materials it supplied. In order to facilitate payments to Cenco, and to insure there would be no materialman's lien(2) on the finished project, Terry Ray, appellant's president, drafted a joint check agreement. The agreement was between appellant, RC and Cenco, was printed on appellant's letterhead, and stated:

December 20, 1995

Supplier: Central Plumbing & Electric Supply Company

315 Southwest

Harlingen, TX 78550

Central Plumbing & Electric Supply Company is selling to R. C. Plumbing Company materials to be incorporated into the Stell and Faulk Kitchen Additions located in Brownsville, Texas.

The overall value of all materials and fixtures is $45,600 including materials previously incorporated and paid for with Checks #28540, 28230 & 28388 totaling $23,344.38.

R.C. Plumbing agrees that in consideration for Central Plumbing & Electric furnishing materials for the referenced project, checks to be issued under this contract will be paid jointly to R. C. Plumbing and Central Plumbing & Electric Supply Company.

In order to expedite payment, Terry Ray Construction, Inc. must receive, on or before the 25th day of each month, copies of invoices or statements showing the value of materials supplied by Central Plumbing & Electric, on the above referenced project.

Nothing in this agreement shall be construed to make Terry Ray Construction, Inc. a party to any contract, purchase order, or any other agreement between R.C. Plumbing and Central Plumbing & Electric Supply Company, nor to infer responsibility for the whole or partial performance thereof. By agreeing to this joint check agreement, Central Plumbing & Electric Supply Company agrees to provide all materials necessary for the above referenced project.

Accepted by: Subcontractor

[signed by Robert Camacho for R.C. Plumbing]

Accepted by: Supplier

[signed by Paul Pena for Cenco]

Accepted by: Terry Ray Construction, Inc.

[signed by Terry Ray, President]

In February, RC filed for bankruptcy and walked off the job. Wanting to complete the Stell and Faulk project on time, Ray contacted Cenco about supplying the remaining materials for the job. Cenco then delivered a large shipment of materials directly to appellant. On March 20, 1996, Terry Ray, on behalf of appellant, filled out a credit application and submitted it to Cenco. That same day, Cenco approved the application and granted appellant a credit line of $17,000. The following day, appellant issued a joint check in the amount of $5,071.41 to Cenco and RC for the balance RC owed Cenco. Cenco then supplied the materials that appellant needed to complete the project and charged them to appellant's account.

After Cenco delivered all the materials appellant needed, the balance on appellant's account was $15,342.54. Cenco demanded payment, but appellant refused to pay the entire amount. Appellant asserted Cenco was limited to the $45,600 amount set out in the joint check agreement. Appellant later offered a check made out jointly to Cenco and RC in the amount of $10,606.67 ($45,600 minus prior payments for materials), conditioned upon Cenco's release of all liens. Cenco refused the offer and filed suit against appellant.

Appellant then filed a counterclaim claiming that the joint check agreement constituted a binding contract between Cenco and appellant that Cenco would not charge more than $45,600 for the plumbing materials it had agreed to supply for the Stell and Faulk project. Appellant also claimed that the interest charged by Cenco was usurious.

After a bench trial, the court rendered judgment for Cenco in the amount of $15,342.54, pre-judgment interest at the rate of six percent per annum, attorney's fees, court costs and post-judgment interest. The court denied all relief requested by appellant in its counterclaim. Appellant then filed this appeal.

B. Findings of Fact and Conclusions of Law

The trial court made the following findings of fact:

(1) on December 20, 1995, appellant, RC and Cenco entered into a joint check agreement;

(2) on March 20, 1996, after RC stopped work on the project, appellant entered into an agreement with Cenco regarding the purchase of the remaining materials;

(3) on March 21, 1996, appellant paid $5,071.41 pursuant to the joint check agreement for materials previously delivered;

(4) appellant and Cenco agreed in writing that appellant would incur a finance charge at the rate of 1.5% per month on invoices unpaid after the 10th day of the month following the prior month's billing;

(5) Cenco delivered the remaining materials to appellant;

(6) the reasonable market value of those materials was $15,342.54;

(7) appellant's account became past due;

(8) Cenco made written demand for payment of the $15,342.54 thirty days before filing suit;

(9) appellant did not pay the demanded amount;

(10) appellant conditionally offered $10,606.07 to Cenco in settlement for Cenco's claim; and

(11) $32,000 is a reasonable attorney's fee.

The trial court made the following conclusions of law:

(1) appellant is indebted to Cenco in the sum of $15,342.54 for plumbing supplies;

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. City of Seven Points
806 S.W.2d 791 (Texas Supreme Court, 1991)
Humphrey v. Camelot Retirement Community
893 S.W.2d 55 (Court of Appeals of Texas, 1994)
Peoples State Bank of Clyde v. Andrews
881 S.W.2d 520 (Court of Appeals of Texas, 1994)
Westech Engineering, Inc. v. Clearwater Constructors, Inc.
835 S.W.2d 190 (Court of Appeals of Texas, 1992)
Croucher v. Croucher
660 S.W.2d 55 (Texas Supreme Court, 1983)
Texas Gas Utilities Company v. Barrett
460 S.W.2d 409 (Texas Supreme Court, 1970)
Stable Energy, L.P. v. Newberry
999 S.W.2d 538 (Court of Appeals of Texas, 1999)
Allee v. Benser
779 S.W.2d 61 (Texas Supreme Court, 1988)
Alamo Lumber Co. v. Gold
661 S.W.2d 926 (Texas Supreme Court, 1983)
In Re Cummings
13 S.W.3d 472 (Court of Appeals of Texas, 2000)
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
Asai v. Vanco Insulation Abatement, Inc.
932 S.W.2d 118 (Court of Appeals of Texas, 1996)
Micrea, Inc. v. Eureka Life Insurance Company of America
534 S.W.2d 348 (Court of Appeals of Texas, 1976)
Hickey v. Couchman
797 S.W.2d 103 (Court of Appeals of Texas, 1990)
Patterson v. Neel
610 S.W.2d 154 (Court of Appeals of Texas, 1980)
Bocquet v. Herring
972 S.W.2d 19 (Texas Supreme Court, 1998)
Houston Sash and Door Co., Inc. v. Heaner
577 S.W.2d 217 (Texas Supreme Court, 1979)
Maeberry v. Gayle
955 S.W.2d 875 (Court of Appeals of Texas, 1997)
Sterner v. Marathon Oil Co.
767 S.W.2d 686 (Texas Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
Terry Ray Construction, Inc. v. Cenco Corporation, D/B/A Central Plumbing & Electric Supply Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/terry-ray-construction-inc-v-cenco-corporation-dba-texapp-2001.