Terry Contracting, Inc. v. Levitt

54 A.D.2d 1, 386 N.Y.S.2d 233, 1976 N.Y. App. Div. LEXIS 13083

Opinions

Greenblott, J.P.

Petitioner Aetna Casualty and Surety Company (Aetna) issued a performance bond on behalf of Terry Contracting, Inc. (Terry) to the State of New York, in connection with a contract entered into between Terry and the State on March 19, 1959 for the construction of a portion of Prospect Expressway, Fort Hamilton Parkway Interchange, for the benefit of those performing labor for the project and supplying materials thereto. The bond provided that Aetna was "subrogated to all rights, privileges and properties of the principal(s) in said contract” and that Terry assign "any and all monies and properties that may be due and payable to” Terry "or that may thereafter become due and payable” to Terry "on account of [the] contract or on account of extra work or materials supplied in connection therewith”.

Between April, 1959 and July, 1962, Terry performed services pursuant to said contract with the State, during which disputes arose between the parties. Terry contended that the [3] State had breached the contract in that it had compelled Terry to perform work over and beyond that specified by the contract, and that the State had delayed and disrupted Terry’s performance of the contract, all of which greatly increased the cost of performance of the work through the employment of additional labor and the furnishing of additional materials and services. In an action for breach of contract following completion of the project, Terry recovered judgment against the State (Terry Contr. v State of New York, 42 AD2d 619), part of said sum representing damages for breach of contract and part representing disputed sums due Terry under the terms of the contract. At the commencement of this proceeding, after accumulation of interest and certain additional items the State stands liable in the sum of $322,636.08.

At some point in time Terry had borrowed $330,000 from the Royal State Bank of New York (to whom Chemical Bank is now the ultimate successor in interest), of which $234,654.55 plus interest remains unpaid. The notes evidencing this indebtedness were already past due as of September, 1961 when Terry, on July 11, 1962, gave Royal State Bank security therefor by assigning to it "the sum of $700,000 out of the proceeds of its claims against the State for damages sustained through the breaches of the terms of said Contract by the State of New York in compelling the performance of work above and beyond that specified by the terms of the contract, by compelling work to be performed [by] methods which differed from those on the Plans and Specifications, by delaying the work without cause, and by disrupting the work without cause, all of which required the employment of additional labor, the furnishing of additional materials and service without compensation, and for other breaches of said contract”.

Aetna having paid $419,092.63 as surety for labor and materials, Terry and Aetna instituted this proceeding to compel the Comptroller to pay to Aetna the full amount of Terry’s judgment against the State. Royal State Bank, by its successors, cross-petitioned, claiming a prior right, by virtue of the assignment of July 11, 1962, to the sum of $152,191.71, claimed to represent the amount awarded to Terry as damages for breach of contract. Finding the amount awarded for damages for breach of contract to be $98,346.55, Special Term (after certain deductions not challenged here) granted the cross petition to the extent of directing payment to Chemical [4] Bank in the sum of $96,041.11.* So much of the judgment as incorporates this directive is the subject of this appeal.

In holding with Royal and its successors, Special Term found that the assignment to Aetna did not include moneys awarded for breach of a contract, distinguishing moneys owed for work performed under the contract, and further held that since the claim for damages for breach of contract did not exist at the time of the assignment to Aetna, such an assignment could not adversely affect the interest of third-party creditors. Dealing first with the latter holding, we are of the view that the rule has been misapplied. Potential rights under an executory contract are assignable (see, generally, 3 NY Jur, Assignments, § 20), but it is claimed that the equitable lien of such an assignment is inferior to the rights of creditors. The case of Matter of Black v Sully (138 App Div 562) dealt with an assignment which had been enjoined, so that the assignment was in fraud of creditors; therefore, the case does not support the conclusion reached by Special Term or the contention of respondents. Special Term also relied on Matter of Schaefer Brewing Co. v Amsterdam Tavern (171 Misc 352). That case cites Titusville Iron Co. v City of New York (207 NY 203). There, however, a forfeiture rather than an assignment was involved, and title in the claimed property had passed to a receiver in bankruptcy before the forfeiture and before any transfer of possession. The facts in the present case are considerably different and thus distinguishable. Firstly, the assignment to the bank repeatedly acknowledges the assignment to Aetna and expressly subordinates the former’s interest (although the scope of these provisions is here disputed). Secondly, and perhaps sufficient not only to distinguish the above-cited cases but also to warrant the application of a different rule is the fact that insofar as the State’s breaches of contract resulted in increased payments for labor and materials, the payments required to be made by Aetna as surety were of necessity increased in the same amount. In such circumstances, we see no reason why the claim of Aetna should stand on a lesser footing than the claim of the bank as [5] creditor. Furthermore, as is evident from repeated references in the bank’s assignment, the assignment to Royal was taken with actual knowledge of the assignment to Aetna.

The priority of the claims, therefore, must be determined by the terms of the assignments. As previously noted, Terry assigned to Aetna without restriction or limitation, "any and all monies * * * that may be * * * or * * * become * * * payable * * * on account of [the] contract or on account of extra work or materials supplied in connection therewith”. The basis for Terry’s claim against the State on its sixth cause of action (which resulted in the award which is the subject of the present dispute) was that the State, by interference causing delays in Terry’s performance, had increased Terry’s costs for labor, materials, and the like. These increased costs were thus incurred so as to enable Terry to complete the work for which it had contracted. We fail to see how payments made therefor, merely because they are denominated damages for breach of contract, can be regarded as other than payments "on account of [the] contract” or at the very least as payments "on account of extra work or materials supplied in connection therewith.”

The mere fact the bank was subsequently assigned only an interest in sums as might be awarded as damages for breach of contract does not of itself indicate that such sums were intended to be excluded from Aetna’s assignment, and in this case the bank’s assignment by its own terms clearly negates such a conclusion. That document declares:

Free access — add to your briefcase to read the full text and ask questions with AI

Terry Contracting, Inc. v. Levitt, 54 A.D.2d 1, 386 N.Y.S.2d 233, 1976 N.Y. App. Div. LEXIS 13083 (N.Y. Ct. App. 1976).

54 A.D.2d 1 (Terry Contracting, Inc. v. Levitt) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Titusville Iron Co. v. . City of New York
100 N.E. 806 (New York Court of Appeals, 1912)
In re Black
138 A.D. 562 (Appellate Division of the Supreme Court of New York, 1910)
F. & M. Schaefer Brewing Co. v. Amsterdam Tavern, Inc.
171 Misc. 352 (New York Supreme Court, 1939)
Terry Contracting, Inc. v. State
42 A.D.2d 619 (Appellate Division of the Supreme Court of New York, 1973)