Terex Corp v. Ingalls Shipblding Inc

CourtMississippi Supreme Court
DecidedMarch 2, 1992
Docket92-CA-00690-SCT
StatusPublished

This text of Terex Corp v. Ingalls Shipblding Inc (Terex Corp v. Ingalls Shipblding Inc) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terex Corp v. Ingalls Shipblding Inc, (Mich. 1992).

Opinion

IN THE SUPREME COURT OF MISSISSIPPI NO. 92-CA-00690-SCT TEREX CORPORATION v. INGALLS SHIPBUILDING, INC.

DATE OF JUDGMENT: 3/2/92 TRIAL JUDGE: HON. BILL JONES COURT FROM WHICH JACKSON COUNTY CIRCUIT COURT APPEALED: ATTORNEYS FOR WILLIAM N. REED APPELLANT: H. MITCHELL COWAN ATTORNEYS FOR APPELLEE: WILLIAM T. REED

GEORGE M. SIMMERMAN,JR. NATURE OF THE CASE: CIVIL - CONTRACT DISPOSITION: AFFIRMED IN PART, REVERSED AND RENDERED IN PART - 3/28/96 MOTION FOR REHEARING FILED: MANDATE ISSUED: 4/18/96

EN BANC.

SMITH, JUSTICE, FOR THE COURT:

¶1. On December 10, 1985, Terex Corporation ("Terex") and Ingalls Shipbuilding, Inc. ("Ingalls") contracted in the amount of $252, 920 for Terex to supply two 10,000 pound terrain diesel powered forklifts to be used on a ship, designated LHD-1, built for the United States Navy. The Navy had very specific criteria for the forklifts and also required extensive, expensive testing on the original forklift built. Included in the contract were options for Ingalls to procure more forklifts from Terex in the event the Navy should award more contracts for LHDs to Ingalls. Ingalls exercised this option in September of 1987. Prior to Ingalls exercising its option, Terex experienced major changes. Northwest Engineering Company acquired Terex and closed Terex's United States manufacturing plant where these specific forklifts were constructed. Terex could no longer build these forklifts, so Terex attempted to locate other forklifts that would meet the specifications. Ingalls discovered a height limitation of 117 inches when they were inspecting one of the replacement forklifts that Terex suggested and the forklift proved to be too tall. In fact, the first forklift set that Terex built was too tall, but Ingalls modified it accordingly.

¶2. When Ingalls first filed its Complaint, Terex sought protection from the Ohio Bankruptcy Court. The Ohio bankruptcy judge dismissed that case and Terex was ordered by the lower court to pay Ingalls' attorney's fees of $16,478.64. The final amended complaint, filed February 1, 1991, alleged that Terex breached its subcontract with Ingalls in refusing to supply the forklifts and was therefore liable for actual damages in the amount of $227,454. This was the excess amount that Ingalls claimed that it had to pay to procure the forklifts. Ingalls also alleged that Terex acted tortiously and in bad faith when Terex refused to honor the option contract, and when Terex requested the temporary restraining order in bankruptcy.

¶3. The case was tried by a jury in the Jackson County Circuit Court. The jury returned a verdict for Ingalls for $227,454. Terex appeals to this Court arguing that Ingalls' modification of the contract relieved Terex of any obligation to perform; that Ingalls did not purchase reasonably comparable substitute forklifts; that Ingalls failed to satisfy a condition precedent; that the jury's award of damages is contrary to the court's instructions and against the overwhelming weight of the evidence; and that the circuit court erred in refusing to vacate the award of attorney's fees under the Litigation Accountability Act. Ingalls cross-appeals for assessment of prejudgment interest, attorney's fees and costs pursuant to the Litigation Accountability Act of 1988 Miss. Code Ann. § 11-55-1, et seq, (Supp. 1995), all of which the trial court denied.

¶4. Issues I - III raised by Terex are without merit and need not be discussed. We address Issue IV which states that the jury's award of damages was contrary to the overwhelming weight of the evidence and that the trial court erred in denying Terex a remittitur and Issue V which is a cross-appeal by Ingalls requesting prejudgment interest and attorneys fees. After a thorough examination of the record and case authority, we find these issues meritorious, thus holding that Terex was entitled to the remittitur and Ingalls was entitled to prejudgment interest.

STATEMENT OF THE FACTS

¶5. On December 10, 1985, Terex Corporation ("Terex") and Ingalls Shipbuilding, Inc. ("Ingalls") contracted in the amount of $252,920 for Terex to supply two 10,000 pound terrain diesel powered forklifts to be used on a ship, designated LHD-1, built for the United States Navy. The two forklifts are referred to in tandem as a "ship set." Pursuant to Article III of the Special Provisions of the Ingalls purchase order, Terex granted Ingalls options to buy additional ship sets of the forklift for three ships potentially to be constructed by Ingalls for the Navy in the future. Ingalls argued that this was a supply contract which required Terex to either manufacture the units or have the units manufactured by someone else. At the time the purchase order was issued, Terex was the debtor-in-possession in a Chapter 11 bankruptcy proceeding.

¶6. Ingalls states that Terex approached Ingalls at the behest of the Navy, after Ingalls did not receive suitable proposals from potential suppliers. Both parties admit that due to the Navy's specific requirements, these particular forklifts were difficult to locate and/or build. Terex was already building forklifts for the United States Marine Corps and these forklifts were similar to those being specified by the Navy. The forklifts would require modifications, but would save the Navy and Ingalls a portion of the testing costs and the costs necessary to integrate new components into the Navy's spare parts system. This Navy testing process is known as First Article Testing. In addition to the First Article Testing, one of the tests is called a shock test and it alone costs $50,000. This testing process is performed on the first forklift built, and applied to all subsequent units as long as the units are made in strict accordance with the original specifications.

¶7. Terex manufactured the forklifts at its plant in Hudson, Ohio. On March 31, 1987, the second option period under the purchase order expired without Ingalls having ordered any additional forklifts from Terex. On May 22, 1987, during the third option period, Ingalls and Terex first discussed Ingalls' purchase of two forklifts for a second Navy ship, LHD-2.

¶8. In the meantime, Northwest Engineering Company had purchased Terex. This transaction resulted in the closing of the Ohio plant where Terex built the forklifts. In mid-August, 1987, Terex advised Ingalls that Terex's Ohio plant was closing, that the plant in Scotland was insufficient for this particular purpose, and that other alternate sources of forklifts should be explored. Terex advised Ingalls in writing on September 14, 1987, that Terex could not build the forklifts for LHD-2.

¶9. Gerald Dickinson of Ingalls formally exercised Ingalls' option to order two forklifts for LHD-2 on September 15, 1987. From October 1987 to February 1988 Terex and Ingalls discussed alternative sources for LHD-2 forklifts. Several potential sources of forklifts were investigated by Terex and Ingalls, one of which was a forklift manufactured by John Deere, which measured 131 inches in height.

¶10. The height of the John Deere forklifts raised questions about the suitability of the Terex forklifts for LHD-1, which were already completed and in storage until time to be placed on the ship. That ship set measured 124 inches in height. The close scrutiny of the John Deere forklifts led to the discovery that the forklifts could only be a certain height, a criterion not in the specifications that Terex used to build the first ship set. Some of the doors on the LHD-1 measured 120 inches and the forklift must be able to move unhindered throughout the ship.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Odom v. Roberts
606 So. 2d 114 (Mississippi Supreme Court, 1992)
Rubel, Executors v. Rubel
75 So. 2d 59 (Mississippi Supreme Court, 1954)
Greenlee v. Mitchell
607 So. 2d 97 (Mississippi Supreme Court, 1992)
Merritt v. State
517 So. 2d 517 (Mississippi Supreme Court, 1987)
Hans Const. Co., Inc. v. Drummond
653 So. 2d 253 (Mississippi Supreme Court, 1995)
Green v. Grant
641 So. 2d 1203 (Mississippi Supreme Court, 1994)
Stubblefield v. Jesco, Inc.
464 So. 2d 47 (Mississippi Supreme Court, 1985)
Bell v. City of Bay St. Louis
467 So. 2d 657 (Mississippi Supreme Court, 1985)
Simpson v. State Farm Fire and Cas. Co.
564 So. 2d 1374 (Mississippi Supreme Court, 1990)
Pioneer Life Ins. Co. of Illinois v. Moss
513 So. 2d 927 (Mississippi Supreme Court, 1987)
Dixon v. State
519 So. 2d 1226 (Mississippi Supreme Court, 1988)
Sunburst Bank v. Keith
648 So. 2d 1147 (Mississippi Supreme Court, 1995)
Valley Forge Ins./CNA v. Strickland
620 So. 2d 535 (Mississippi Supreme Court, 1993)
Aetna Cas. & Sur. Co. v. Doleac Elec. Co.
471 So. 2d 325 (Mississippi Supreme Court, 1985)
Weems v. American SEC. Ins. Co.
450 So. 2d 431 (Mississippi Supreme Court, 1984)
Wells Fargo Armored Service Corp. v. Turner
543 So. 2d 154 (Mississippi Supreme Court, 1989)
City of Mound Bayou v. Roy Collins Const.
499 So. 2d 1354 (Mississippi Supreme Court, 1986)
Stockett v. Exxon Corporation
312 So. 2d 709 (Mississippi Supreme Court, 1975)
Universal Life Ins. Co. v. Veasley
610 So. 2d 290 (Mississippi Supreme Court, 1992)
Warwick v. Matheney
603 So. 2d 330 (Mississippi Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
Terex Corp v. Ingalls Shipblding Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terex-corp-v-ingalls-shipblding-inc-miss-1992.