Teresa Von Illyes v. Cary Rolfing, Laura Rolfing, and Kenneth Rolfing

Court of Appeals of Texas·Decided March 28, 2023·No. 07-22-00129-CV·Published

Opinion

In The

Court of Appeals

Seventh District of Texas at Amarillo

No. 07-22-00129-CV

TERESA VON ILLYES, APPELLANT V.

CARY ROLFING, LAURA ROLFING, AND KENNETH ROLFING, APPELLEES

On Appeal from the 17th District Court Tarrant County, Texas1

Trial Court No. 017-311724-19, Honorable Melody Wilkinson, Presiding

March 28, 2023

MEMORANDUM OPINION

Before PARKER and DOSS and YARBROUGH, JJ.

Appellant Teresa Von Illyes appeals from the jury verdict and judgment in favor of the Rolfings on claims arising from the remodel of the Rolfings’ home. We affirm in part and reverse and render in part.

1 Pursuant to the Texas Supreme Court’s docket equalization efforts, this case was transferred to this Court from the Second Court of Appeals. See TEX. GOV’T CODE ANN. § 73.001. Should a conflict exist between precedent of the Second Court of Appeals and this Court on any relevant issue, this appeal will be decided in accordance with the precedent of the transferor court. TEX. R. APP. P. 41.3.

BACKGROUND

In June of 2019, Cary and Laura Rolfing, brother and sister, sought bids from contractors to renovate and remodel a home owned by their father, Kenneth Rolfing.2 The home was rundown and in poor condition. The Rolfings received a bid from Teresa Von Illyes and John Barton, d/b/a Clearfork General Construction. The Rolfings entered into a contract with Clearfork. The contract price was $67,150 and called for a six-week time frame for completion. The contract required payments by the Rolfings of “one third of the total project costs up front with the second payment at time of one[-]third completion and the final payment at time of completion of project.” The contract provided, among other things, that Clearfork would replace interior and exterior doors and windows including trim work; replace wood flooring; remove and install new sheetrock; repair wall cracks; paint walls and ceilings throughout; remove/replace kitchen cabinets and countertops; remove/replace appliances (oven, refrigerator, dishwasher); install new light switches, covers, and plugs throughout; and install thermostats and smoke detectors. Although the contract generally describes the work to be done, the contract does not itemize the cost of any work to be performed. Von Illyes hired her father, Floyd Stober, to oversee the project.

The Rolfings made the first payment on the contract before work began. Cary testified that there were problems within the first two weeks because “there was no one there to do the work.” He expected the project to be completed by “mid to late July at the

2 Because the appellees share the same last name, when referring to them individually, we will refer to them by their first names.

latest.” Soon after construction began, changes were made outside the contract for roof repair ($7,000) and ductwork ($1,950). As of mid-July, the renovation was one-third complete, and the Rolfings had paid Von Illyes and Clearfork a total of $44,200 on the contract, plus an additional $8,950 for the roof and ductwork.

Through text messages and emails to Von Illyes, Cary expressed his frustration that construction was behind schedule and displeasure with the workmanship of the project as a whole. In early August, Cary made a “punch list” of items that he and Laura had identified as requiring completion or correction to finish the project. Cary also put blue tape on those areas that needed to be repaired or repainted.

Separately, both Von Illyes and Barton sought final payment for the project from Cary. Cary refused to make the final payment because of his complaints that the work was neither complete nor satisfactory. Von Illyes filed a mechanic’s lien against the property on August 26. On August 28, Barton texted Cary a picture of a mechanic’s lien that Barton had filed. After learning that liens had been filed, Cary told the workers at the house to take their tools and leave. Cary emailed Von Illyes to “cease work” until the matter was resolved.

The Rolfings sued Von Illyes, Barton, and Clearfork seeking release of liens, damages for breach of contract and deceptive trade practices, and attorney’s fees. Von Illyes and Barton each filed a counterclaim alleging breach of contract by the Rolfings for nonpayment. Von Illyes also sought recovery in quantum meruit.

Cary testified to a host of problems with the workmanship and quality of the work performed. More than 130 photographs were admitted into evidence depicting the poor

workmanship and substandard quality of the remodel job performed by Clearfork. Cary testified that the project was not completed by August 26, 2016, and less than ten percent of the items on the punch list had been completed when the workers left.

Von Illyes testified that electrical, plumbing, and structural issues, among other things, caused delays with the project. She acknowledged that the Rolfings paid $44,200 plus the amount agreed upon for the roof and duct work, but still owed approximately $23,000 on the contract. She admitted that they are entitled to an offset of $2,000 for some things that were not finished. However, she testified that the project was complete as of August 26. Von Illyes disputed that Cary formally gave her a punch list. She claimed that Clearfork prepared its own punch list, but Cary kicked the workers off the property before the work on the list could be completed. Von Illyes testified that Cary did not show up for the final walkthrough. She also noted that, “fixing or repairing blue-tape items after a final walkthrough is not part of the completion of a project.”

The case was tried to a jury which found that Clearfork breached the contract and failed to comply with the implied warranty of good and workmanlike performance. The jury awarded the Rolfings damages in the amount of $27,1503 and $6,000 in legal fees. Von Illyes filed a motion for judgment notwithstanding the verdict. The trial court entered

3 The Rolfings brought claims for breach of contract and violations of the Texas Deceptive Trade Practices Act. The jury awarded the Rolfings identical damages of $25,150 for loss of benefit of the bargain and $2,000 for cost of repair in response to Question 2 (damages for breach of contract) and Question 7 (damages for violation of the D.T.P.A.). The Rolfings failed to obtain the necessary jury findings in their favor as to the alleged violations of the Texas Deceptive Trade Practices Act. The trial court’s judgment awarded the Rolfings total damages of $27,150 plus attorney’s fees and costs. Von Illyes has raised no challenge to the jury’s findings related to liability for breach of contract.

judgment on the jury’s verdict. After her motion for new trial was overruled by operation of law, Von Illyes brought this appeal. Barton did not appeal the trial court’s judgment.

In her first two issues, Von Illyes challenges the legal and factual sufficiency of the evidence to support the award of damages in favor of the Rolfings. In her third issue, she contends that the jury’s determination that she failed to complete compensable work for which she was not compensated is against the great weight of the evidence.

STANDARD OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Teresa Von Illyes v. Cary Rolfing, Laura Rolfing, and Kenneth Rolfing, (Tex. Ct. App. 2023).

Teresa Von Illyes v. Cary Rolfing, Laura Rolfing, and Kenneth Rolfing (Teresa Von Illyes v. Cary Rolfing, Laura Rolfing, and Kenneth Rolfing) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Osterberg v. Peca
12 S.W.3d 31 (Texas Supreme Court, 2000)
Dallas Railway & Terminal Company v. Gossett
294 S.W.2d 377 (Texas Supreme Court, 1956)
Walker & Associates Surveying, Inc. v. Austin
301 S.W.3d 909 (Court of Appeals of Texas, 2010)
Vortt Exploration Co., Inc. v. Chevron USA, Inc.
787 S.W.2d 942 (Texas Supreme Court, 1990)
Leyendecker & Associates, Inc. v. Wechter
683 S.W.2d 369 (Texas Supreme Court, 1984)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
LTS Group, Inc. v. Woodcrest Capital, L.L.C.
222 S.W.3d 918 (Court of Appeals of Texas, 2007)
Reliant Energy Services, Inc. v. Cotton Valley Compression, L.L.C.
336 S.W.3d 764 (Court of Appeals of Texas, 2011)
Green International, Inc. v. Solis
951 S.W.2d 384 (Texas Supreme Court, 1997)
Nabours v. Longview Savings & Loan Ass'n
700 S.W.2d 901 (Texas Supreme Court, 1985)
Ebby Halliday Real Estate, Inc. v. Murnan
916 S.W.2d 585 (Court of Appeals of Texas, 1996)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Knight Renovations, LLC v. Charles R. Thomas
525 S.W.3d 446 (Court of Appeals of Texas, 2017)
Albert G. Hill, Jr. v. Shamoun & Norman, Llp
544 S.W.3d 724 (Texas Supreme Court, 2018)
McGinty v. Hennen
372 S.W.3d 625 (Texas Supreme Court, 2012)