Tennessee Valley Authority v. Southern Railway Co.

257 F. Supp. 121, 1966 U.S. Dist. LEXIS 6779
CourtDistrict Court, N.D. Alabama
DecidedJuly 29, 1966
DocketCiv. A. No. 1080
StatusPublished

This text of 257 F. Supp. 121 (Tennessee Valley Authority v. Southern Railway Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Valley Authority v. Southern Railway Co., 257 F. Supp. 121, 1966 U.S. Dist. LEXIS 6779 (N.D. Ala. 1966).

Opinion

LYNNE, Chief Judge.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

This cause came on to be tried before the court without a jury on April 29, May 31, June 1, and June 2, 1966, and was submitted for final judgment on the pleadings, proof, and arguments of counsel, on the limited issue as to the direct and special benefits accruing to defendants as a result of alterations to the Southern Railway bridge as stated in the pretrial order entered March 1, 1966; from all of which the court makes and [123]*123enters the following findings of fact and conclusions of law:

FINDINGS OF FACT

1. The Southern Railway Company (Southern) has owned and maintained a railroad bridge across the Tennessee River at Florence, Alabama, for a great many years. Pursuant to the judgment entered herein on May 6, 1960, as affirmed by the Court of Appeals for the Fifth Circuit (294 F.2d 491 (1961)), the Tennessee Valley Authority was authorized and directed to make certain alterations and modifications to a portion of the bridge to preserve its safety and utility and to meet the requirements of navigation.

2. The bridge is approximately 2,577 feet long, and prior to its alteration consisted of 12 deck plate girder spans, 15 double-deck fixed truss spans, 1 double-deck through truss swing span, all supported on stone masonry and concrete piers and abutments. The upper deck is used for a single-track railroad. The lower deck was arranged for highway traffic and was so used until a new highway bridge was constructed immediately downstream from the old bridge about 1940.

3. The project for altering the bridge included the realignment, widening, and deepening of the navigation channel under the bridge to increase the horizontal clearance to 350 feet (measured perpendicular to the channel) and to provide vertical clearance to elevation 476 feet above mean sea level. The alterations did not change the overall length of the bridge, and affected only' approximately 505 feet located over and adjacent to the navigation canal. The following parts were removed and replaced:

One' 62'6" double-deck truss span (erected 1906)
The 412' double-deck through truss swing span (erected 1890) with machinery and machinery house (erected 1906)
Part of one 44' deck plate girder span (erected 1894)
One steel bent which supported the south end of the 44' girder span (erected 1894)
Tract, timber deck, special rail joints on spans removed, wire lines, a timber building, and other miscellaneous items One sandstone masonry pier (Pier A, erected 1840) which supported the south end of the 62'6" truss span
One sandstone masonry pier (Pier B, erected 1890) which supported the north end of the 62'6" truss span and the south end of the swing span
One circular sandstone masonry pivot pier which supported the center of the 412' swing span (erected 1890)
Part of the sandstone masonry abutment (erected 1840) and its concrete encasement (added in 1937) which supported the north end of the 412' swing span and the south end of the 44' girder span

4. The wrought-iron and steel framework of the super-structure which was removed showed evidence of age in the form of rust, corrosion, and pitting. A crack had developed in a hip joint on the downstream truss of the swing span which was caused either by excessive and prolonged stress or metal fatigue from repeated operations of opening and closing the bridge to river traffic. The machinery and electrical controls were also old, worn, deteriorated and obsolete. Much of the substructure was also in bad condition. Pier A was splitting vertically, was held together with timbers and steel rods, and had only a tapered shaft with no spread footings to distribute the load. The foundation of this pier was unstable. It was fitting on sand and gravel and the underlying rock was honeycombed with numerous seams and cavities. Pier B also consisted of a tapered shaft with no spread footings, and it was underlaid with seams, cavities, and mud for a depth of 15 feet. The north abutment, constructed of sandstone masonry with concrete encasement, had many loose joints and was sitting on an unstable foundation of sand, gravel, and mud for a depth of about 11 feet [124]*124above bedrock. Operations over the bridge were restricted by load and speed limitations imposed by Southern.

5. New parts installed to replace the parts removed are as follows:

Four reinforced concrete piers Two 43'3" steel tower spans with new timber decks

One 406' through truss vertical lift span with new timber deck and special rail joints, all complete with operating and signal equipment The designed carrying capacity of the bridge was not increased.

6. TVA was given responsibility for doing all things necessary to complete the bridge alterations in accordance with the plans and specifications on file herein, and in carrying out that responsibility TVA contracted part of the work and performed part of the work with its own forces. The alteration work was begun on May 2, 1961. The bridge was closed to traffic on September 8, 1961, and reopened to traffic on September 20, 1962.

7. The TVA Bridge Act provides in pertinent part that in the event of such alterations the bridge owner (Southern) “shall be charged with a sum which shall equal the net value to the owner of any direct and special benefits accruing to the owner from any improvement or addition or betterment of the altered, reconstructed, relocated, or replaced bridge, trestle, or structure” (16 U.S.C. § 831c-l (1964)). The Truman-Hobbs Act provides :

The bridge owner shall bear such part of the cost as is attributable to the direct and, special benefits which will accrue to the bridge owner as a result of the alteration, including the expect-able savings in repair or maintenance costs; and that part of the cost attributable to the requirements of traffic by railroad or highway, or both, including any expenditure for increased carrying capacity of the bridge, and including such proportion of the actual capital cost of the old bridge or of such part of the old bridge as may be altered or changed or rebuilt, as the used service life of the whole or a part, as the case may be, bears to the total estimated service life of the whole or such part: Provided, That in the event the alteration or relocation of any bridge may be desirable for the reason that the bridge unreasonably obstructs navigation, but also for some other reason, the Secretary may require equitable contribution from any interested person, firm, association, corporation, municipality, county, or State desiring such alteration or relocation for such other reason, as a condition precedent to the making of an order for such alteration or relocation. The United States shall bear the balance of the cost, including that part attributable to the necessities of navigation [33 U.S.C. § 516 (1964)].

8. Regulation No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federal Crop Ins. Corp. v. Merrill
332 U.S. 380 (Supreme Court, 1947)
Roberts v. Federal Crop Insurance Corporation
158 F. Supp. 688 (E.D. Washington, 1958)
United States v. Hedburg
217 F. Supp. 711 (D. South Dakota, 1963)
Southern Railway Co. v. Tennessee Valley Authority
223 F. Supp. 1 (E.D. Tennessee, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
257 F. Supp. 121, 1966 U.S. Dist. LEXIS 6779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-valley-authority-v-southern-railway-co-alnd-1966.