Tennessee Industrial MacHinery Co. v. Accuride Corp.

139 S.W.3d 290, 2004 Tenn. App. LEXIS 2, 2004 WL 34507
CourtCourt of Appeals of Tennessee
DecidedJanuary 6, 2004
DocketM2002-01844-COA-R3-CV
StatusPublished
Cited by2 cases

This text of 139 S.W.3d 290 (Tennessee Industrial MacHinery Co. v. Accuride Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Industrial MacHinery Co. v. Accuride Corp., 139 S.W.3d 290, 2004 Tenn. App. LEXIS 2, 2004 WL 34507 (Tenn. Ct. App. 2004).

Opinion

OPINION

ALAN E. HIGHERS, J.,

delivered the opinion of the court,

in which W. FRANK CRAWFORD, P.J., W.S., and HOLLY M. KIRBY, J., joined.

This appeal involves the lower court’s award of a garnishment judgment against Accuride Corporation, as well as its subsequent denial of Accuride’s Tenn. R. Civ. P. 59.04 motion to alter or amend the judgment. For the following reasons, we reverse the judgment of the lower court and remand for further proceedings.

Facts and Procedural History

Accuride Corporation (“Accuride”) is a wheel manufacturer who operated a manufacturing plant in Columbia, Tennessee from October 1997 through May 2002. In October 1997, Accuride received a proposal from Industrial Finishing Systems, Inc. (“IFS”), in which IFS offered to design, procure, and install a wheel paint line system for Accuride’s plant. On November 1, 1997, Accuride accepted IFS’s proposal and agreed to pay a total price of $1,395,000.00 for the wheel paint line system. This total price was separated into incremental payments as follows:

Thirty percent (30%) upon issuance of the purchase order;
Thirty percent (30%) upon approval of drawing;
Twenty percent (20%) upon approval of construction, authorization and shipment;
Ten percent (10%) upon installation and operation of system; and
Ten percent (10%) thirty days after system operates to Accuride’s satisfaction.

*292 After finalizing this contract, IFS then entered into an agreement with Tennessee Industrial Machinery, Inc. (“TIMCO”), in which IFS agreed to pay TIMCO five percent of the contract price with Accuride in exchange for TIMCO’s aid in locating and purchasing an industrial paint system.

The wheel paint line system was installed over the following months according to schedule. Upon its completion, however, Accuride found that the system did not perform in a satisfactory manner. Accuride informed IFS of the performance problems by letter dated October 27, 1998, and then tried to ameliorate the problem by hiring other contractors and suppliers to repair the system, at a cost of $170,000.00. As a result of these developments, Accuride withheld some of the payment that would otherwise have been due on its contract with IFS. During this same period, TIMCO also experienced contractual problems with IFS. Specifically, IFS failed to pay TIMCO the five percent commission provided for in their contract. On June 8, 1998, TIMCO filed a lawsuit for breach of contract against IFS in the Chancery Court of Maury County. TIM-CO also named Accuride as a garnishment defendant in that action, alleging that Ac-curide owed money to IFS for the paint line system and that this debt to IFS should be garnished to satisfy IFS’s debt to TIMCO.

On August 21, 1998, the trial court entered an Interim Order/Restraining Order against Accuride that restrained any final payment to IFS on the paint line system contract. A Temporary Injunction, ordering substantially the same restraint, was then entered on October 30, 1998. On November 16, 1999, the lower court entered judgment, on the breach of contract claim, in favor of TIMCO against IFS for $107,816.23. The judgment further ordered Accuride to pay to the Clerk & Master all payments, originally meant for IFS, that were retained by Accuride pursuant to the restraining order. Accuride did not make the payment, and, on January 10, 2000, TIMCO served a garnishment on Accuride that sought “any and all property of Defendant [IFS] in Garnishee’s possession, including, but not limited to, any accounts payable and funds due Defendant.” Accuride filed an Answer to the Garnishment on February 2, 2000, alleging that it was not indebted to IFS. Accuride acknowledged that it held retain-age from IFS in the amount of roughly $140,000, but argued that this amount was to satisfy “unliquidated claims” against IFS in excess of the retainage amount. On April 28, 2000, TIMCO filed a motion entitled “Motion for Order to Show Cause and for Judgment Against Garnishee Defendant.” TIMCO’s motion was accompanied by two documents. The first was a letter dated November 9, 1998, from Accuride to IFS, in which Accuride indicated its intention to retain the final ten percent payment of $139,500.00 to offset damages occasioned by the faulty paint line system. Specifically, this letter stated that:

The above problems [with the paint line systems] have cost Accuride tens of thousands of dollars for its personnel and contractors to make repairs, as well as lost production due to conveyor downtime. The lost production has threatened us with loss of business, which we can no longer afford. We have no more confidence that IFS is willing or able to correct these problems. Our October 27 letter was our final attempt to allow IFS to correct the situation. As a result, we must now hire other contractors and suppliers at a cost of over $170,000 to correct these problems. Unfortunately, we must retain the final 10% payment of $139,500 to partially pay for these corrections.

*293 The second document, from Accuride’s financial department, was a February 3, 2000 payment history indicating that Accuride paid IFS a total of only $825,300.00 on the paint line system contract.

The lower court conducted a hearing on TIMCO’s motion on May 23, 2000. TIM-CO alleged that the February 3, 2000 payment history made clear that Accuride held retainage in the amount of roughly $570,000. 1 TIMCO argued that this re-tainage amount was more than adequate to cover the garnishment amount of $107,816.23, as well as any unliquidated claims Accuride might have. Upon completion of the hearing, the trial court found that Accuride was retaining only “One Hundred Thirty-nine Thousand Five Hundred ($139,500) Dollars, in funds which belong to Defendant, IFS.” The lower court then acknowledged that “Accuride alleges that they have unliquidated claims against IFS over the improper installation of certain machinery which is the subject of this lawsuit.” The trial court found, however, that “allegations of unliquidated claims are not sufficient to justify withholding these funds and not honoring the garnishment.” Consequently, judgment was entered in favor of TIMCO against the garnishee Accuride in the amount of $107,816.23.

On February 9, 2001, Accuride filed a motion for new trial or to alter or amend the judgment. The garnishee argued that the trial court’s judgment was contrary to both the evidence presented at the hearing, as well as the relevant law in Tennessee. The lower court conducted a hearing and subsequently denied Accuride’s motion in an order dated June 27, 2002. The trial court found that Accuride had presented no new evidence unknown to it at the time of the prior hearing, nor had Accuride shown any other ground that merited relief pursuant to. Tenn. R. Civ. P. 59. The trial court also noted that Accuride had failed to demonstrate any mistake, inadvertence, or other basis for relief under Tenn. R. Civ. P. 60. Finally, on July 25, 2002, Accuride filed the instant appeal challenging the judgment of the lower court.

Issue Presented

Accuride raises ■ one issue for our consideration:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
139 S.W.3d 290, 2004 Tenn. App. LEXIS 2, 2004 WL 34507, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-industrial-machinery-co-v-accuride-corp-tennctapp-2004.