Tennessee Gas Pipeline Co. v. F.E.R.C.

CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 24, 1994
Docket93-04089
StatusPublished

This text of Tennessee Gas Pipeline Co. v. F.E.R.C. (Tennessee Gas Pipeline Co. v. F.E.R.C.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Co. v. F.E.R.C., (5th Cir. 1994).

Opinion

United States Court of Appeals,

Fifth Circuit.

No. 93-4089.

TENNESSEE GAS PIPELINE CO., Petitioner,

v.

FEDERAL ENERGY REGULATORY COMMISSION, Respondent.

March 25, 1994.

Petition for Review of an Order of the Federal Energy Regulatory Commission.

Before JOHNSON, HIGGINBOTHAM, and EMILIO M. GARZA, Circuit Judges.

JOHNSON, Circuit Judge:

On April 8, 1991, Tennessee Gas Pipeline Company ("Tennessee")

and Flagg Energy Development Corporation ("Flagg") entered into a

firm natural gas transportation contract. Tennessee agreed to

transport 4,140 dekatherms of natural gas each day from various

points in and offshore Louisiana to Connecticut on Flagg's behalf.

Tennessee also agreed to construct and operate the facilities

necessary to transport the natural gas. Flagg agreed to pay

Tennessee for its services.

Prior to entering into this contract, the Federal Energy

Regulatory Commission ("FERC" or "the Commission") authorized

Tennessee to charge Flagg certain rates for the transportation

services. The Commission also ruled that Tennessee could later

seek changes to those rates, as allowed by section four of the

Natural Gas Act ("NGA"). Tennessee sought to change the rates on

February 28, 1992. Flagg intervened and charged, among other

things, that its gas transportation contract prohibited the type of

1 rate changes sought by Tennessee. The Commission agreed.

Tennessee appeals. We reverse.

I. Facts and Procedural History

Tennessee entered precedent agreements with seven different

companies in the winter of 1988-89. The companies proposed to pay

Tennessee to transport natural gas to various points in the

Northeast. Flagg entered such a precedent agreement with Tennessee

on January 9, 1989. It desired for Tennessee to transport natural

gas from various points in and offshore Louisiana to New Britain,

Connecticut, and Bloomfield, Connecticut. Tennessee agreed to seek

authorization from FERC to build the facilities necessary to

transport that natural gas.

Consistent with the precedent agreements with the seven

different companies—including its agreement with Flagg—Tennessee

sought FERC approval to construct and operate new facilities which

would expand the capacity of its existing pipeline system. The new

facilities were to be located in five separate zones, which

Tennessee designated Segments U, 1, 2, 3, and 4. In its

application to FERC, Tennessee asserted that it would transport

natural gas to Flagg through Segments U, 2, and 3 and would charge

Flagg for the cost of operating those three facilities.1 Rate

1 There are two methods of charging for gas transportation: The "incremental cost allocation" method and the "rolled in" method. Under the incremental cost allocation method, the new customers pay for all of the costs of the new facilities. This method spares existing customers from having to pay for the expansion of the transportation system, even though they may use the expansion facilities. The rolled in method of charging for gas transportation requires each shipper—both old and new—to pay its share of the transportation costs based upon its

2 Schedule NET-EU set forth the rates which Tennessee proposed to

charge. However, Tennessee requested permission to change the

rates if all of the proposed facilities were not approved by

October 1, 1989.

FERC approved the construction of three of the five Segments

by May of 1990—Segments 1, 2, and 3. See Tennessee Gas Pipeline

Co., 51 FERC ¶ 61,113, 61,274, 61,275-276 and n. 22 (1990).

Because FERC had not yet given Tennessee permission to construct

the proposed facilities for Segments U or 4, it disapproved

Tennessee's request to charge Flagg for any use of Segment U in a

May 2, 1990, order ("May Order"). Id. However, the Commission

decided that Tennessee could seek to amend its NET-EU rates to

"roll in"2 the costs associated with Segments U and 4 after those

projects were approved and placed in service. The Commission

asserted that Tennessee could seek such a rate change at a later

date through a section 4 proceeding. Id. at ¶ 61,274. FERC

calculated a rate for Segment 4 in its September 13, 1990, order.

However, it again refused to compute a rate for Segment U because

the proposed facilities had still not been approved. Tennessee Gas

Pipeline Co., 52 FERC ¶ 61,257, 61,930 (1990).

Based upon, and specifically referring to, the May Order,

Tennessee and Flagg entered a Firm Natural Gas Transportation

Agreement ("contract") on April 8, 1991. Tennessee agreed to

proportionate use of the facility in question. Tennessee proposed to charge Flagg under the incremental cost allocation method. 2 See supra note 1.

3 construct the facilities needed to receive and deliver gas to

Flagg. The specific rate formula for transporting the gas was set

out in section 8.2 of the contract. However, section 8.4 of the

contract provided that "pursuant to this Article VIII," Tennessee

has the unilateral right "to file and make effective changes in the

rates, charges, and conditions applicable to service."

Consistent with its construction of section 8.4 of the

contract, Tennessee filed a limited rate case under section 4 of

the NGA to revise the rates in its NET-EU schedule. Among other

things, Tennessee sought to charge Flagg and another company,

Capitol District Energy Center Cogeneration Associates ("Capitol

District"), for their use of Segment U.3 Apparently complying with

the Commission's May Order, Tennessee proposed to roll the Segment

U charge into these companies' gas transportation charges. See 51

FERC at ¶ 61,274 (deciding that "Tennessee may seek to amend its

NET-EU rates to reflect the rolling in of all costs associated with

various Northeast projects by initiating a section 4 proceeding

after all the projects have been approved and placed in service"

(emphasis added)).

Both Flagg and Capitol District filed motions to intervene.4

3 Flagg and Capitol District are the only NET-EU customers which use Segment U. Tennessee uses that Segment to transport natural gas from the Gulf Coast approximately 1400 miles north to various points in the Northeast on Flagg's and Capitol District's behalf. Unlike the gas transported for Flagg and Capitol District, the natural gas transported for the other NET-EU customers is both received and delivered in the Northeast. 4 Tennessee and Capitol District have settled their disputes in this matter.

4 Flagg proffered numerous objections to Tennessee's proposals.

Important for our purposes, Flagg contended that its contract with

Tennessee prohibited Tennessee from charging Flagg for its use of

Segment U. According to Flagg, Tennessee could only charge for the

use of Segments 2 and 3. Flagg requested FERC to review the matter

in an expedited paper hearing, and FERC granted the request,

limiting its review to deciding whether the Tennessee-Flagg

contract precluded Tennessee from charging Flagg for its Segment U

use. Tennessee Gas Pipeline Co., 58 FERC ¶ 61,343 (1992). Finding

the contract clear and unambiguous and basing its decision solely

on the plain language of the contract, the Commission concluded

that the contract did not allow Tennessee to charge Flagg for

Segment U.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Railroad Co. v. Androscoggin Mills
89 U.S. 594 (Supreme Court, 1874)
Eagle Life Insurance Co. v. G.I.C. Insurance Co.
697 S.W.2d 648 (Court of Appeals of Texas, 1985)
FORT WORTH LLOYDS INSURANCE COMPANY v. Willham
406 S.W.2d 76 (Court of Appeals of Texas, 1966)
Woods v. Sims
273 S.W.2d 617 (Texas Supreme Court, 1954)
TM Productions, Inc. v. Nichols
542 S.W.2d 704 (Court of Appeals of Texas, 1976)
Green Avenue Apartments, Inc. v. Chambers
239 S.W.2d 675 (Court of Appeals of Texas, 1951)
Universal C. I. T. Credit Corp. v. Daniel
243 S.W.2d 154 (Texas Supreme Court, 1951)
De Gonzalez v. Mission American Insurance Co.
795 S.W.2d 734 (Texas Supreme Court, 1990)
Duracon, Inc. v. Price
817 S.W.2d 147 (Court of Appeals of Texas, 1991)
Johnson v. Dick
281 S.W.2d 171 (Court of Appeals of Texas, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
Tennessee Gas Pipeline Co. v. F.E.R.C., Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-co-v-ferc-ca5-1994.