Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission

926 F.2d 1206, 288 U.S. App. D.C. 333
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 5, 1991
DocketNo. 89-1785
StatusPublished
Cited by1 cases

This text of 926 F.2d 1206 (Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission, 926 F.2d 1206, 288 U.S. App. D.C. 333 (D.C. Cir. 1991).

Opinions

Opinion for the Court filed by Circuit Judge STEPHEN F. WILLIAMS.

Concurring opinion filed by Circuit Judge CLARENCE THOMAS.

STEPHEN F. WILLIAMS, Circuit Judge:

In its Opinion No. 240, the Federal Energy Regulatory Commission picked the figure 15.1% as the return on equity for Tennessee Gas Pipeline Company for the period June 1, 1982 through January 31, 1983. Tennessee Gas Pipeline Co., 32 FER.C 11 61,086 (1985). Because of a serious methodological error — FERC had derived one of the key ingredients in its calculation from a logically irrelevant prior period — we reversed and remanded, saying: “[s]uch result-oriented manipulation of an objective ratemaking calculation is patently arbitrary and capricious decisionmaking.” Public Service Comm’n of New York v. FERC, 813 F.2d 448, 465 (D.C.Cir.1987). On remand, the Commission again picked [335]*33515.1%. Tennessee argues not only that the decision on remand is arbitrary and capricious, but that it is so egregious as to require us to set the rate of return ourselves. We agree that the Commission erred fatally and that we must reverse; as ratemaking is for the Commission and not for us, however, we must again remand. ******

In the early 1980s Tennessee filed a number of general rate increases under § 4 of the Natural Gas Act, 15 U.S.C. § 717c (1988), which the Commission consolidated. A major issue, and the one that survives through to this case, was choosing the appropriate rate of return on equity, an inevitable component of cost-of-service rate-making. Recognizing that utility investors must be allowed an opportunity to earn returns sufficient to “attract capital,” Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 605, 64 S.Ct. 281, 289, 88 L.Ed. 333 (1944), and “to compensate [the] investors for the risks assumed,” id., the Commission endeavors to set a utility’s rate of return on equity at its cost of equity capital. “The cost of capital is the minimum rate of return necessary to attract capital to an investment.” A. Lawrence Kolbe et al., The Cost of Capital: Estimating the Rate of Return for Public Utilities 13 (1984).

In Opinion No. 190, Tennessee Gas Pipeline Co., 25 FERC ¶ 61,020 (1983), the Commission addressed the two periods immediately preceding the present one and set the cost of equity capital (and hence the return on equity) at 15.95%. It reached this number by taking the midpoint of a “zone of reasonableness.” Id. at 61,097. The Commission evidently found the lower bound of this zone in its staff’s recommendation of 15%,1 and the upper bound in a discounted cash flow (“DCF”)2 analysis of Tennessee’s parent company, Tenneco, Inc. Id. at 61,093.

Opinion No. 190 did not reach the period at issue here, but an Administrative Law Judge sought to apply its methodology to the period. Tennessee Gas Pipeline Co., 25 FERC 1163,052 (1983). She believed that the 15% lower bound had been the result of risk premium analysis, which typically takes the risk-free rate of return on U.S. government bonds and adds an estimated premium for the greater risk of the particular stock. Accordingly, she used a kind of “reverse engineering” to arrive at a lower bound of 13.2%.3 She set the upper bound at 16.93%, the unrevised DCF figure from Opinion No. 190. Id. at 65,170. Finally, she chose the midpoint of this zone of reasonableness, 15.1%. Id.

In Opinion No. 240, Tennessee Gas Pipeline Co., 32 FERC 1161,086 (1985), the Commission expressly adopted the AU’s analysis and conclusion, noting “[t]he close proximity of the issuance of Opinion No. 190 to [the AU’s] decision.” Id. at 61,225. On Tennessee’s request for rehearing, the [336]*336Commission rejected Tennessee’s argument that it was improper to use DCF figures from prior periods. Tennessee Gas Pipeline Co., 33 FERC 1161,005 (1985). We found the use of obsolete data arbitrary and capricious, and reversed and remanded. Public Service Comm’n of New York v. FERC, 813 F.2d at 462-65.

On remand, the Commission again used the ALJ’s reverse-engineered risk premium figure of 13.2% as its lower bound and used an updated DCF figure of 18.79% as its upper bound. Tennessee Gas Pipeline Co., 46 FERC 1161,089 at 61,383 (1989) (“Order on Remand”). While recognizing that the midpoint of this zone of reasonableness was 15.99%, id., it instead chose its old favorite, 15.1%, id. at 61,384. To justify choosing well below the midpoint, the Commission noted that the price of Tenneco’s stock rose in the six months following the end of the relevant period, so that its dividend yield (dividend divided by price) fell. Id. at 61,383. Use of this out-of-period data would, the Commission noted, result in a DCF or upper limit of only 16.84%. Id. (Explicit use of that figure as the upper bound would have yielded a midpoint of 15.02%,4 a rate quite similar to what the Commission adopted.)

On Tennessee’s request for rehearing, the Commission acknowledged that its Order on Remand failed to articulate its rationale, and explained that its reference to the out-of-period data was “made only to show the existence of a lag in the decline in dividend yields following the decline in interest rates.” Tennessee Gas Pipeline Co., 49 FERC 1161,392 at 62,420 (1989) (“Order Denying Rehearing”). On the basis of this supposed lag, the Commission explained that it made a “pragmatic adjustment.” Id. at 62,419. Thus the supposed lag — the proposition that investors are not able to account fully for the effects of a decline in interest rates on their investment alternatives until some six months or more after those rates are published — is the sole basis for the Commission’s use of a rate of return below the midpoint.

* * He * * *

The Commission’s approach to estimating the cost of equity capital appears to be a two-step process, in which it first frames a zone of reasonableness with the estimation tools of its choice. Then, in the absence of evidence that leads the Commission to prefer one estimate over the other, it sets the rate of return at the average of those boundary figures. If “other factors” warrant a preference one way or the other, the Commission makes a suitable “pragmatic adjustment”.

We have no quarrel with this general methodology. Even if we did, we have no authority to insist that the Commission use “any single formula or combination of formulae.” Hope, 320 U.S. at 602, 64 S.Ct. at 287. But the notion of lawfulness requires insistence that the chosen framework not collapse in practice into a standardless exercise of Commission discretion resting on no more than an assertion of “expertise”. See, e.g., Greater Boston Television Corporation v. FCC, 444 F.2d 841, 850-52 (D.C.Cir.1970). We therefore turn to an evaluation of the “pragmatism” behind the adjustment.

The trend of Tenneco’s dividend yield diverged from the trend of interest rates during the disputed period. One held steady, the other fell. The Commission introduced its “lag” theory as the explanation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
926 F.2d 1206, 288 U.S. App. D.C. 333, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-co-v-federal-energy-regulatory-commission-cadc-1991.