Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission

17 F.3d 98
CourtCourt of Appeals for the Fifth Circuit
DecidedMay 31, 1994
Docket93-4089
StatusPublished
Cited by21 cases

This text of 17 F.3d 98 (Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tennessee Gas Pipeline Co. v. Federal Energy Regulatory Commission, 17 F.3d 98 (5th Cir. 1994).

Opinion

JOHNSON, Circuit Judge:

On April 8, 1991, Tennessee Gas Pipeline Company (“Tennessee”) and Flagg Energy Development Corporation (“Flagg”) entered into a firm natural gas transportation contract. Tennessee agreed to transport 4,140 dekatherms of natural gas each day from various points in and offshore Louisiana to Connecticut on Flagg’s behalf. Tennessee also agreed to construct and operate the facilities necessary to transport the natural gas. Flagg agreed to pay Tennessee for its services.

Prior to entering into this contract, the Federal Energy Regulatory Commission (“FERC” or “the Commission”) authorized Tennessee to charge Flagg certain rates for the transportation services. The Commission also,ruled that Tennessee could later seek changes to those rates, as allowed by section four of the Natural Gas Act (“NGA”). Tennessee sought to change the rates on February 28, 1992. Flagg intervened and charged, among other things, that its gas transportation contract prohibited the type of rate changes sought by Tennessee. The Commission agreed. Tennessee appeals. We reverse.

*100 I. Facts and Procedural History

Tennessee entered precedent agreements with seven different companies in the winter of 1988-89. The companies proposed to pay Tennessee to transport natural gas to various points in the Northeast. Flagg entered such a precedent agreement with Tennessee on January 9, 1989. It desired for Tennessee to transport natural gas from various points in and offshore Louisiana to New Britain, Connecticut, and Bloomfield, Connecticut. Tennessee agreed to seek authorization from FERC to build the facilities necessary to transport that natural gas.

Consistent with the precedent agreements with the seven different companies — including its agreement with Flagg — Tennessee sought FERC approval to construct and operate new facilities which would expand the capacity of its existing pipeline system. The new facilities were to be located in five separate zones, which Tennessee designated Segments U, 1, 2, 3, and 4. In its application to FERC, Tennessee asserted that it would transport natural gas to Flagg through Segments U, 2, and 3 and would charge Flagg for the cost of operating those three facilities. 1 Rate Schedule NET-EU set forth the rates which Tennessee proposed to charge. However, Tennessee requested permission to change the rates if all of the proposed facilities were not approved by October 1, 1989.

FERC approved the construction of three of the five Segments by May of 1990 — Segments 1, 2, and 3. See Tennessee Gas Pipeline Co., 51 FERC ¶ 61,113, 61,274, 61,275-276 and n. 22, 1990 WL 488828 (1990). Because FERC had not yet given Tennessee permission to construct the proposed facilities for Segments U or 4, it disapproved Tennessee’s request to charge Flagg for any use of Segment U in a May 2, 1990, order (“May Order”). Id. However, the Commission decided that Tennessee could seek to amend its NET-EU rates to “roll in” 2 the costs associated with Segments U and 4 after those projects were approved and placed in service. The Commission asserted that Tennessee could seek such a rate change at a later date through a section 4 proceeding. Id. at ¶ 61,274. FERC calculated a rate for Segment 4 in its September 13, 1990, order. However, it again refused to compute a rate for Segment U because the proposed facilities had still not been approved. Tennessee Gas Pipeline Co., 52 FERC ¶ 61,257, 61,930 (1990).

Based upon, and specifically referring to, the May Order, Tennessee and Flagg entered a Firm Natural Gas Transportation Agreement (“contract”) on April 8, 1991. Tennessee agreed to construct the facilities needed to receive and deliver gas to Flagg. The specific rate formula for transporting the gas was set out in section 8.2 of the contract. However, section 8.4 of the contract provided that “pursuant to this Article VIII,” Tennessee has the unilateral right “to file and make effective changes in the rates, charges, and conditions applicable to service.”

Consistent with its construction of section 8.4 of the contract, Tennessee filed a limited rate case under section 4 of the NGA to revise the rates in its NET-EU schedule. Among other things, Tennessee sought to charge Flagg and another company, Capitol District Energy Center Cogeneration Associates (“Capitol District”), for their use of Segment U. 3 Apparently complying with the Commission’s May Order, Tennessee pro *101 posed to roll the Segment U charge into these companies’ gas transportation charges. See 51 FERC at ¶ 61,274 (deciding that “Tennessee may seek to amend its NET-EU rates to reflect the rolling in of all costs associated with various Northeast projects by initiating a section 4 proceeding after all the projects have been approved and placed in service” (emphasis added)).

Both Flagg and Capitol District filed motions to intervene. 4 Flagg proffered numerous objections to Tennessee’s proposals. Important for our purposes, Flagg contended that its contract with Tennessee prohibited Tennessee from charging Flagg for its use of Segment U. According to Flagg, Tennessee could only charge for the use of Segments 2 and 8. Flagg requested FERC to review the matter in an expedited paper hearing, and FERC granted the request, limiting its review to deciding whether the Tennessee-Flagg contract precluded Tennessee from charging Flagg for its Segment U use. Tennessee Gas Pipeline Co., 58 FERC ¶ 61,343 (1992). Finding the contract clear and unambiguous and basing its decision solely on the plain language of the contract, the Commission concluded that the contract did not allow Tennessee to charge Flagg for Segment U. Tennessee Gas Pipeline Co., 60 FERC ¶ 61,261 (1992). The Commission denied Tennessee’s motion for rehearing on January 21, 1993. Tennessee appeals.

II. Discussion

A. Background

As late as the mid-1940s, just after World War II, contracts between natural gas companies (e.g., suppliers and transporters) and natural gas purchasers (e.g., public service commodity companies) began to take one of two shapes with respect to rates., The contracts either set forth a specific, unchangeable rate for natural gas supply or they set no specific rate whatever. Compare United Gas Pipe Line Co. v. Mobile Gas Service Corp., 350 U.S. 332, 76 S.Ct. 373, 100 L.Ed. 373 (1956) with United Gas Pipe Line Co. v. Memphis Light, Gas and Water Division, 358 U.S. 103, 79 S.Ct. 194, 3 L.Ed.2d 153 (1958); see also Federal Power Commission v. Sierra Pacific Power Co., 350 U.S. 348, 76 S.Ct. 368, 100 L.Ed. 388 (1956).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ANR Pipeline v. FERC
Fifth Circuit, 2025
Vaughn v. GULF COPPER
54 F. Supp. 2d 688 (E.D. Texas, 1999)
C.C. Port, Ltd. v. Davis-Penn Mortg. Co.
61 F.3d 288 (Fifth Circuit, 1995)
C.C. Port, Ltd. v. Davis-Penn Mortgage Co.
61 F.3d 288 (Fifth Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
17 F.3d 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tennessee-gas-pipeline-co-v-federal-energy-regulatory-commission-ca5-1994.