Tenneco Oil Co. v. Gulsby Engineering, Inc.

846 S.W.2d 599, 1993 Tex. App. LEXIS 276, 1993 WL 14661
CourtCourt of Appeals of Texas
DecidedJanuary 28, 1993
DocketC14-92-00252-CV
StatusPublished
Cited by28 cases

This text of 846 S.W.2d 599 (Tenneco Oil Co. v. Gulsby Engineering, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tenneco Oil Co. v. Gulsby Engineering, Inc., 846 S.W.2d 599, 1993 Tex. App. LEXIS 276, 1993 WL 14661 (Tex. Ct. App. 1993).

Opinion

OPINION

ROBERTSON, Justice.

The trial court granted summary judgment on all liability issues in favor of Ten-neco Oil Company and Tenneco Natural Gas Liquids (“Tenneco”) and submitted for jury determination Tenneco’s claim for attorney’s fees. In response to an issue asking how much money, if any, would compensate Tenneco for reasonable and necessary attorney’s fees, the jury found $ 0.00. Both parties have appealed the judgment. *602 Gulsby Engineering, Inc., Jerry G. Gulsby and Clara J. Gulsby, Individually, and d/b/a Gulsby Enterprises (“Gulsby”) appeal from the grant of summary judgment on all liability issues. Tenneco appeals from the judgment denying recovery of attorney’s fees. Because we find the trial court erred in holding Mr. and Mrs. Gulsby individually liable, we modify the judgment to reflect that Tenneco recover damages solely from Gulsby Engineering, Inc. Except as so modified, we affirm the remainder of the judgment.

In 1981, Tenneco sought bids for the construction of a natural gas processing plant in Sabine Pass. Ortloff Corp. v. Gulsby Eng’g, Inc., 706 F.Supp. 1295, 1300 (S.D.Tex.1988), aff'd, 884 F.2d 1399 (5th Cir.1989) (per curiam) (published by table). Among those submitting bids were Gulsby and the Ortloff Corporation. 706 F.Supp. at 1300. Ortloffs design employed a recently patented gas separation process that utilized a split vapor method for recovering natural gas. Id. at 1297. Under Gulsby’s proposed design, there would be four residue gas compressors and product treating equipment to remove carbon dioxide. Id. at 1300. Recovery under this system was calculated at 82.9 percent. Id. Under Ort-loff’s patented system, only three residue gas compressors were needed and there was no need for product treating equipment. Id. Ortloff guaranteed ethane recovery of 87.5 percent and calculated 91.9 percent. Id.

After reviewing the bids, Tenneco asked Gulsby to revise its design. Id. Gulsby subsequently submitted a bid embodying Ortloff’s patented system. Id. at 1301. Gulsby was awarded the contract and constructed the plant. See id. at 1303. The construction contract contained two indemnity provisions and a provision allowing Tenneco to withhold payment if there was evidence of or the filing of causes of action for which Tenneco could become liable. Upon completion of the plant, Tenneco withheld payment until Gulsby provided a Letter of Credit in the amount of $325,-000.00 as security for the performance of the indemnity obligations.

Claiming patent infringement, unfair competition, and misappropriation of confidential information, Ortloff filed suit in federal court against Tenneco and Gulsby. Id. at 1296. Upon the filing of that suit, Tenneco sought and received Gulsby’s agreement to substitute collateral for the Letter of Credit securing the indemnity obligations under the contract. The collateral was a corrected deed of trust to four tracts of land owned by Gulsby. Mr. and Mrs. Gulsby signed this deed individually and d/b/a Gulsby Enterprises. Mr. and Mrs. Gulsby also signed this deed as guarantors.

In the Ortloff suit, the district court found that Tenneco had passed to Gulsby details of Ortloff’s proposed design and that Tenneco was liable for improper use of Ortloff’s confidential information. Id. at 1308. The district court also found Gulsby liable for unfair competition by misappropriation of Ortloff’s bid information. Id. The district court found that both Tenneco and Gulsby had infringed Ortloff’s patent in the construction and operation of the Sabine Pass Plant. Id. Although the district court found that Tenneco willfully provided Gulsby with confidential information, the court noted that Gulsby took steps to avoid infringement of Ortloff’s patent and Tenneco sought legal advice before beginning plant operations. Id. at 1305, 1309. Thus, the district court found that the infringement was not willful. Id. at 1305. Regarding damages, the court found both Tenneco and Gulsby liable in the amount of $835,000.00, the amount of Gulsby’s profits. Id. at 1309.

On appeal, the Fifth circuit affirmed the trial court’s finding that Tenneco and Guls-by infringed Ortloff’s patent in the construction and operation of the plant, that Tenneco improperly used Ortloff’s confidential information, and that Gulsby engaged in unfair competition by misappropriation. 884 F.2d at 1399.

Following affirmance of the judgment by the Fifth Circuit, Tenneco paid the damage award to Ortloff and then filed this suit seeking indemnity from Gulsby pursuant to the indemnity provisions in the construe *603 tion contract. Tenneco filed a motion for summary judgment on all causes of action and the trial court granted this motion. Having granted the partial interlocutory summary judgment on all liability issues, the trial court submitted the issues of attorney’s fees to the jury. The two special issues submitted to the jury asked what sum of money, if any, would compensate Tenneco for reasonable and necessary attorney’s fees in their defense of the Ortloff litigation and in their prosecution of this case. The jury answered $ 0.00 to both issues.

I. THE SUMMARY JUDGMENT AS TO LIABILITY

Gulsby raises ten points of error challenging the trial court’s grant of summary judgment in favor of Tenneco. On appeal from a summary judgment, the question is whether the movant met its burden of proving that there was no genuine issue of material fact and that it was entitled to judgment as a matter of law. Nixon v. Mr. Property Mgmt. Co., 690 S.W.2d 546, 548 (Tex.1985). In determining whether there is a disputed fact issue precluding summary judgment, we must accept as true the evidence favorable to the non-movant, indulging all reasonable inferences and resolving any doubts in the non-movant’s favor. Id. at 548-49.

In point of error one, Gulsby contends the trial court erred in granting the motion because the evidence raised fact questions as to Gulsby’s liability for Tenneco’s independent intentional tort. Tenneco claimed Gulsby was required to indemnify Tenneco for its intentional tort pursuant to §§ 7.1 and 17.1 of the construction contract. Gulsby first contends that Tenneco’s act of misusing Ortloff’s confidential information constitutes an intentional tort. Because the district court found that Tenneco alone was liable for the improper use of Ortloff's confidential information, Gulsby claims that this intentional act is unprotected by the indemnity provisions of the contract.

Even if we were to hold that the district court’s conclusion regarding Tenne-co’s liability for this act established an independent, intentional tort on Tenneco s part, we would nevertheless find no error by the trial court in granting summary judgment. The single damage award is supported, not only by the findings of liability for misappropriation and improper use of confidential information, but also by the findings of liability for patent infringement. Thus, we overrule point of error one.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

David Robertson v. Oksana Robertson
Court of Appeals of Texas, 2015
Rena Abel v. Alexander Oil Company
474 S.W.3d 795 (Court of Appeals of Texas, 2014)
Crimson Exploration, Inc. v. Intermarket Management, LLC
341 S.W.3d 432 (Court of Appeals of Texas, 2010)
Taurus Demetrick Blakemore v. State
Court of Appeals of Texas, 2008
THH Properties Ltd. Partnership v. Hill
930 So. 2d 1214 (Louisiana Court of Appeal, 2006)
English v. BGP International, Inc.
174 S.W.3d 366 (Court of Appeals of Texas, 2005)
in Re: Mission Petroleum Carriers, Inc.
Court of Appeals of Texas, 2005
GeoSurveys, Inc. v. State National Bank
143 S.W.3d 220 (Court of Appeals of Texas, 2004)
Material Partnerships, Inc. v. Ventura
102 S.W.3d 252 (Court of Appeals of Texas, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
846 S.W.2d 599, 1993 Tex. App. LEXIS 276, 1993 WL 14661, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tenneco-oil-co-v-gulsby-engineering-inc-texapp-1993.