Templo Calvario Spanish Assembly of God v. Gardner Construction Corp.

198 Cal. App. 4th 509, 129 Cal. Rptr. 3d 574, 2011 Cal. App. LEXIS 1077
CourtCalifornia Court of Appeal
DecidedAugust 16, 2011
DocketNo. F060838
StatusPublished
Cited by5 cases

This text of 198 Cal. App. 4th 509 (Templo Calvario Spanish Assembly of God v. Gardner Construction Corp.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Templo Calvario Spanish Assembly of God v. Gardner Construction Corp., 198 Cal. App. 4th 509, 129 Cal. Rptr. 3d 574, 2011 Cal. App. LEXIS 1077 (Cal. Ct. App. 2011).

Opinion

Opinion

FRANSON, J.

INTRODUCTION

Appellant Templo Calvario Spanish Assembly of God (Templo) and respondent Gardner Construction Corporation (Gardner) entered into a contract in 2008 for Gardner to construct a church. The parties had a dispute, [513]*513Templo petitioned for arbitration, but before the petition was ruled upon, the parties agreed to submit the matter to arbitration under the terms of an arbitration provision in the contract. Because Gardner was unlicensed, the arbitrator ruled that Gardner must disgorge the entire $160,213 Templo had paid to Gardner. Templo petitioned the superior court to confirm the arbitration award. Gardner followed with a petition to vacate the arbitration award. Based on the 1949 California Supreme Court holding in Loving & Evans v. Blick (1949) 33 Cal.2d 603 [204 P.2d 23] (Loving & Evans), the court granted Gardner’s petition to vacate the award. The superior court ruled: “[T]he . . . contract was illegal and void because Gardner Corporation was an unlicensed contractor. . . . Since the contract is illegal and void, so is the arbitration provision in the contract. Since the arbitration provision fails, the arbitrator was without authority to render a decision.” (Some capitalization omitted.)

On this appeal, Templo contends the superior court’s order vacating the arbitration award was erroneous because under the 2005 California Supreme Court case of MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc. (2005) 36 Cal.4th 412 [30 Cal.Rptr.3d 755, 115 P.3d 41] (MW Erectors), the contract was not automatically illegal and void, and the arbitrator had the authority to render a decision. As we shall explain, we agree with appellant Templo and reverse the superior court’s order vacating the arbitration award.

FACTUAL AND PROCEDURAL BACKGROUND

A. The Arbitrator’s Award

The arbitrator’s findings included the following:

“Contract and Amendment
“1. Templo entered into a written Commercial Construction Contract (‘Contract’) with Gardner Construction Corporation . . . , which included an arbitration provision. The Contract is dated June 1, 2008. The Contract was executed by Dean Gardner, as President of Gardner Construction Corporation, with a handwritten date of July 2, 2008. Templo executed the Contract through Dr. Rogelio Ovalle, Pastor of Templo, with a handwritten date of July 2, 2008.
“2. The parties, namely Templo and Gardner Construction Corporation, also executed an Amendment, dated June 1, 2008, but bearing the handwritten date of July 2, 2008 .... The subject of the Contract and Amendment is construction of a building for Templo by Gardner Construction Corporation. . . . HO ■ • • HD
[514]*514“6. . . . The Arbitrator expressly finds that the Contract and Amendment are in fact the operative agreements and reflect that the party serving as the general contractor under the Contract and Amendment was Gardner Construction Corporation. . . .
“Payment
“7. Templo made two separate payments following execution of the Contract and Amendment. Templo issued a check to Gardner Construction dated July 20, 2008, in the sum of $43,000 .... Templo issued a second payment to Gardner Construction dated August 15, 2008 in the sum of $117,213 .... The Arbitrator finds that the total amount advanced by Templo to Gardner Construction was the sum of $160,213. [f] . . . [f]
“Licensure
“11. Dean Gardner testified that Gardner Construction Corporation is not licensed as a contractor. . . . The Arbitrator finds that while the Contract and Amendment were between Templo and Gardner Construction Corporation, Gardner Construction Corporation is not currently a licensed contractor, it was not a licensed contractor at the time the Contract and Amendment were executed, nor was it licensed at any time during the Templo project.
“12. California Business [and]. Professions Code section 7031, subdivision (a), expressly precludes a person from collecting compensation for construction work unless (1) the person was ‘a duly licensed contractor at all times during the performance of [the construction work],’ ....
“13. If a corporation without a contractor[’]s license enters into a construction contract and agrees to conduct construction work, the [Business and Professions Code] [s]ection 7031 litigation bar precludes the unlicensed coiporation from collecting compensation for construction work. ... [f] ... [f]
“15. The evidence and documents also establish that Dean Gardner expended considerable time and effort on the project for Templo. The Arbitrator finds that Mr. Gardner’s efforts prior to execution of the Contract and Amendment were directly and unequivocally related to construction work that was the subject of the Contract and Amendment and were expended in anticipation of a formal agreement, which was in fact executed (along with the Amendment) on or about July 2, 2008.
“16. The Arbitrator finds that Mr. Gardner is not entitled to recover any sums for his efforts based upon a quantum meruit theory or any other common count type of claim. (See MW Erectors, supra, 36 Cal.4th at [p.] 428.)
[515]*515“Disgorgement
“17. Templo demands in its Arbitration Brief that Gardner Construction Corporation return the sum of $146,481 to Templo.
“18. Notwithstanding the substantial compliance exceptions under Business [and] Profession^] Code section 7031, subdivisions (a) or (e), ‘a person who utilizes the services of an unlicensed contractor may bring an action in any court of competent jurisdiction in this state to recover all compensation paid to the unlicensed contractor for performance of any act or contract.’ (Bus. & Prof. Code, § 7031, subd. (b).)
“19. The Arbitrator finds that Templo is entitled to disgorgement of all sums paid pursuant to the Contract and Amendment.”

B. Superior Court Ruling

Templo petitioned the superior court for confirmation of the arbitration award. Gardner then petitioned the court to vacate the award. Gardner’s petition to vacate the award challenged the arbitrator’s award on many grounds, including that the arbitrator had exceeded his powers because the arbitrator had ruled on many issues that had not been submitted by the parties for determination. However, no allegation was made that the construction contract or the arbitration provision was illegal or void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rodgers v. HB Construction CA2/5
California Court of Appeal, 2023
Vascos Excavation Group LLC v. Gold
California Court of Appeal, 2023
Vascos Excavation Group v. Gold CA2/5
California Court of Appeal, 2022
Ahdout v. Hekmatjah
213 Cal. App. 4th 21 (California Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
198 Cal. App. 4th 509, 129 Cal. Rptr. 3d 574, 2011 Cal. App. LEXIS 1077, Counsel Stack Legal Research, https://law.counselstack.com/opinion/templo-calvario-spanish-assembly-of-god-v-gardner-construction-corp-calctapp-2011.