Tempe v. Lejas

CourtCourt of Appeals of Arizona
DecidedAugust 27, 2024
Docket1 CA-CV 23-0542
StatusUnpublished

This text of Tempe v. Lejas (Tempe v. Lejas) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tempe v. Lejas, (Ark. Ct. App. 2024).

Opinion

NOTICE: NOT FOR OFFICIAL PUBLICATION. UNDER ARIZONA RULE OF THE SUPREME COURT 111(c), THIS DECISION IS NOT PRECEDENTIAL AND MAY BE CITED ONLY AS AUTHORIZED BY RULE.

IN THE ARIZONA COURT OF APPEALS DIVISION ONE

CITY OF TEMPE, Defendant/Appellee.

v.

LEJAS CORPORATION, Defendant/Appellant.

No. 1 CA-CV 23-0542 FILED 08-27-2024

Appeal from the Superior Court in Maricopa County Nos. CV2020-003865 CV2020-006152 (Consolidated) The Honorable Dewain D. Fox, Judge

AFFIRMED IN PART; VACATED AND REMANDED IN PART

COUNSEL

May, Potenza, Baran & Gillespie, P.C., Phoenix By Justin R. DePaul, Jesse R. Callahan, Andrew S. Lishko Counsel for Defendant/Appellant

City Attorney, City of Tempe, Tempe By Sonia M. Blain, Sarah R. Anchors, Matthew J. Mansfield Counsel for Defendant/Appellee TEMPE v. LEJAS Decision of the Court

MEMORANDUM DECISION

Presiding Judge Jennifer B. Campbell delivered the decision of the Court, in which Judge Kent E. Cattani and Judge Paul J. McMurdie joined.

C A M P B E L L, Judge:

¶1 This appeal arises from general contractor Lejas Corporation’s installation of a storm drain as part of a City of Tempe project. After the City discovered the issue, the parties engaged in cooperative discussions about possible cures for months. The City then terminated the contract and refused to pay any portion of Lejas’s final payment application for the retention amount and work performed to specifications.

¶2 This action followed.1 The superior court entered summary judgment for the City on Lejas’s claims for breach of contract, violation of the governing prompt pay statute, breach of contract on a curative contract, and declaratory relief. The court also entered summary judgment for the City on its counterclaim for breach of contract. We affirm the judgment only insofar as it pertains to Lejas’s claim that the City breached a contract for curative work because no evidence showed that such a contract was formed. We otherwise vacate and remand, holding that material factual disputes preclude summary judgment.

BACKGROUND

¶3 In September 2018, the City hired Lejas as the general contractor for the construction of pickleball courts. The parties’ contract (the Contract) specified the following: Lejas was to perform all work on the project in accordance with defined specifications and was to install all material “in a good and workmanlike and substantial manner and to the satisfaction of the City or its properly authorized agents and strictly pursuant to and in conformity with the Contract.” Under Section 6.4.2 of the Contract, Lejas would be “deemed in default” if it “fail[ed] to adequately perform the services set forth in the plans and specifications of

1 Subcontractor Hurricane Fence Company and surety Philadelphia Indemnity Insurance Company were also parties to the action, but they are not part of this appeal.

2 TEMPE v. LEJAS Decision of the Court

and fail[ed] to cure such non-performance within ten (10) days after written notice from City.” In the event of a default, the City could terminate the contract and hire a different contractor.

¶4 Lejas was to submit payment requests on a standard form and the City would make payments in accordance with the prompt pay statute for public construction projects, A.R.S. § 34-221. “[F]inal payment” was contingent on Lejas “turn[ing] over the entire work in full accordance with these specifications.” Before making the final payment, the City would complete a “final inspection” to determine if the work was “completed in accordance with the Contract,” and, through the record engineer or architect, would certify all record drawings were complete. Completion was defined as “full completion of all construction associated with the Contract,” including a close-out package containing, among other things, the certified record plans. The Contract specified, “Contractor is responsible for complying with the specifications and is hereby forewarned that final approval of any work will not be given until the entire project is completed and accepted by City.”

¶5 Lejas began work on the project and received multiple progress payments, with the City withholding retention of five to ten percent from each payment. The City then discovered that Lejas, acting on a subcontractor’s advice, had installed a storm drain approximately 2.5 inches below the design specifications.

¶6 The parties began talking about how to resolve the deviation. In late March 2019, the City’s outside design firm proposed grading and a pipe extension to address the “incorrectly constructed pipe elevation.” Lejas objected to the allegation that the work was “incorrectly constructed” but stated that the subcontractor wanted to resolve the dispute by simply raising the pipe to the design elevation—even though the subcontractor believed this would be insufficient to properly evacuate stormwater. The City responded that it believed a correction to the design elevation, plus a pipe extension, was the best solution. The parties continued to discuss elevation concerns and possible solutions.

¶7 In May, the City opened the pickleball courts to the public with the storm drain issue still unresolved. On June 13, Lejas submitted a payment application (Pay Application 6), which was labeled “FINAL,” seeking $52,226.35. Most of that sum represented the retention amounts held on the previous progress payments, but $13,253 was for new work, specifically installing a windscreen.

3 TEMPE v. LEJAS Decision of the Court

¶8 On June 21, Lejas provided a proposal for correcting the storm drain elevation issue. The City responded that the price was too high given that “we are paying [Lejas] to fix [its] mistake.” Lejas explained that its subcontractor insisted on a premium for a quick turnaround.

¶9 On July 1, the City told Lejas it could not process Pay Application 6 without the close-out package. In response, Lejas submitted as-built drawings noting “Additional Drainage Solutions Forthcoming.”

¶10 On July 15, the City issued a “Non-Conformance Report” for the storm drain, directing Lejas to “correct to design elevation or contact [the City] with alternatives.” The parties then met and discussed a potential alternative. Lejas indicated that it would provide a proposal for the alternative but never did so.

¶11 On October 9, the City issued a default notice giving Lejas until October 18 to provide “an agreeable proposal to correct its non-conforming work.” The City also provided an estimate from a different contractor to correct the storm drain for $27,086.97 and indicated it would withhold that amount from the retention balance to pay that cost if necessary. The letter also stated that “Lejas has had ample time to present the City with a proposal to correct its non-conforming work and has failed to do so,” but the City was nonetheless giving Lejas “this final opportunity to submit a proposal to correct.” The City warned that it would move forward with the other contractor’s estimate if Lejas did not provide “a written proposal” by the deadline, noting that “Lejas failed to cure its non-performance within the ten-day period prescribed by section 6.4.2 of the Contract[, t]he Contract does not require that the City give Lejas any further opportunity to cure the non-conforming work beyond that ten-day period, and therefore the City reserves the right to reject any proposal submitted by Lejas[] and move forward with its alternative estimate.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Andrews v. Blake
69 P.3d 7 (Arizona Supreme Court, 2003)
Foundation Development Corp. v. Loehmann's, Inc.
788 P.2d 1189 (Arizona Supreme Court, 1990)
Mining Investment Group, LLC v. Roberts
177 P.3d 1207 (Court of Appeals of Arizona, 2008)
Hill-Shafer Partnership v. Chilson Family Trust
799 P.2d 810 (Arizona Supreme Court, 1990)
American Power Products, Inc. v. CSK Auto, Inc.
396 P.3d 600 (Arizona Supreme Court, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Tempe v. Lejas, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tempe-v-lejas-arizctapp-2024.