Temeron, Inc. v. Ferraro Energy Corp.

1993 OK CIV APP 97, 861 P.2d 319, 64 O.B.A.J. 3008, 1993 Okla. Civ. App. LEXIS 126
Court of Civil Appeals of Oklahoma·Decided May 11, 1993·No. No. 79431·Published·Cited by 1 cases

Opinion

MEMORANDUM OPINION

HANSEN, Chief Judge:

Appellant, Temerón, Inc., (Temerón), seeks review of the trial court’s order which sustained Appellee Ferraro Energy Corporation’s, (FEC), motion for summary judgment. The order similarly sustained Appellee, Northern Natural Gas Company’s, (Northern), motion to dismiss. Tem-erón brought this action against Appellees, alleging breach of contract against FEC and against Northern for its intentional interference with Temerón’s contract. The facts presented to the trial court are these.

On or about August 1, 1986, Temerón and FEC entered into a consulting service agreement wherein Temerón agreed to review FEC’s gas purchase contracts to determine whether FEC was receiving all monies to which it might be entitled under the contracts. The agreement provides in part:

1. Services to be provided:
A. Consultant [Temerón] will schedule and conduct a preliminary review of Producers [FEC] contracts to determine if it appears that a full review may disclose underpayments to Producer. There will be no charge to producer for such service. All work papers, notes, etc. created during such review shall remain the sole property of Consultant.
[322]*322B. If Producer determines that it would benefit from a full review, Consultant will schedule such examination upon notification from Producer and the execution of this Agreement.
2. Assignment of Claim(s):
A. Producer hereby grants Consultant the option to take an assignment of any and all claim(s) identified by Consultant. If Consultant elects to take assignment of a claim on its own account it will pay Producer fifty percent (50%) of any amount it receives from any settlement and/or litigation. Such amounts are due to Producer within thirty (30) days of the receipt thereof by Consultant. Consultant will have full and total authority to accept the terms of any settlement that it deems appropriate. Consultant may require Producer to enter a separate assignment to document Consultant’s ownership of the claim(s). Producer further agrees to cooperate with Consultant in executing any documents reasonably required by Consultant to commence, continue or finalize any settlement and/or litigation. Additionally, Producer will furnish any and all witnesses and documents required by Consultant without subpoena as deemed necessary by Consultant in pursuing any claim assigned pursuant to this Agreement. Consultant will assume all costs associated with such negotiations and/or litigation and hold Producer harmless therefrom. Any payment to Producer shall be reduced pro rata by all unrecovered expenses and attorney’s fees incurred in pursuing and collecting the claim.
* * * * * *
8. Term:
This Agreement shall become effective from the date set forth above, and shall continue in effect for a period of four(4) years and ,on a month-to-month basis thereafter until the parties hereto have accomplished the purpose for entering into this Agreement.

Pursuant to this agreement, Temerón examined FEC’s records and determined Northern owed FEC several million dollars under their gas purchase contract, a fact unknown to FEC until Temerón examined the records. With FEC’s approval, Temer-ón instituted legal action against Northern in FEC’s name, Cause No. 87-01248 (hereinafter “Ferraro v. Enron”), to recover monies due FEC under its gas purchase contract with Northern. FEC and Northern began settlement negotiations without involving Temerón. Temerón maintains the evidence shows Northern would not settle with FEC unless Temerón was excluded from the settlement. FEC thereafter terminated Temeron’s services under the consulting agreement. After FEC terminated Temeron’s services, Temerón attempted to intervene in Ferraro v. Enron. FEC, but not Northern, opposed Temeron’s intervention and the trial court denied the motion. FEC appealed the denial of intervention but subsequently dismissed the appeal after FEC and Northern settled the action for two million dollars. Temerón has received no compensation for its work under the consulting agreement.

FEC’s motion for summary judgement was predicated on two grounds: first, that Temerón is precluded from litigating this action because it is barred by the doctrines of res judicata and collateral estoppel by virtue of the denial of intervention in Ferraro v. Enron and second, because Temer-ón may not recover damages on quasi-contract for services it rendered in the hopes of gaining a business advantage. We will address the issues raised in the motion for summary judgment and then address the issues raised in Northern’s motion to dismiss.

Because Temerón dismissed its appeal of the denial of the motion to intervene and such denial has become final, Temerón may not now attack the propriety of that order. All that is in issue here is whether Temerón is precluded from maintaining this action against FEC based on the denial of intervention. Appellant sought intervention pursuant to 12 O.S. 1991, § 2024. It is unclear from a review of the pleadings on the motions to inter[323]*323vene whether Temerón sought permissive intervention or intervention as of right. Both FEC and Temerón agreed the trial court’s first order denying intervention was based on Temeron’s failure to present evidence that Temerón had received an assignment from FEC of FEC’s claims against Northern. In its denial of Temeron’s renewed motion to intervene, the trial court stated simply “There is no evidence of a written agreement.”

The doctrine of res judicata, or claim preclusion, operates to bar relit-igation by the parties or their privies of issues which were or could have been litigated in an action which resulted in a final judgment on the merits. Erwin v. Frazier, 786 P.2d 61, 64 (Okla.1989). A judgment on the merits is one that disposes of the real or substantial grounds of action or defense as distinguished from matters of practice, procedure or form. Points v. Oklahoma Publishing Company, 672 P.2d 1146, 1147, note 3 (Okla.1983). When collateral estoppel (issue preclusion) is invoked, the point upon which the plea of estoppel is based must be in issue in the present action and must have been in issue and decided in the former action. Boy Scouts of America, Inc., v. Thompson, 380 P.2d 705 (Okla.1963); Flick v. Crouch, 434 P.2d 256 (Okla.1967).

Orders denying intervention are final, appealable orders. Rule 1.10(a)(14)(5); Gettler v. Cities Service Company, 739 P.2d 515 (Okla.1987). All issues raised in a petitioning intervenor’s motion to intervene may be afforded preclusive effect if such were fully litigated and result in an adjudication on the merits. Castro Convertible Corporation v. Castro, 596 F.2d 123 (5th Cir.1979); Saunders v. Bankston, 31 Colo.App. 551, 506 P.2d 1253 (1972).

In Gettler v. Cities Service Company, supra, the Oklahoma Supreme Court outlined four countervailing interests when applying joinder and intervention statutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Temeron, Inc. v. Ferraro Energy Corp., 1993 OK CIV APP 97, 861 P.2d 319, 64 O.B.A.J. 3008, 1993 Okla. Civ. App. LEXIS 126 (Okla. Ct. App. 1993).

1993 OK CIV APP 97 (Temeron, Inc. v. Ferraro Energy Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Temeron, Inc. v. Ferraro Energy Corp.
861 P.2d 319 (Court of Civil Appeals of Oklahoma, 1993)