Teledyne Wisconsin Motor v. Local 283, United Automobile, Aerospace, & Agricultural Implement Workers

386 F. Supp. 1231, 88 L.R.R.M. (BNA) 2486
CourtDistrict Court, E.D. Wisconsin
DecidedJanuary 23, 1975
Docket74-C-585
StatusPublished
Cited by4 cases

This text of 386 F. Supp. 1231 (Teledyne Wisconsin Motor v. Local 283, United Automobile, Aerospace, & Agricultural Implement Workers) is published on Counsel Stack Legal Research, covering District Court, E.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teledyne Wisconsin Motor v. Local 283, United Automobile, Aerospace, & Agricultural Implement Workers, 386 F. Supp. 1231, 88 L.R.R.M. (BNA) 2486 (E.D. Wis. 1975).

Opinion

MEMORANDUM

WARREN, District Judge.

This suit is brought by an employer, Teledyne Wisconsin Motor (hereinafter “Teledyne”), in an attempt to resolve a labor dispute concerning a refusal of certain of its production employees to work overtime hours. The employees at issue are members of Local 288, International Union, United Automobile, Aerospace and Agricultural Implement Workers of America (hereinafter “the union”) ; the union is a party defendant in this action.

This Court’s jurisdiction over the subject matter of the controversy is alleged to exist by virtue of the provisions of § *1233 301 of the Labor Management Relations Act, 29 U.S.C. § 185; in view of the provisions of § 4(a) of the Norris-LaGuardia Act, 29 U.S.C. § 104(a), whether the Court has jurisdiction to provide the injunctive relief requested is one of the material questions of law that have been argued by the parties.

I. FACTUAL BACKGROUND

This lawsuit represents but one aspect of what appears to be a continuing struggle between the union and Teledyne to establish the nature of the arbitration procedures that are required under the collective bargaining agreements that have come into effect between them. The material facts giving' rise to this particular suit are relatively few in number and are not substantially disputed.

The most recent collective bargaining agreement (hereinafter ‘‘the agreement”) was executed in May of 1974 and has been in effect between the parties at all times material to this action; it includes some provisions for arbitration of disputes that arise between the parties, but it does not contain a “no-strike” clause to prohibit the union from engaging in work stoppage to press for concessions from the employer.

The plaintiff Teledyne is a manufacturer in the business of producing piston engines and employs members of the union to fill its requirements for both maintenance and production labor. For some time prior to November, 1974, Teledyne had been in the practice of regularly scheduling overtime hours for the employees represented by the union and had come to rely upon such overtime work in estimating production capacities; commitments for the sale and delivery of their product are based on an assumption that overtime help will be available from production and maintenance personnel.

The union has traditionally recognized this need for overtime assistance and maintains no general policy in opposition to either regularly scheduled or sporadie overtime work. The May, 1974 agreement states at paragraph 20.E.:

“E. ' It shall not be compulsory for any individual employee to work overtime. However, this provision may not be used by any department or group of employees to prevent the scheduling of a work week beyond forty (40) hours. Employees who are scheduled to work overtime and who chose not to work shall, whenever reasonably possible, advise their Foreman in advance of their not working.”

. The union takes a different position in regard to overtime labor by other than maintenance personnel when some of its members have been placed on layoff status by the employer. In this circumstance, other provisions of the agreement become relevant. At paragraph 46.A. the agreement states that:

“46. A. No employee shall regularly work more than forty (40) hours per week before all employees on the seniority list are re-employed. Maintenance work that cannot be performed during normal working hours, may be done on overtime hours.”

It is this clause that has engendered the dispute here at issue; its provisions have come into question because, due to a severe reduction in the number of orders for its engines, Teledyne has been in the process of reducing its production output and has found it necessary to lay off certain of its employees that are represented by the union. On November 12, 1974, six union members were laid off; on November 27, 1974, approximately 220 additional employees represented by the union were laid off.

The current dispute between Teledyne and the union centers on an interpretation of the provisions of paragraph 46.-A.: Teledyne maintains that, by its terms, this clause imposes no limitation on the employer’s right to schedule irregular and sporadic overtime work regardless of whether any union members are then on layoff status. The union on the other hand, takes the position that paragraph 46.A. requires a policy where *1234 by absolutely no overtime hours are to be worked by production personnel when any union members are on layoff status unless the employer makes a specific request in that regard and the union sees fit to authorize the added work time.

The union is currently enforcing its position by refusing to permit any overtime work to be done by those of its members who are engaged in production labor and by imposing penalties upon any of its members who do not refuse requests for overtime work that have not first received union approval.

The foregoing conditions have resulted in a veritable deadlock between the union and Teledyne: Teledyne refuses to take any employees off layoff status, and the union refuses to permit any of its production personnel to accept requests for overtime labor until such time as Teledyne removes some employees from layoff status.

The plaintiff claims that the problems engendered by the union’s refusal to permit overtime work for production personnel has caused and will continue to cause it irreparable harm; it brings this action to secure an injunction against the union to foreclose further work stoppage and requests an order to compel the union to enter into arbitration to clarify the nature of the employer’s right, if any, to schedule sporadic overtime labor under the provisions of paragraph 46.A.

On December 10, 1974, the plaintiff filed its complaint and petition for injunction; a memorandum in support of its position was filed on December 12, 1974. Pursuant to plaintiff’s request, an evidentiary hearing was held before this Court on December 13, 1974. The defendant presented its position at this hearing and subsequently filed a supplemental brief as requested by the Court. The Court is of the opinion that sufficient information has been submitted so as to warrant a decision on the merits of the dispute at this time.

II. THE PROPRIETY OF INJUNC-TIVE RELIEF

A. ) Prior Litigation.

Initially the Court would note that it is aware of the prior litigation that has occurred in this district between these parties or their predecessors in interest. Teledyne Wisconsin Motor v. International Union, United Automobile, Aerospace and Agricultural Implement Workers of America, Local 283 et al., 318 F.Supp. 557 (E.D.Wis.1970). The Court would assure the parties that that decision will be given thorough consideration when it becomes relevant to the particular issues herein presented.

B. ) The Prohibitions of the NorrisLaGuardia Act, 29 U.S.C. § 101, et seq.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
386 F. Supp. 1231, 88 L.R.R.M. (BNA) 2486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teledyne-wisconsin-motor-v-local-283-united-automobile-aerospace-wied-1975.