Teledyne Portland Forge v. Ohio Valley Gas Corp.

666 N.E.2d 1278, 1996 Ind. App. LEXIS 835
CourtIndiana Court of Appeals
DecidedJuly 2, 1996
Docket93A02-9508-EX-457
StatusPublished
Cited by3 cases

This text of 666 N.E.2d 1278 (Teledyne Portland Forge v. Ohio Valley Gas Corp.) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Teledyne Portland Forge v. Ohio Valley Gas Corp., 666 N.E.2d 1278, 1996 Ind. App. LEXIS 835 (Ind. Ct. App. 1996).

Opinion

OPINION

GARRARD, Judge.

Teledyne Portland Forge appeals a series of adverse rulings by the Indiana Utility Regulatory Commission in proceedings conducted pursuant to the Gas Cost Adjustment (GCA) statute, Ind.Code § 8-1-2-42(g). The appeals were consolidated pursuant to IndAppellate Rule 5(B).

FACTS

Beginning in the late 1970s, the federal government began to restructure the regulation of the natural gas industry. In April of 1992, the Federal Energy Regulatory Commission (FERC) issued Order 636, which was designed to complete the evolution to competition in the natural gas industry. Prior to Order 636, natural gas producers typically sold gas at regulated prices to interstate pipelines, which then resold the gas to local utilities for distribution to consumers. Thus, both the natural gas and the transportation service costs were “bundled” together in sales to the utilities. Order 636 required pipelines to “unbundle” these service costs. The purpose of Order 636 was to create competition so that all natural gas suppliers, including the pipeline merchant, would compete for gas purchasers on an equal footing, which would benefit all gas consumers by ensuring an adequate and reliable supply of natural gas at the lowest reasonable price. (Order 636 at 2, Appendix of Appellant). The implementation of Order 636 required significant alterations in the structure of interstate natural gas pipeline services, and as a result the pipelines incurred substantial “transition costs.” FERC determined that the pipelines were entitled to “full cost recovery” from their customers of all prudently incurred transition costs. (Order at 192, 200, Appendix of Appellant).

Ohio Valley Gas Corporation is a state-regulated natural gas utility and a purchaser of pipeline services. Thus, it incurred these transition costs, which are paid through FERC-regulated pipeline rates. (R. 572-75; 594—95). As a result of the increased costs, Ohio Valley filed a petition with the Commission to recover these transition costs from its own customers. The ability of Ohio Valley to recoup these transition costs from its gas customers is not in dispute, as all parties concede that these costs are proper “gas costs” under the GCA statute. However, Teledyne only purchases transportation services, and not natural gas, from Ohio Valley. The dispute is whether Ohio Valley may collect these transition costs from its transportation customers.

In order to properly understand the procedural posture of this case, it may be helpful to give context to the issues by explaining the process by which a gas utility is permitted to adjust its charges to customers to reflect fluctuations in its cost of gas without going through a complete rate change proceeding. See Indiana Gas Co. v. Office of Utility Consumer Counselor, 610 N.E.2d 865, 867 (Ind.Ct.App.1993) (hereinafter Indiana Gas III). This separate proceeding is referred to as a gas cost adjustment application and is covered by I.C. § 8-1-2-42(g). Under such a proceeding, the Commission holds a summary hearing on the sole issue of a gas cost adjustment. I.C. § 8-1-2-42(g)(1), (3). A utility may file an application within three months of its most recent application. I.C. § 8-1-2-42(g)(3). GCAs generally seek to pass through, on a dollar for dollar basis, any increase or decrease in gas cost the utility is experiencing. Indiana Gas III, 610 N.E.2d at 867. A GCA hearing is not intended to serve as a substitute for a general rate proceeding, but is rather intended to be a summary proceeding to determine gas cost adjustments. Indiana Gas Co. v. *1281 Office of Utility Consumer Counselor, 575 N.E.2d 1044, 1049 (Ind.Ct.App.1991) (hereinafter Indiana Gas I).

Ohio Valley filed its application for a gas cost adjustment on April 21,1995, requesting recovery of transition costs incurred as a result of Order 636. 1 (GCA47). Teledyne intervened in this action, and the Commission held an evidentiary hearing on June 9, 1995. It was undisputed that the tariffs for Ohio Valley’s gas customers included a provision specifically providing for GCA proceedings in order to adjust gas costs, while the tariffs for transportation customers, such as Teledyne, did not include such a provision. Thus, in order for Ohio Valley to collect transition costs from transportation customers, the transportation tariffs had to be amended. In support of its request to recover transition costs from its transportation customers, Ohio Valley presented testimony that the costs benefitted the entire natural gas industry; thus, it was fair to apportion the costs to all customers. Teledyne participated in the hearing but did not present any evidence.

The Commission issued its order in GCA47 on July 19, 1995. The Commission found that it had subject matter jurisdiction to determine gas costs and, as the “transition costs” were in fact gas costs, it could properly determine whether such costs could be recovered from transportation customers, even if an amendment to the tariff were necessary to collect the costs. The final order of the Commission in GCA47 authorized Ohio Valley to amend the tariff under which it provides service to Teledyne in order to recover a portion of the transition costs arising from Order 636.

ISSUES AND DISCUSSION

Teledyne raises the following issues in its appeal:

I.Whether the Commission acted beyond its statutory authority by ordering a tariff amendment in a GCA proceeding.
II. Whether the Commission lacked jurisdiction as a result of a deficient public notice.
III. Whether the evidence at the hearing supports the imposition of a surcharge for the collection of transition costs from transportation customers of Ohio Valley.

ISSUE I

Teledyne’s first argument is that the Commission acted beyond its statutory authority by permitting a tariff amendment in a GCA proceeding. We conclude that the Commission did have the authority under the GCA statute to reach this issue.

Teledyne asks us to review the Commission’s interpretation of its authority under I.C. 8-1-2-42(g). When we review the decision of an administrative agency, we are not bound by its interpretations of law, and we are free to determine any legal question which arises out of its decision. Indiana Gas III, 610 N.E.2d at 869. Whenever an agency interprets its own statute, we accord its interpretation great weight, but we are not bound by the agency’s interpretation and should reverse if the agency incorrectly interpreted the statute. Id.

The GCA statute provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Gypsum, Inc. v. Indiana Gas Co.
735 N.E.2d 790 (Indiana Supreme Court, 2000)
Indiana Payphone Ass'n v. Indiana Bell Telephone Co.
690 N.E.2d 1195 (Indiana Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
666 N.E.2d 1278, 1996 Ind. App. LEXIS 835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/teledyne-portland-forge-v-ohio-valley-gas-corp-indctapp-1996.