Teeples v. Tolson

207 F. Supp. 212, 1962 U.S. Dist. LEXIS 3674
District Court, D. Oregon·Decided May 22, 1962·No. Civ. 60-316·Published·Cited by 14 cases

Opinion

KILKENNY, District Judge.

Plaintiffs demand judgment against the defendant insurance company for the *213 sum of $77,455.00 with interest and attorney fees. Plaintiffs are engaged in the general construction business in the state of Oregon. Defendant and associated underwriters are engaged in the insurance business and are authorized to carry on an insurance underwriting business in the state of Oregon.

On December 7, 1959, plaintiffs signed a contract to erect a department store building in the city of Portland and thereafter commenced the construction of such building. In January 1960 defendant, in consideration of payment of a premium, issued to plaintiffs a policy of insurance with a limit of $100,000.00, the defendant intending to insure plaintiffs during the course of the construction of said building under the terms and conditions set forth in the certificate of insurance, which certificate was in full force and effect at the time of the occurrence hereinafter mentioned.

During ■ the course of construction a segment of the building collapsed due to ■defects in design and engineering in the joints of the concrete beams.

In May 1960, plaintiffs presented a ■claim to defendant for an amount in excess of the face of the policy and in June 1960, defendant paid to plaintiffs on said claim the estimated cost of repair of the units of the structure which actually collapsed and the repair of certain joints where damage was visible. After the initial collapse, plaintiffs, working with a representative of defendant, engaged the services of a new architect and engineer and he concluded that the initial design of said structure was wholly inadequate to support its weight and that a new and different design, reinforcing and changing the original, was absolutely necessary. The shoring mentioned was temporary in nature and for the time being prevented the collapse of the remainder of the «joints in question. The shoring had to be removed in order to properly utilize the floor space and when removed, the joints would collapse unless reinforced.

The parties agree that the new architect is well qualified in this field. He arrived at the conclusion that the entire structure was under-designed and could not carry the weight load which would be required.

The language on the face of the policy would indicate that it was an all risk type. 1 The language of the insuring clause is quite broad. 2 However, there is an express limitation of liability in the policy. 3 The exclusionary clause 4 *214 is quite limited in scope. The intention of the parties is declared in another portion of the policy. 5 The expert, so engaged by plaintiffs, arrived at the conclusion that it was necessary to redesign the entire building. At the time of the partial collapse, the structure was in skeleton form only, but the cost of construction to that date far exceeded the face of the policy. The redesigned structure, which was eventually completed and on which damages are claimed under the policy, contained a great amount of material and labor over and above what would be required under the original plans and the cost of such would be greatly in excess of the cost to repair all of the beams and joints, those which collapsed and those which were shored up. The original claim of the plaintiffs was as follows:

(1) Repair Beams $ 58,140.00

(2) Costs incidental to collapse and repair 8,618.00

(3) Electrical and pipe changes arising hereunder 2,000.00

(4) Welding Expenses 2,065.00

(5) Bridging Expenses 6,526.00

(6) Column remodeling and escalator framing 6;062.00

(7) Wall shearing (tentative estimate) 8,395.00

(8) Tie Roof together 15,015.00

(9) Engineering fees 8,760.00

Total $115,571.00

In the trial the estimated cost was increased by the expert to $140,000.00. However, as I look at the record, there was no breakdown in this last estimate on which a court could properly act. Damages must be proved with reasonable certainty. Parker v. Harris Pine Mills, Inc., 206 Or. 187, 205, 291 P.2d 709, 56 A.L.R.2d 382. The same rule applies to proof on the cost of repairs. The expert fixed the cost of repairing the collapsed and cracked joints at $22,795.00, which sum, less $250.00 ($22,545.00) has heretofore been paid by defendant to plaintiffs, without surrender of any rights.

It is the plaintiffs’ contention that defendant is liable under the policy, not only for the actual cost of the repair of the collapsed portion of the building, but also for the added expense of labor, material and engineering expenses under the redesign prepared by said expert. In addition, plaintiffs contend that they are entitled to a reasonable attorney fee and interest from May 7, 1960, the date of the claim.

Defendant contends that plaintiffs were paid in full for the cost of repair of any damage which actually occurred at or about the time of the partial collapse.

Free access — add to your briefcase to read the full text and ask questions with AI

Teeples v. Tolson, 207 F. Supp. 212, 1962 U.S. Dist. LEXIS 3674 (D. Or. 1962).

207 F. Supp. 212 (Teeples v. Tolson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cardone v. Boston Regional Medical Center, Inc.
800 N.E.2d 335 (Massachusetts Appeals Court, 2003)
Sentinel Management Co. v. New Hampshire Insurance Co.
563 N.W.2d 296 (Court of Appeals of Minnesota, 1997)
Witcher Construction Co. v. Saint Paul Fire & Marine Insurance Co.
550 N.W.2d 1 (Court of Appeals of Minnesota, 1996)
McNeilab, Inc. v. North River Insurance
645 F. Supp. 525 (D. New Jersey, 1986)
Shea v. BAY STATE GAS CO. CAMP DRESSER & McKEE INC.
418 N.E.2d 597 (Massachusetts Supreme Judicial Court, 1981)
Shea v. Bay State Gas Co.
383 Mass. 218 (Massachusetts Supreme Judicial Court, 1981)
United States Fidelity & Guaranty Co. v. Nevada Cement Co.
561 P.2d 1335 (Nevada Supreme Court, 1977)
Travelers Indemnity Company v. United States
543 F.2d 71 (Ninth Circuit, 1976)
Bryan Const. Co. v. EMP. SURPLUS LINES INS. CO.
281 A.2d 97 (New Jersey Superior Court App Division, 1971)
Employers Casualty Company v. Holm
393 S.W.2d 363 (Court of Appeals of Texas, 1965)